New Construction / International / V6 /

01 - Management

Information correct as of 20thAugust 2026. Please see kb.breeam.com for the latest compliance information.

Aftercare – speculative developments - KBCN0101

For speculative projects (i.e. where the end occupiers are unknown), the Aftercare issue will be filtered out. Any relevant minimum standard will not be applicable in such cases. Where the end-user is unknown it is not possible to demonstrate compliance with the Aftercare issue requirements.  

BREEAM AP – Achieving the design credit at the Post Construction Assessment - KBCN0215

Where a project will be undertaking a post construction stage assessment only (no interim assessment), to demonstrate that the criteria were met at the design stage a "BREEAM credit monitoring report" should be provided when the assessment is submitted, which shows that at the design stage of the project the building was still on target for the proposed BREEAM rating. This could be an excel document showing the issues that the design is on target for achieving with a short summary of how the BREEAM AP is steering the project for the correct rating. As long as the criteria are met and the correct information can be gathered for your evidence, a design stage certification is not required.

BREEAM AP – Change of BREEAM APs/Sustainability champions during project - KBCN0295

Whilst it would generally be preferable to retain the same individual in the role of BREEAM AP/Sustainability champion throughout the design and construction of a particular project for the purposes of continuity, we appreciate that this may not always be feasible. It is therefore entirely appropriate that the three credits available for using BREEAM APs/Sustainability champions can still be awarded where the individual performing the role changes (provided the ongoing involvement of an AP/SC is maintained in accordance with the criteria).  

BREEAM AP/Sustainability Champion appointment timing - KBCN0738

It is acceptable for the BREEAM AP/Sustainability Champion to be appointed later than the required stage, if it can be demonstrated that the AP/Sustainability Champion was appointed at the earliest appropriate time in the project and that the late involvement will not have a detrimental effect on the setting of BREEAM performance targets that need to be formally agreed no later than the concept design stage.

Capital cost reporting and LCC measured area - KBCN0438

When assessing the Capital cost reporting and the LCC credits, the area to be considered should be the Gross Internal Floor Area (GIFA), according to the below RICS definition: Gross Internal Floor Area Gross Internal Floor Area is the area of a building measured to the internal face of the perimeter walls at each floor level, which includes: And excludes:
14.02.18 - KBCN content amended to extend the applicability to LCC and to refer to GIFA rather than GEA, to reflect current industry practice.

Certificate validity – EMS - KBCN1401

The requirement for the principal contractor to operate an EMS relates to the duration of operations on site. Therefore, certification against ISO 14001/EMAS must be valid as above and cannot be expired, pending or applied retrospectively.

Change in main contractor - KBCN0645

In situations where the main contractor changes mid-project, for example where the original contractor goes into administration and is replaced by another main contractor, it is acceptable for the post-construction credits to be awarded based on the new contractor providing information on their activities. This is providing the project is yet to start on site. This is in effect assessing the issue using the Post Construction Assessment route instead of a Post Construction Review. However, if the project has already started on site and information about the site activities of the previous contractor is not available it would not be appropriate to award the credit solely based on the new contractor activities.

Commissioning – evidence - KBCN1099

Where the criteria require that seasonal commissioning activities are to be completed over a minimum 12 month period following the occupation of the building, it is accepted that completed records may not be available at the time of Final Certification. In such cases, evidence of the appointment of a seasonal commissioning manager and schedule of commissioning responsibilities which fulfils the BREEAM criteria are acceptable to demonstrate compliance.

Commissioning – Monitor and specialist commissioning manager - KBCN00051

The commissioning monitor is typically a project team member who will monitor the systems commissioning and testing programme for the building. The individual may combine that role with that of the specialist commissioning manager to deal with complex systems if they have the necessary knowledge. However, if the building has several specialist systems it is unlikely that the same person would be able to carry out all of the commissioning and more than one specialist would most likely be required.

Commissioning – Role of the specialist commissioning manager - KBCN0604

The specialist commissioning manager for a complex system will generally be be a specialist contractor. They must provide independent design review, oversee the commissioning and independently verify the work carried out by the installer, in line with the criteria. It may be possible for the specialist commissioning manager to be part of the principal contractor's organisation, provided it is demonstrated that they are independent of the design and installation and that any potential conflict of interest has been managed.
22 Nov 2021 - Wording updated to clarify the intent.

