Changing the project scope (Fully fitted/Shell Only/Shell & Core) between Design Stage certification and Post Construction Review - KBCN0990

The Post Construction Review (PCR) must reflect the Design Stage (DS) in all aspects. If anything changes in terms of the scheme, version, building type, functions, scope, size between DS certification and PCR, then the project cannot have a PCR and would need to be registered as a new Post Construction Assessment (PCA). Therefore if a Shell only/Shell and core project has been certified at the DS, this cannot be changed to Fully fitted at PCR and should go through a PCA. However, only in this specific situation, where it changes from Fully Fitted to Shell and vice versa, the DS registration can be used to submit a PCA. Submitting a PCA against the DS registration will supercede the DS certification and the certificate will be re-issued as a PCA. This will incur the PCA certification fee. Any other changes between DS certification and PCR will need to be registered as a new assessment and can be submitted as a PCA. Queries regarding registrations and PCRs can be directed to the BREEAM Registration team.

Evidence – Photographs not permitted for security reasons - KBCN0389

Where photographs are not permitted during a site visit for security reasons, in addition to any alternative evidence requirements listed in the Schedule of Evidence for each issue, the assessor will also need to provide a detailed site inspection report and/or as-built drawings (where permitted by the client). If following this approach, full justification and documentary evidence from the client will be required for QA purposes.

Evidence: Final design/’as-built’ drawings as evidence - KBCN0393

Where drawings are not clearly marked to indicate their 'as-built' status, additional evidence would need to be provided by the design team to confirm the drawings represent the completed development and that there have been no changes relevant to the BREEAM/HQM assessment. This could, for example, be a written confirmation from the architect or the contractor, as appropriate.

Evidence: Post construction assessment evidence - KBCN0407

For the purposes of robustness and completeness, both design AND post-construction stage evidence is required for a post construction assessment. However, it is possible to provide only post construction stage (PCS) evidence where it is clear that this completely supersedes the design stage (DS) evidence and renders it unnecessary.

Shell & core project: Completing as fully-fitted - KBCN0394

It is possible to complete an assessment as fully fitted following a design stage certification as a shell & core project. Whilst the assessment will reference much of the same evidence gathered for design stage, it must be re-registered and may be submitted as a fully-fitted Post-construction assessment.
17/04/18 Wording clarified