Home Quality Mark / HQM ONE / B My Home /

5 Energy

Information correct as of 19thApril 2024. Please see kb.breeam.com for the latest compliance information.

Adding rows to the Energy Reporting tool - KBCN1441

After entering the first product, fill out the row beneath it with the details of another product and a row will automatically be added.

Alternative certification schemes LZCTs options - KBCN1314

Where Microgeneration Certification Scheme (MCS) or CHPQA certification is not available, the design team must investigate the availability of alternative accreditation schemes in line with the Directives listed in the LZCT definition of the Decentralised Energy issue, or an equivalent country or regional directive or standard. Where an alternative accreditation scheme exists it should be used for the purpose of verifying compliance of the specified LZCT. If no alternative accreditation scheme exists, the design team must demonstrate they have investigated the competence of the installer selected to install the LZCT and are confident that they have the skill and competence to install the technology appropriately.

batch upload of HQM SAP XMLS - KBCN1428

There is a bulk HQM SAP xml upload feature at the start of an HQM assessment within the BREEAM Projects tool within the 'Homes' section.

Building assessed as part of a larger development - KBCN1313

Where the building under assessment forms part of a larger development and either a new or existing low or zero Carbon technology (LZCT) installation is provided for the whole site, then the amount of LZCT energy generation counted for in this issue, and subsequent CO2 emissions saved, should be proportional to the building’s energy consumption compared to the total energy consumption for the site.

Converting energy consumption into kWh/annum from new EU energy labels - KBCN1462

To convert the energy consumption from new EU energy labels into kWh/annum, the following guidance should be followed: Dishwasher: multiply kWh/100 cycles figure on EU energy label by 2.8 to get kWh/annum Washing machines and washer dryers: multiply kWh/100 cycles figure on EU energy label by 2.2 to get kWh/annum Ovens: multiply kWh/cycle figure on EU energy label by 286 to get kWh/annum
25 Aug 2023 - Correction to 'typo error' for dishwasher conversion factor - previously shown as 2.08, now corrected to 2.8

Decorative gas/ethanol fires - KBCN1301

Although fires may be decorative, if they are permanent features of the home that burn fuel to produce heat, they will have an impact on local air quality. They should be assessed in the Impact on Local Air Quality issue.

District heating connected after post-construction stage - KBCN1312

For HQM, at design stage, it may be acceptable to assume a network will be implemented and used by the assessed home, at completion if appropriate design-stage evidence demonstrates this, even if the system is not implemented at the time of the design-stage assessment. At post-construction, evidence would need to be revised and re-submitted based on what has happened in practice. In most cases the district heating network would need to have been installed and connected to, in order to use this system as part of the home’s energy calculations for the Energy and Cost issue, and to demonstrate installation of LZCTs in the Decentralised Energy issue. However, there is a possibility that time-frames could be flexible depending on the specific scenario being considered, which are judged on a case by case basis. To be considered, a technical query needs to be raised, with detailed information about the project including: location, size, whether it’s mixed-use or a phased development, type of network being connected to, time-frames of the connection and justifications for these, and the assurances that will be in place to ensure this happens in-practice. If it is not possible to provide this information during the design stage, this can be raised later but please be aware that there is a risk that credits achieved at design stage may be lost at post-construction stage, if the network is not connected to as planned. If this does happen, the ‘infrastructure’ criteria in the Decentralised energy issue may still be applicable if adequate infrastructure is installed by post-construction stage, which can be used to connect the home to LZCTs in the future, in line with any relevant criteria (e.g. feasibility study, CN4 etc.). In terms of how this works for BREEAM, it is possible that connection after post-construction could be acceptable, if the development is part of a larger or mixed-use project where the centralised services provision only becomes viable at a later phase and there are robust, legally enforceable routes to ensuring delivery of them to a set timeline. Evidence would need to be reviewed at post-construction stage on a case by case basis, in line with KBCN0267.

Heat pumps - KBCN1316

Heat pumps can only be considered as a renewable technology when used in heating mode. Refer to Annex VII of Directive 2009/28/EC for more detail on accounting for energy from heat pumps.

Heated common areas for homes - KBCN1390

A BRUKL is only required for the HQM calculation if it is already required by building control.

If heated common areas are not applicable to the assessment but the assessment tool is requesting inputs for them, please check your inputs for shared common areas in the 'Home details' and 'Energy and cost' parts of the tool.


HQM – Update to Building Regulations & SAP 10 - KBCN1553

We have incorporated the Building Regulations changes into HQM V6. HQM V6 (which has been published and is available for assessors to use) is compatible with SAP 10.  
30/10/23-Updated compliance note to confirm HQM V6 is compatible with SAP 10

Oil-fired boilers benchmarks - KBCN1293

It has come to our attention that there is an error in Table 35, relating to the NOx emission benchmarks for oil-fired boilers. The table below confirms the correct benchmarks.
Appliance type and unit Fuel 7 credits (Low pollution location) 7 credits (High pollution location) 10 credits (Low pollution location) 10 credits (High pollution location)
Boiler (mg/kWh) Oil 56 73 56 55 67 50
This will be confirmed in the next update of the technical manual, but can be applied immediately to HQM ONE projects.

When PV is connected to the communal landlord areas in a block of flats - KBCN1444

In terms of crit 4.a (There is a direct supply of energy produced to the home under assessment), where PV is connected to the communal landlord areas in a block of flats, instead of directly to individual flats, this criteria can be deemed to be met because PV wired to each individual flat would conflict from a material efficiency point of view.
Information correct as of 19thApril 2024. Please see kb.breeam.com for the latest compliance information.