Community transport schemes in rural areas - KBCN00013

In rural areas, where scheduled public services are insufficient to gain credits via the calculation of the Accessibility Index, community transport schemes, including 'on-demand services', can be used to achieve the 'dedicated bus service' option. In such cases evidence must be provided to demonstrate:
Content reworded to highlight the availability of the on-demand service to all potential users. 24/04/2017

Cycle spaces – Folding bicycles and scooters - KBCN00024

The provision of cycle storage that is only suitable for folding bicycles or scooters is not compliant. Providing reduced storage space for folding bicycles or scooters in place of compliant cycle storage may limit future travel options.
14 03 2018 Wording clarified and reference to scooters included.

Cycle spaces – Prominent location - KBCN00053

The requirement to provide cycle storage facilities in a prominent location on site, within view of building users, is intended to encourage use through advertising their presence to building users. Providing these facilities inside the assessed building, such as in the basement, may be compliant so long as there is prominent signage to indicate their location to all building users.  

Cyclist safe access - KBCN0188

Safe access for cyclists must be via a compliant cycle lane, unless it is demonstrated that it would be impractical to cycle for a short distance between the site entrance and cycle storage. For example, where a gate, door or barrier forces the cyclist to dismount and walk for a short distance to access the cycle storage and it would be impractical for cyclists to re-mount1. Where it is not practical to provide compliant cycle lane from the entrance to the cycle storage, the safety of cyclists and pedestrians must be maintained. 1. The intent is that this be a short distance, over which cyclists would typically not choose to re-mount and is anticipated to be no greater than 10m. In order to be considered compliant for greater distances, evidence must be provided of effective additional physical measures to deter cyclists from re-mounting.
29/09/2021 - Additional note (1) added to provide further clarification of the intent
21/02/2020 Re-worded to clarify the intent
02 Jul 2021 - Applicability to UK NC2018 confirmed
 

Cyclists’ facilities – Visitors - KBCN00014

Where the cycle spaces requirement is based on the number of staff plus visitors, customers or patients, the number of cyclist facilities required to demonstrate compliance is based on the number of cycle spaces for staff only. Visitors, customers or patients would not be expected to have access to showers and lockers within a building.

Dedicated cycle paths in the absence of cycle facilities - KBCN00039

Safe cycle access needs to be provided even if there are no dedicated cycle facilities. The dedicated cycle paths will generally need to be provided to the main entrance(s) of the building along routes likely to be used by cyclists through the site.  The design team are required to determine what is required to satisfy the intent of the criteria. Cycle access and cyclists' facilities are assessed independently of each other. Building users may cycle even if the building does not have cycle storage facilities and so safe and secure access to and from the building must be provided.

Number of compliant cycle storage spaces - KBCN1016

According to BREEAM New Construction Guidance, for sites where at least 50% of the available BREEAM credits for Public transport accessibility (Tra 01) have been awarded, the provision of the number of compliant cycle spaces required in Cyclist Facilities issue (Tra 03) can be reduced by 50%. However, this reduction cannot be applied to BREEAM Communities assessments for Cyclist Facilities issue (TM 05). This is firstly to ensure comparability amongst different Communities projects, namely the ones certified prior to the release of the new BREEAM New Construction Manual. Moreover, to allow for the sequential order of BREEAM schemes which is to comply with BREEAM Communities requirements first as they will help achieve BREEAM New Construction criteria. Less cycle spaces can be designed and built at building level assessment, provided that robust evidence can demonstrate the number of cycle storage spaces committed to provide at Masteplanning stage is more than required by individual buildings.

Restricted movement within a secure perimeter - KBCN000009

Where the movement of pedestrians, cyclists and vehicles is tightly controlled within a secure perimeter due to security considerations, these areas may be excluded from the safe access criteria. Where the whole assessment is within such a zone, the credit may be awarded by default.
08 Jun 2022 Applicability to UK NC2018 confirmed

Timescales for management and maintenance responsibilities - KBCN0370

Where there are requirements for management and maintenance outputs or activities these should, as a minimum, cover a five year period following occupation of the development for the phase of development being assessed. This timeframe applies to the following management and maintenance activities: Management and maintenance activities are often fundamental in ensuring that the original sustainability measure or approach is successful over the long term.

Tram services - KBCN000004

Tram services are classified as train services when assessing transport accessibility.  
Information correct as of 24thApril 2024. Please see kb.breeam.com for the latest compliance information.