New Construction / UK / V6 / 03 Energy /

Ene 04 - Low carbon design

Information correct as of 13thMarch 2025. Please see kb.breeam.com for the latest compliance information.

On-site LZC – whole site shared connection - KBCN1424

To be recognised in BREEAM, the on-site Low and Zero Carbon (LZC) technology must have a direct physical connection to the assessed asset. OR Where the LZC technology is; It is acceptable to allocate the renewable energy generated proportionally as a calculation of the asset's predicted energy consumption compared to the total energy consumption of the whole site. To allocate renewable electricity by proportional consumption: Where consumption data is missing, renewable electricity must not be allocated to the assessed asset. In this case, it is assumed that all electricity consumed is sourced from the grid.
17-Jan-2024 - Applicability BIU V6 Ene 13 removed, as this approach is not applicable to assessing the area of PV fitted.
21-Dec-2022 - Applicability to In-Use V6 confirmed.
24-Aug-2022 - Applicability to UKNC V6 confirmed.

Quantifying the reduced total energy demand and CO2 emissions resulting from passive design measures - KBCN1677

Please note that in order to demonstrate the reductions from passive design measures, the notional building figures may be taken from the energy model to confirm the building without passive design measures, to compare against the actual building figures, which will include passive design measures.  A separate energy model is therefore not necessarily required for the building without passive design measures.
Information correct as of 13thMarch 2025. Please see kb.breeam.com for the latest compliance information.