Aircraft safety – developments in the proximity of airports - KBCN0912
Where it can be demonstrated that an assessed development, within or adjacent to an airport or similar, must restrict the ecological value of the site for reasons of aircraft safety (mitigating the risk of bird-strikes to meet local or national regulations), the approach for some issues in the Land Use and Ecology category can be adjusted. If in these circumstances, the client wishes to enhance ecological value on an external site, outside of the main development site, this can be considered in the following way for each issue:
Site selection: The development site only must be assessed.
Ecological value of site and protection of ecological features: The development site only must be assessed, but the recommendations may be tailored to suit the requirements of the relevant legislation.
Enhancing site ecology: The development site and the external site must be included in the SQE’s report and recommendations, albeit that, for the development site, the approach may to be to restrict biodiversity. Enhancements implemented in-line with the recommendations of the SQE are likely to apply to the external site.
Long term impact on biodiversity: Both sites must be considered in the SQE’s report to meet the prerequisite/first credit as applicable, albeit that, for the development site, the approach may to be to restrict biodiversity. Further credits in relation to improving and maintaining the site’s long-term biodiversity can be awarded on the basis of adopting these for the external site only, in line with the guidance.
Role of the SQE in planning and measures on-site - KBCN1372
The main role of the Suitably Qualified Ecologist for 'planning and measures on-site' is to make recommendations in their Preliminary Ecological Appraisal. It is important that these are incorporated into the project’s scheduling, management and resources and that ultimately, they are implemented in practice. The person coordinating this does not need to be the SQE, as long as this individual has the appropriate level of authority to take the relevant actions and the methodology is followed. At post-construction stage, evidence needs to demonstrate these measures are implemented in practice, through site visits and appropriate evidence. In some cases, the SQE may need to be involved themselves in checking their recommendations are implemented for certain measures, if they consider this is required. However, if this is required, it would be up to the SQE to confirm in their Preliminary Ecological Appraisal.