ASWL – submission timescales

If no new standards are being proposed for use on a project, it is not necessary to submit an Approved Standards and Weightings List (ASWL) to BRE Global for approval. Please note that a completed list must always be submitted as part of the report submission to the Quality Assurance (QA) team.

Where new standards are being proposed for use, the ASWL should be submitted to the BREEAM technical team at least 3 months prior to the submission of the assessment for QA. Those received at the same time as the report may result in a delay to the QA process.

BRE Global aims to review new standards within four weeks, however this may be exceeded in cases where further investigation into the applicability of proposed new standards is required. BRE Global will keep the assessor updated of the status of the review in these instances.