New Construction / UK / 2011 / 01-Management /

Man 03 - Construction Site Impacts

Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.

Change in main contractor - KBCN0645

In situations where the main contractor changes mid-project, for example where the original contractor goes into administration and is replaced by another main contractor, it is acceptable for the post-construction credits to be awarded based on the new contractor providing information on their activities. This is providing the project is yet to start on site. This is in effect assessing the issue using the Post Construction Assessment route instead of a Post Construction Review. However, if the project has already started on site and information about the site activities of the previous contractor is not available it would not be appropriate to award the credit solely based on the new contractor activities.

Definition – Project value - KBCN0552

The term ‘project value’ represents the total project cost, which includes all costs such as construction, design, land acquisition, etc.

Environmental Checklist section 2.2.5 - KBCN0225

In May 2013 the Environment Agency updated their guidance document "Building A Better Environment" and Checklist 2.2.5 is no longer included. However, the EA have allowed the continued use of Checklist 2.2.5 from the original 2006 guidance for the purposes of demonstrating compliance with Man 03. It can be found on the extranet: Home » Extranet » BREEAM 2011 UK New Construction » BREEAM 2011 New Construction Technical Guidance » Supporting Documents  

Environmental management – no principal contractor - KBCN1213

In order to achieve compliance where there is no principal contractor, the criteria must be met by the party which fulfills an equivalent role in managing the construction. The intent of the criteria is to ensure that the site is managed in accordance with demonstrably sustainable principles by the party having overall control of site management and operations. 

Environmental management – Timing of obtaining ISO 14001/EMAS certification - KBCN0229

The contractor must be in possession of the ISO 14001/EMAS certification prior to starting works on the development under assessment. This is to ensure that the aim of the issue, to ‘encourage construction sites managed in an environmentally sound manner’, can be achieved. To uphold the robustness of BREEAM, the date of certification to ISO 14001/EMAS must be prior to initial works starting on the site.  

Evidence requirements – responsible sourcing of materials at post-construction - KBCN1599

Whilst the UK BREEAM manuals are less prescriptive in the evidential requirements to allow flexibility, to ensure consistency across the schemes, it is expected that robust evidence should be provided to verify the source of any certified materials and how the assessor has confirmed the products and manufacturers used. Evidence supplied at post construction stage must reflect the completed building and confirm the responsibly sourced materials that have been procured and installed on the project. Supporting documentation is required to validate letters of confirmation or schedules of materials. Evidence provided could include proof of purchase, for example, invoices, delivery tickets, purchase orders or correspondence from suppliers. This may be an example for each material sourced, rather than every delivery ticket for instance.  Alternatively, evidence of the use of the responsibly sourced materials may include as-built drawings, O&M documentation or site photographs.

Legally harvested and traded/Legal and sustainable timber – Reclaimed/recycled timber - KBCN0654

Timber should, wherever possible, be sourced in accordance with the UK Government’s Timber Procurement Policy. However, if for reclaimed timber the original procurement details are unobtainable, robust evidence to demonstrate it has been reclaimed can be acceptable. The government UK Government Timber Procurement Policy Timber Procurement Advice Note (6th edition) states: As an alternative to demanding timber and wood-derived products from a Legal and Sustainable source, Contracting Authorities can demand ‘recycled timber’. Documentary evidence and independent verification will also apply to recycled timber and recycled wood-derived products but will focus on the use to which the timber was previously put rather than the forest source. And defines ‘recycled timber’ as: “…recovered wood that prior to being supplied to the Contracting Authority had an end use as a standalone object or as part of a structure and which has completed its lifecycle and would otherwise be disposed of as waste. The term ‘recycled’ is used to cover the following categories: pre-consumer recycled wood and wood fibre or industrial by products but excluding sawmill co-products (sawmill co-products are deemed to fall within the category of virgin timber), post-consumer recycled wood and wood fibre, and drift wood. It also covers reclaimed timber which was abandoned or confiscated at least ten years previously.” As per the above policy, BREEAM requires “Documentary evidence and independent verification” that all reclaimed/recycled timber products meet the definition of ‘recycled timber’ given above.
01/06/2020: Amended to clarify and extended applicability to Mat 03

Pollution Prevention Guidance documents - KBCN1051

On 17 December 2015, the Pollution Prevention Guidance documents (PPGs) published by the Environment Agency were withdrawn. These can be found in the National Archives or on the Scottish Environment Protection Agency website where they are still current documents. Many BREEAM schemes and the Home Quality Mark refer to these PPG documents as they are still considered to be best practice even though they have been withdrawn. Projects should continue to use the PPGs referenced in the relevant manuals. BREEAM will continue to review this situation and provide an update as and when appropriate.
26 09 2018 Made applicable to Man 03 and Pol 03 in UK NC2018 and Man 03 in UK NC 2011, UK NC2014 and UKRFO 2014

Scope of construction works included - KBCN0642

Only the scope of works the principal contractor is responsible for needs to be considered in the assessment of this Issue. This also includes works carried out by sub-contractors that are engaged by the principal contractor.
03.11.2021 Above text added to issue 2.0 of the UK RFO technical manual. Text remains applicable to all previous issues of the manual.

Transport of construction materials – Data and methodology - KBCN0413

To ensure comparability across assessments, the information completed in the scoring and reporting tool should be restricted to the minimum data specified in the technical manual. For the purposes of this BREEAM Issue, the distances reported should be calculated from the point from which the products or materials were sourced, whether this be directly from a manufacturer or from a builders' merchant/distributor: Where products cannot be sourced locally, for example on small islands, the transport required to import the materials or products can be discounted, and only the local onward transport to the site recorded. The aim of this requirement is to encourage developers to consider the impacts of transporting products and materials to site. As such, the criteria seek to address only those impacts, which can be influenced by the developer.
27.07.2018 Wording amended to add clarity.

Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.