Refurbishment and Fit Out / International / 2015 / 01 - Management /
MAN 05 - Aftercare
Information correct as of 4thDecember 2024. Please see kb.breeam.com for the latest compliance information.
Aftercare – speculative developments - KBCN0101
For speculative projects (i.e. where the end occupiers are unknown), the Aftercare issue will be filtered out. Any relevant minimum standard will not be applicable in such cases.
Where the end-user is unknown it is not possible to demonstrate compliance with the Aftercare issue requirements.
Post Occupancy Evaluation – Bespoke - KBCN0678
It is acceptable to use a bespoke POE providing that the assessor is satisfied that the methodology covers all relevant aspects of a compliant POE. The assessor should therefore refer to the further guidance on POE provided in the BREEAM technical manual for information on what a compliant POE methodology should contain, as copied below:
- The BCO guide to Post Occupancy Evaluation (POE), British Council for Offices, 2007
- BRE Digest 478, Building performance feedback: getting started, Building Research Establishment, 2003
- Guide to Post Occupancy Evaluation Report and Toolkit, HEFCE, AUDE & University of Westminster, 2006
Seasonal commissioning evidence - KBCN0818
Where the criteria require that seasonal commissioning activities are to be completed over a minimum 12 month period following the occupation of the building, it is accepted that completed records may not be available at the time of Final Certification.
In such cases, evidence of the appointment of a seasonal commissioning manager and schedule of commissioning responsibilities which fulfils the BREEAM criteria are acceptable to demonstrate compliance.
Seasonal commissioning of Solar Photovoltaics (PV) - KBCN0244
Solar PVs can be excluded from the requirements for seasonal commissioning. This is because commissioning at a particular time of the year will not affect the original commissioning of the system.
Submitting aftercare & post occupancy evaluation data - KBCN0589
Where credits have been awarded which require post-occupancy evaluation or an element of aftercare data collection (according to scheme requirements) from the building once operational and occupied, the data gathering must take place at the specified time and the findings reported to BRE.
The timing of this evidence gathering depends on the criteria of the BREEAM scheme having been undertaken. However, for all schemes, once the evidence is due for submission, it should be sent to
[email protected] with the following title;
'
BREEAM Assessment Type Building Data
BREEAM Assessment Reference'
For example, a BREEAM 2011 New Construction assessment would use the following title when submitting their evidence;
'BREEAM NC 2011 Building Data BREEAM-1234-5678'
This KBCN replaces KBCN0695 for HQM.
Information correct as of 4thDecember 2024. Please see kb.breeam.com for the latest compliance information.