Change in main contractor - KBCN0645

In situations where the main contractor changes mid-project, for example where the original contractor goes into administration and is replaced by another main contractor, it is acceptable for the post-construction credits to be awarded based on the new contractor providing information on their activities. This is providing the project is yet to start on site. This is in effect assessing the issue using the Post Construction Assessment route instead of a Post Construction Review. However, if the project has already started on site and information about the site activities of the previous contractor is not available it would not be appropriate to award the credit solely based on the new contractor activities.