Considerate construction – corporate registration - KBCN0905

Where credits are awarded for the assessment of the site against a compliant scheme, corporate registration, which assesses the contractor's overall operations and performance across multiple sites, is not in itself recognised. To award considerate construction credits, BREEAM requires the assessment of the specific assessed development, in line with the criteria.

Considerate construction: Checklist A1 – Photo card identification - KBCN1632

Checklist A1 Reference 4.e. requires the following: 'Operatives’ identification; all operatives to be provided with a photo identification clip card' However, since this was introduced into 'considerate construction' requirements, data protection legislation and expectations around privacy have progressed. This requirement can, therefore, be disregarded.

Considerate constructors exemplary criteria - KBCN0843

Where the exemplary criterion has been met, the exemplary credit will be awarded in addition to the two standard credits for considerate construction. There is no need for the assessor to demonstrate compliance with the standard credits in this case, just the exemplary one.  

Definition – Critical value - KBCN1006

Critical value aims to maximise whole life value of the building based on client requirements, and differs from minimising life cycle cost. This is a more specific analysis of how the building's ongoing maintenance and operation can impact business needs. For instance:  

Definition – Project value - KBCN0552

The term ‘project value’ represents the total project cost, which includes all costs such as construction, design, land acquisition etc.

Design team meetings via conference call - KBCN0201

Design team meetings can be conducted via conference calls.

Conference calls may provide a more convenient and sustainable way to conduct meetings. 


Elemental LCC and options appraisal timing - KBCN1889

The elemental LCC should be undertaken as part of the strategic options appraisal process and used to inform the selection of significant building elements and systems, such as the structure, envelope and building services. Completing the options appraisal after key design decisions have been finalised may reduce its effectiveness and limit the opportunity for the findings to influence the final design. However, the timing requirement can still be met, where the assessor agrees that there is a justification for the appraisal continuing into early AIA Stage 2 - Schematic Design (or equivalent), and clear evidence to demonstrate that: In all cases, the outline elemental LCC plan and identification of relevant project options must be completed by the end of Concept Design

Environmental management – no principal contractor - KBCN1213

In order to achieve compliance where there is no principal contractor, the criteria must be met by the party which fulfills an equivalent role in managing the construction. The intent of the criteria is to ensure that the site is managed in accordance with demonstrably sustainable principles by the party having overall control of site management and operations. 

Environmental management – Timing of obtaining ISO 14001/EMAS certification - KBCN0229

The contractor must be in possession of the ISO 14001/EMAS certification prior to starting works on the development under assessment. This is to ensure that the aim of the issue, to ‘encourage construction sites managed in an environmentally sound manner’, can be achieved. To uphold the robustness of BREEAM, the date of certification to ISO 14001/EMAS must be prior to initial works starting on the site.  

Fabric testing and inspection in hot climates - KBCN0790

The requirements for thermographic survey and air tightness testing are applicable to both, cold and hot climates. A suitably qualified professional will advise on the appropriate testing conditions and specific methods in order to address this issue in different climatic conditions. Building fabric air tightness is important in different climates in order to ensure than no additional energy is consumed due to increased heating or cooling demand originating from the lack of integrity of the building fabric.

FSC and PEFC Mixed Sources certified timber - KBCN00091

Products labelled: Meet the BREEAM responsible sourcing requirements. This means any such products: Products carrying the FSC Mix label contain at least 70% FSC certified and recycled material. These products may contain a small proportion of FSC Controlled Wood (KBCN00054). However for BREEAM compliance, the FSC Mix label is sufficient to meet our requirements.
14-Mar-2024 - Wording clarified and expanded. Relevant prerequisites and requirements clarified. Scheme applicability updated.

FSC Controlled Wood - KBCN00054

The FSC Controlled Wood label minimises the risk that wood comes from illegal or controversial sources, however it does not eliminate this risk. Therefore, products which are: Do not meet the BREEAM definition of responsibly sourced. Where FSC Mix labelled products contain FSC Controlled Wood, see KBCN00091. This means that any such products:
14-Mar-2024 - Wording clarified and expanded. Relevant prerequisites and requirements clarified. Scheme applicability updated.

