New Construction / International / 2013 / 02 - Health and Wellbeing /

Hea 06 - Safe Access

Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.

Areas in the public domain - KBCN0587

Where areas within the site boundary will be public domain after construction, and the design/specification has been determined by the local authority/statutory body/planning permission etc, they can be excluded from the assessment of the 'Safe Access' criteria. Evidence would be required to demonstrate that this was the case. Where the client/design team do not have control of the design of these areas, the development should not be prevented from achieving the credit.

Cyclist safe access - KBCN0188

Safe access for cyclists must be via a compliant cycle lane, unless it is demonstrated that it would be impractical to cycle for a short distance between the site entrance and cycle storage. For example, where a gate, door or barrier forces the cyclist to dismount and walk for a short distance to access the cycle storage and it would be impractical for cyclists to re-mount1. Where it is not practical to provide compliant cycle lane from the entrance to the cycle storage, the safety of cyclists and pedestrians must be maintained. 1. The intent is that this be a short distance, over which cyclists would typically not choose to re-mount and is anticipated to be no greater than 10m. In order to be considered compliant for greater distances, evidence must be provided of effective additional physical measures to deter cyclists from re-mounting.
29/09/2021 - Additional note (1) added to provide further clarification of the intent
21/02/2020 Re-worded to clarify the intent
02 Jul 2021 - Applicability to UK NC2018 confirmed
 

Dedicated cycle paths in the absence of cycle facilities - KBCN00039

Safe cycle access needs to be provided even if there are no dedicated cycle facilities. The dedicated cycle paths will generally need to be provided to the main entrance(s) of the building along routes likely to be used by cyclists through the site.  The design team are required to determine what is required to satisfy the intent of the criteria. Cycle access and cyclists' facilities are assessed independently of each other. Building users may cycle even if the building does not have cycle storage facilities and so safe and secure access to and from the building must be provided.

Restricted movement within a secure perimeter - KBCN000009

Where the movement of pedestrians, cyclists and vehicles is tightly controlled within a secure perimeter due to security considerations, these areas may be excluded from the safe access criteria. Where the whole assessment is within such a zone, the credit may be awarded by default.
08 Jun 2022 Applicability to UK NC2018 confirmed

Safe access – vehicle delivery routes - KBCN1046

Vehicle delivery routes which cross cycle or pedestrian routes may be acceptable provided there are adequate physical control measures in place to ensure safe access and thus minimise the possibility of delivery vehicles coming into conflict with cyclists and pedestrians. Examples of such measures could be vehicle barriers or retractable vehicle bollards, which only allow access to delivery vehicles when required and whose operation and controls account for cycle and pedestrian movements.
18 Mar 2021 wording clarified
07.06.2018 Intent and wording clarified.

Safe access criteria requirements for small infill developments and extensions - KBCN0810

For smaller infill developments (typically those with a total gross floor area of less than 1,000m2) where there is no opportunity to make changes to the surrounding site or access to the building itself (other than those directly related to connecting building access points to existing pathways etc.), it is recognised that full compliance with the BREEAM criteria for safe access may not be achievable.  This applies to developments where either: In such instances the existing site layout should undergo a risk assessment against the BREEAM 'Safe Access' criteria to identify areas where there is potential for enhancement across the site.  The findings should be reported to the client and design team and any non-compliant aspects should be resolved as far as practically possible within the scope of the project, however there is no express requirement to achieve full compliance in every respect.  Where the assessor is satisfied that the above requirements have been met,  the credit for 'Safe access' can be awarded.
31/03/17 Reference to achieving 'Security' credit removed

Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.