In-Use / USA Commercial V6 / Part 1 /

02 - Energy

Information correct as of 26thDecember 2024. Please see kb.breeam.com for the latest compliance information.

Centralised air handling units (AHU) - KBCN0941

The requirements of the: do not apply to centralised AHUs, where it is not technically feasible to sub-meter energy use by separate functional, tenanted or floor areas. The credit(s) will be assessed based on the remaining applicable energy uses.
06-Mar-2024 - Scheme applicability extended to V6.

Clarification – access to daylight - KBCN1648

Q11 of this issue asks 'what percentage of lit asset floor area has access to daylight?' For this issue, 'access to daylight' means: Spaces daylit from the side Spaces daylit from above

Clarification – percentage of end uses - KBCN1650

This percentage is measured by the energy consumption (kWh) of significant energy uses, not by the number of end uses.

Combined sub-metering – electric space / water heating and small power - KBCN00068

For bedrooms and associated spaces in: It is acceptable for an electric space or water heating system to be combined with lighting and small power, provided that sub-metering is provided for each floor plate or other appropriate sub-division. For these asset types, sub-metering electric heating in multiple bedrooms may be costly and technically challenging. Where occupants have individual control but are not responsible for paying the utility bills, the building manager may have little influence on their energy consumption. Therefore, sub-metering electric heating would provide little or no benefit in meeting the aim of the issue.
06-Mar-2024 - Scheme applicability extended to V6. 
15-Dec-2023 - Title updated to clarify that this approach can be applied to both space heating and domestic hot water heating, where appropriate.

Combined system for heating / cooling and domestic hot water - KBCN0329

It is permissible to have combined metering for a shared on-site or district system that combines heating / cooling, and domestic hot water generation. In all cases, justification is provided in the QA report for the combined metering, and explains why it is not technically feasible to provide separate meters.
21-Sep-2022 Applicability of KBCN added to BIU V6. Amended to include district heating and cooling networks.

District heating / cooling / hot water – entering data into the Online Platform - KBCN1536

For assets which use district heating / cooling / hot water, information on the district systems are entered into Ene 09a and 09b. In Ene 05 / 06 / 09, answer 'no' to first question "Is space heating / cooling / hot water generated on-site?" then navigate to: The Online Platform differs from the manual structure, however it does not affect scoring in any way. All data entered contributes to the asset energy calculator. Assets with on-site and off-site systems Only answer questions on the system which provides the most signifcant heating or cooling to the asset. If an asset includes both on-site and off-site systems, choose the one which delivers the most energy annually.

Erratum – scope of issue - KBCN1498

Criterion 1 states: "Where external lighting or car park lighting are not necessary from a safety perspective, the associated credits can be filtered out of the assessment." What this means is: The inclusion of the word 'safety' in this criteria is misleading and will be removed in future versions.
28-Feb-2024 - Wording clarified.

Erratum – up to V6 – methodology – no default energy assumptions - KBCN1630

The scope of the issue applies only to systems with significant energy use. The methodology section states that the online platform will calculate default values, and use this to indicate which systems are in scope. This is incorrect, as default values are not automatically calculated. The energy use of each system will need to be manually estimated. This can be done based on:

Erratum – V6.0.0 – cooling efficiency parameter – EER / SEER - KBCN1560

In the asset energy calculator guidance, the parameter given for cooling efficiency is 'SEER' (Seasonal Energy Efficiency Ratio). This is incorrect and should say 'EER'. This affects the following tables:
International USA
Commercial V6.0.0 Table 19 Table 18
Residential V6.0.0 Table 16 Table 16
This will be updated in the next manual re-issue.

Installed controls – ‘Asset does not have both heating and cooling’ - KBCN1678

In the technical manual, the intent is that Q1, Q2 and Q3 allow the credits to be filtered where the asset has 'neither heating nor cooling', in line with the assessment tool. This will be updated in the next reissue of the technical manual.

Interlock controls – clarification - KBCN1491

An interlock is a control that is wired so that when there is no demand for heating / cooling in a space, the heating / cooling generator and the associated pumps are switched off. Use of thermostatic radiator valves (TRVs) alone does not provide interlock. Partial interlock means that the cooling and heating interlock controls are separate. However, the control function may be set up to minimise the possibility of simultaneous heating and cooling. Total interlock means the controls are wired so that simultaneous heating and cooling is not possible. Where there are separate local heating or cooling units present, these will also need to be wired into the control system for total interlock to avoid the possibility of simultaneous heating and cooling.

Night-time operation – requirement for controls - KBCN1048

Projects or areas of an asset which operate at night-time can adapt or omit the requirement to provide controls or presence detection to align with the building’s hours of operation. This could, for example, include service yards or car parks. The aim of this Issue is to reduce the energy use for external lighting and should not interfere with the building’s operation.
02 Oct 2024 - Updated to clarify the scope of the this guidance and applied to NC V6 and BIU.

On-site LZC – whole site shared connection - KBCN1424

To be recognised in BREEAM, the on-site Low and Zero Carbon (LZC) technology must have a direct physical connection to the assessed asset. OR Where the LZC technology is; It is acceptable to allocate the renewable energy generated proportionally as a calculation of the asset's predicted energy consumption compared to the total energy consumption of the whole site. To allocate renewable electricity by proportional consumption: Where consumption data is missing, renewable electricity must not be allocated to the assessed asset. In this case, it is assumed that all electricity consumed is sourced from the grid.
17-Jan-2024 - Applicability BIU V6 Ene 13 removed, as this approach is not applicable to assessing the area of PV fitted.
21-Dec-2022 - Applicability to In-Use V6 confirmed.

Presence detection – illuminated signs - KBCN1671

The requirements for presence detection do not apply to illuminated signs. In BIU V6, presence detection requirements are included as part of automatic energy saving controls. All other requirements in this criteria must still be met.

Scope of the criteria for lifts – Small service lifts (dumbwaiters) - KBCN1589

Small service lifts, of the type typically used to transport prepared food and crockery in restaurants (sometimes referred to as 'dumbwaiters'), fall outside the scope of this assessment issue.

Single tenant - KBCN1640

Where the assessment area is only occupied by a single tenant, the issue is not filtered out. All relevant credits apply. The criteria is designed to recognise efforts between the asset owner and tenants to coordinate sustainability policies and resource monitoring. This principle is not affected by having a single tenant, even if they might act in the role of a managing occupier.

Systems serving <10% overall floor area - other affected issues - KBCN1542

The methodology for Ene 01 states: "Heating / cooling systems can be excluded from the calculation where the heated or cooled area equates to less than 10% of overall floor area." Systems which heat or cool < 10% overall floor area are not assessed in: Ene 01, 05 and 06 all feed into the asset energy calculator and so their inputs must be consistent. All other issues relating to these excluded systems are still assessed such as:
Information correct as of 26thDecember 2024. Please see kb.breeam.com for the latest compliance information.