Legally harvested and traded timber – Examples - KBCN0956

The following examples are considered compliant for BREEAM purposes. Legally harvested:
  1. Evidence of compliance with the CPET (see here, timber bought inside the UK only)
  2. FSC, PEFC or SFI certification
  3. Evidence of compliance with the EUTR (timber bought inside the EU only)
  4. ASTM D7612-21 (projects in USA and Canada)
  5. Risk assessment/due diligence documentation demonstrating a low risk of non-compliance with the ‘legally harvested’ requirements given in the manual.
Legally traded:
  1. Evidence of compliance with the CPET (see here, timber bought inside the UK only)
  2. FSC, PEFC or SFI certification
  3. ASTM D7612-21 (projects in USA and Canada)
  4. Risk assessment/due diligence documentation demonstrating a low risk of non-compliance with the ‘legally traded’ requirements given in the manual.
17-Dec-2025 Reference to ASTM D7612-21 added

Legally harvested and traded/Legal and sustainable timber – Reclaimed/recycled timber - KBCN1402

As an alternative to virgin timber and wood-derived products from a Legally harvested and traded timber/Legal and Sustainable source, ‘recycled timber’ is acceptable. For the purposes of these prerequisites, ‘recycled timber’ is defined by BREEAM as: Recovered wood that prior to being supplied to the assessed project had an end use as a standalone object or as part of a structure and which has completed its lifecycle and would otherwise be disposed of as waste. The term ‘recycled’ is used to cover the following categories: pre-consumer recycled wood and wood fibre or industrial by products but excluding sawmill co-products (sawmill co-products are deemed to fall within the category of virgin timber), post-consumer recycled wood and wood fibre, and drift wood. It also covers reclaimed timber which was abandoned or confiscated at least ten years previously. BREEAM requires documentary evidence that all reclaimed/recycled timber products meet the definition of ‘recycled timber’ given above.

Life cycle cost – Multiple assessments on the same site - KBCN000003

Where there are multiple assessments on a site and a single life cycle cost (LCC) plan will be carried out, it is acceptable to use this plan as evidence provided that the results of the LCC plan can be applied to all of the assessed buildings and therefore may have a positive influence on the material specification of such buildings. Where the design of some assessments differ to the extent that the LCC plan cannot reasonably be applied, a separate LCC plan is necessary to achieve credits for this issue. Where multiple assessments are covered under a single LCC plan, there must be sufficient detail for each building to enable them to be adequately assessed. 

Meeting the minimum standard requirement – compliance when chain of custody is broken - KBCN1816

Where there is a broken chain in the last link between the purchase and delivery of certified timber from the supplier and the forwarding distribution of the timber to the site under assessment, such as where the timber has been delivered to a subcontractor or fabricator’s premises instead of direct to site (e.g. as part of a bulk order or where limited storage is available on site), compliance can still be achieved if a documented risk assessment confirms that there is low risk of mixing or substitution of certified and non-certified timber. Ways to demonstrate compliance: A. Verification that the subcontractor or fabricator only purchases and uses certified timber. There must be robust mechanisms in place to verify that all timber materials purchased and delivered originate from sustainably managed sources. This includes maintaining documented timber procurement policies and procedures that mandate certified timber orders and delivery checks. Comprehensive supplier details should be readily accessible for review upon request to demonstrate that all timber is certified. B. Where non-certified timber is handled/stored or sourced, that there are robust control measures in place to prevent any substitution or mixing of certified and non-certified timber at every stage of the process. Documentation demonstrating compliance should be maintained and made available upon request. Examples of appropriate control measures are listed below:
Control
Evidence required
Purchasing records All purchase orders, requisition notes, and contracts must explicitly specify the product details and confirm that materials are to originate from legal and sustainable sources.

Segregated storage of timber

Site layout map, stock control processes and records to confirm that certified timber is stored away from non-certified timber.
Segregated delivery of timber to site - All timber must be thoroughly inspected and verified before shipment to confirm that it is correctly marked/labelled as FSC/PEFC-certified. - Delivery notes must be accurately maintained. - A second-party verification process to check tickets and stock, must be carried out upon site delivery to confirm certified status of timber.
Documentation Comprehensive documentation must enable independent assessors to trace any timber back to its sustainable source. This includes maintaining purchase records, goods-inward notices, stock records, and sales documentation such as orders and invoices.
The above is guidance and should not replace any local or national requirements for the sourcing of legally traded and harvested timber.
1 June 2026 - Updated to apply to New Construction and RFO Schemes

Post Occupancy Evaluation – Bespoke - KBCN0678

It is acceptable to use a bespoke POE providing that the assessor is satisfied that the methodology covers all relevant aspects of a compliant POE. The assessor should therefore refer to the further guidance on POE provided in the BREEAM technical manual for information on what a compliant POE methodology should contain, as copied below:

Prerequisite – Reused temporary site timber - KBCN1769

Timber formwork or scaffold boards, that are being reused and are verified as such, can be excluded from the criteria. It is more sustainable to reuse existing timber than to potentially promote the use of virgin timber just to ensure responsible sourcing paperwork is available, which may be logistically hard to obtain for reused timber.

