Change in main contractor - KBCN0645
In situations where the main contractor changes mid-project, for example where the original contractor goes into administration and is replaced by another main contractor, it is acceptable for the post-construction credits to be awarded based on the new contractor providing information on their activities. This is providing the project is yet to start on site. This is in effect assessing the issue using the Post Construction Assessment route instead of a Post Construction Review.
However, if the project has already started on site and information about the site activities of the previous contractor is not available it would not be appropriate to award the credit solely based on the new contractor activities.
Considerate construction – corporate registration - KBCN0905
Where credits are awarded for the assessment of the site against a compliant scheme, corporate registration, which assesses the contractor's overall operations and performance across multiple sites, is not in itself recognised.
To award considerate construction credits, BREEAM requires the assessment of the specific assessed development, in line with the criteria.
Responsible construction practices – Multiple contractors on the same project - KBCN0352
It is the site that must comply with BREEAM issues rather than any individual contractor. Several different contractors may have obligations to meet compliance criteria. One of the contractors and/or site managers may have responsibility for ensuring compliance during site operations. It is ultimately the client/project team's responsibility to determine and demonstrate compliance.