New Construction / International / 2016 / 08 - Land use and ecology /

LE 05 - Long term impact on biodiversity

Information correct as of 24thApril 2024. Please see kb.breeam.com for the latest compliance information.

Aircraft safety – developments in the proximity of airports - KBCN0912

Where it can be demonstrated that an assessed development, within or adjacent to an airport or similar, must restrict the ecological value of the site for reasons of aircraft safety (mitigating the risk of bird-strikes to meet local or national regulations), the approach for some issues in the Land Use and Ecology category can be adjusted. If in these circumstances, the client wishes to enhance ecological value on an external site, outside of the main development site, this can be considered in the following way for each issue: Site selection: The development site only must be assessed. Ecological value of site and protection of ecological features: The development site only must be assessed, but the recommendations may be tailored to suit the requirements of the relevant legislation. Enhancing site ecology: The development site and the external site must be included in the SQE’s report and recommendations, albeit that, for the development site, the approach may to be to restrict biodiversity. Enhancements implemented in-line with the recommendations of the SQE are likely to apply to the external site. Long term impact on biodiversity: Both sites must be considered in the SQE’s report to meet the prerequisite/first credit as applicable, albeit that, for the development site, the approach may to be to restrict biodiversity. Further credits in relation to improving and maintaining the site’s long-term biodiversity can be awarded on the basis of adopting these for the external site only, in line with the guidance.

GN13 Relating ecologist’s report and BREEAM - KBCN0626

Introduction This guidance note is to be used for registered BREEAM UK New Construction 2014 and RFO 2014 and International New Construction 2016 and RFO 2015 assessments, where an ecologist has been appointed by the client and has produced an ecology report for the proposed development. The purpose of this guidance note is to help the BREEAM Assessor relate the content of the ecologist’s report to the BREEAM Land Use and Ecology section criteria (assessment issues LE 02, LE 03 (UK only), LE 04 and LE 05). The guidance within this document has been produced to support the assessment of the aforementioned BREEAM issues and should not be interpreted as criteria. If the BREEAM Assessor chooses to use the template provided within this guidance note as evidence in the assessment (use of this document is optional) the assessor or the appointed suitably qualified ecologist must complete all relevant sections View full Guidance Note (licensed assessors only) View all Guidance Notes (licensed assessors only)
01/04/2020 Clarified applicability to UK RFO 2014 and International RFO 2015 schemes

Habitat management plan – Level of detail required - KBCN0132

The level of detail required in the landscape and habitat management plan needs to be commensurate with the complexity and extent of the landscaped areas. If there is a limited amount of landscaping, then a simple plan would be acceptable, commensurate with the significance of the area assessed. Where the suitably qualified ecologist, appointed prior to commencement of activities on site, confirms that a landscaping and habitat management plan is not applicable due to the nature of the site and its surroundings, such as being nearly all or entirely hardstanding or having little or no external space, then full credits can be awarded for demonstrating that the relevant legislation has been followed.

International suitably qualified professionals - KBCN1266

In some issues the International NC and RFO schemes prescribe specific requirements for suitably qualified professionals. We appreciate that some countries might have different recognition schemes in place, and these might differ from the BREEAM requirements. Where this is the case, assessors should submit a technical query with appropriate information, and we will review and approve each situation on a country basis.

Landscape and Habitat Management Plan – SQE involvement - KBCN0564

Even if not stated explicitly, it is implied and expected that the Suitably Qualified Ecologist (SQE) does verify the content of the Landscape and Habitat Management Plan to ensure that it is consistent with the whole site ecological strategy.  

Late appointment of the Suitably Qualified Ecologist - KBCN0603

If the Suitably Qualified Ecologist (SQE) is appointed after the commencement of activities on-site and if the other requirements of this issue are met, then credits can still be awarded, provided that:

Off-site ecological enhancement - KBCN0651

BREEAM does not recognise enhancements which are not within the boundary of the site being assessed, as the aims of the land use and ecology section relate to the ecological value and biodiversity of the specific site under assessment. However, off-site ecological enhancement can be accepted where: Full justification and robust evidence must be submitted when relying on this approach. BREEAM recognises that the red-line boundary drafted for planning purposes may not reflect the entire site within the control of the developer or building owner.

Shared ecological enhancements - KBCN0656

A site-wide approach to ecological enhancements can be used on sites where multiple buildings share areas of soft landscaping. The enhancement benefits are applied to the individual building assessments within the site. Similarly, where a building comprises more than one assessment, eg different floor assessments, a green roof on top of that building can be used to award credits for each assessment for which the Land use and ecology issues apply. The benefit can be applied on a site-wide basis provided all developments are completed within the appropriate timeframe of a valid ecological survey.    