New Construction / NOR / 2016 / 09 - Pollution /
POL 03
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.
Adoption of road in the development - KBCN0331
Where a development includes roads, these are often adopted by a statutory authority (for example the Highways agency or the local authority in the UK).
Where the authority will be taking responsibility for the roads, the following guidance should be followed to determine if the water run-off from the roads needs to be considered as part of the assessment:
- If the road drainage system bypasses the new development's network to connect directly to the local drainage network, then the water running off from the roads does not need to be considered for this assessment. Evidence will need to be provided to demonstrate if this is the case.
- If the road drainage system connects to the development drainage network before connecting to the local drainage network, then the water run off from the roads must be considered for the assessment.
Where the authority will NOT be taking responsibility for the roads, the BREEAM criteria should be followed for all drainage on site.
Flood risk – Site situated across numerous flood zones - KBCN0532
Where a site is situated across more than one flood zone, the flood zone with the highest probability of flooding, i.e. the worst case scenario, must be considered for the purpose of the BREEAM assessment. An exception to this would be where the areas in the higher probability zone include only soft landscaping and it can be demonstrated that access to the building will be maintained in a flooding event.
This is to ensure that the site has adequately managed the worst case scenario level of flood risk associated with the site's location.
22/07/2022 Applicability to HQM One confirmed
07/03/2018 Updated to include circumstances where an exception may apply.
Greenfield/Brownfield site – Definition - KBCN1259
For the purposes of this Issue, the following definitions apply:
Greenfield site
A site which has never been built on, includes minimal development or which has been substantially cleared of all buildings and associated fixed surface infrastructure* and has subsequently remained undisturbed for five years or more.
* Typically, the site includes less than 5% residual development by area.
This supersedes the definition of 'Greenfield' for this Issue in the technical manual.
Brownfield site
Any site which does not fall within the above definition of 'Greenfield site'
Minimising water course pollution – no water courses present - KBCN0550
The credit for 'minimising water course pollution' has to be assessed even in cases where no water courses are in close vicinity to the site under assessment. This is because the aim of this credit is to encourage developments to minimise water course pollution by restricting the discharge of potentially contaminated water from entering the public sewer.
Minimising water course pollution does not focus on water directly entering water courses.
Surface water run-off – no change in impermeable area - KBCN1212
CN 3.9 states: "Where the man-made impermeable area draining to the watercourse (natural or municipal) has decreased or remains unchanged post-development, the peak and volume rate of run-off requirements for the surface water run-off credits will be met by default… In this instance a flood risk assessment must be carried out and any opportunities identified to reduce surface water run-off are implemented."
Where the flood resilience credits are not being targeted, a flood risk assessment is not required. Instead, a separate study identifying opportunities to reduce surface water run-off may be carried out, and the measures implemented.
Where there is no change in impermeable area, opportunities should be identified to reduce run-off. It is not necessary to carry out a flood risk assessment to fulfill the intent of this criteria.
Surface water run-off not flooding property - KBCN0565
Where parts of a site may flood in the event of local drainage system failure, it is still possible to demonstrate compliance if the building itself will not be at risk of flooding.
Watercourse pollution from indoor parking - KBCN0545
If the design team can demonstrate that there will be absolutely no run-off from the indoor parking then the intent of the credit will be met. However, such proof would also have to demonstrate that no hydrocarbon spillage from vehicles found its way into the watercourse/sewer. It is likely that there would be water ingress from outside or that internal parking areas would have drains fitted and be cleaned regularly. In such conditions, the criteria are still applicable.
The intent of this criteria is to ensure no hydrocarbons run off to any watercourse.
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.