Speculative office including floor finishes/suspended ceiling

The requirements can still be met where a speculative development includes the installation of floor finishes/suspended ceilings provided a Lease Agreement will be implemented to confirm that tenants are not permitted to remove these finishes.

BREEAM recognises that incoming tenants may need to adapt ceiling or floor finishes to suit the requirements of their fit-out. Therefore, where these finishes are installed throughout, in line with Criterion 2, the following applies:
A tenancy agreement, applied to the first tenancy, should stipulate that floor or ceiling finishes may only be modified where necessary, for example, to accommodate new partitions, lighting or other services, to replace worn or damaged components or to replace small, localised areas with a specialist floor or ceiling to account for abnormal conditions, such as wet areas.

Documentary evidence of this must be provided as evidence for the credit to be awarded.

18/04/2017 KBCN made applicable to NC 2016 and IRFO 2015  
05/07/2018 Paragraph added to clarify the requirements of the tenancy agreement
27 Jul 2021 Clarified that the terms of paragraph 2 apply also to floor finishes