Project budget - KBCN0893

The project budget is required as evidence to demonstrate that an amount of money has been set aside for the commissioning and testing programme, responsibilities and criteria. It is appreciated that, for confidentiality issues, the principal contractor might not be willing to the project's overall budget with all stakeholders. In such cases, compliance with this requirement will be met where it is clearly demonstrated that the costs related to sustainability measures, which may involve members of the design team, have been included in the overall budget. A wish-list that will later be value-engineered out of the project will not be deemed acceptable. The costs relating to sustainability measures included in the brief must be costed.

Responsible construction practices – Multiple contractors on the same project - KBCN0352

It is the site that must comply with BREEAM issues rather than any individual contractor. Several different contractors may have obligations to meet compliance criteria. One of the contractors and/or site managers may have responsibility for ensuring compliance during site operations. It is ultimately the client/project team's responsibility to determine and demonstrate compliance.

Scope of construction works included - KBCN0642

Only the scope of works the principal contractor is responsible for needs to be considered in the assessment of this Issue. This also includes works carried out by sub-contractors that are engaged by the principal contractor.

Seasonal commissioning of Solar Photovoltaics (PV) - KBCN0244

Solar PVs can be excluded from the requirements for seasonal commissioning. This is because commissioning at a particular time of the year will not affect the original commissioning of the system.

Stakeholder consultation – Building occupier unknown - KBCN0227

Where the building occupier is unknown, it is still possible to achieve the credit. The end user requirements must be assumed and considered by other project parties (e.g. client, design team, etc.) using their experience and judgement until such time as the occupier is known.  

Stakeholder consultation – Existing shared facilities - KBCN0360

The consultation must include any existing shared facilities relied on to achieve compliance as well as the new facilities. To ensure the shared existing facilities are appropriate and in line with the users' requirements.  

Submitting aftercare & post occupancy evaluation data - KBCN0589

Where credits have been awarded which require post-occupancy evaluation or an element of aftercare data collection (according to scheme requirements) from the building once operational and occupied, the data gathering must take place at the specified time and the findings reported to BRE. The timing of this evidence gathering depends on the criteria of the BREEAM scheme having been undertaken. However, for all schemes, once the evidence is due for submission, it should be sent to BREEAM@bre.co.uk with the following title; 'BREEAM Assessment Type Building Data BREEAM Assessment Reference' For example, a BREEAM 2011 New Construction assessment would use the following title when submitting their evidence; 'BREEAM NC 2011 Building Data BREEAM-1234-5678'
This KBCN replaces KBCN0695 for HQM.

Testing and inspecting building fabric – Untreated spaces - KBCN0972

Untreated spaces, which are not subject to compliance with statutory energy performance regulations, can be excluded from the scope of the 'Testing and inspecting building fabric/thermographic survey/air pressure testing' criteria.    

Testing and inspecting the building fabric – Shell Only - KBCN0573

For Shell Only assessments with spaces which are intended to be treated post-assessment, imposing the requirement for a thermographic survey on a future user is not acceptable, as it may be difficult and unreasonable to expect them to remediate any defects revealed by the survey. Therefore the credit is still applicable even if building services have not yet been fitted. While we appreciate that it may be more challenging to achieve this credit for a shell only assessment compared to shell and core and fully fitted buildings, please note that the credits within the Management category do have a higher weighting for shell only assessments and there are also fewer credits applicable. Therefore each credit in the management category is worth more, as a percentage of the final score, than they are for shell and core / fully fitted buildings. This, therefore, helps to justify any potential additional burden felt by shell only assessments for this credit.

Thermographic survey – Seasonal constraints - KBCN00031

Where seasonal constraints prevent the thermographic survey from being completed prior to certification at the post construction stage, the requirements can be satisfied with: Thermographic surveys are designed to map the thermal efficiency of buildings and to detect areas where there are breaches in the thermal envelope. Surveys need to be conducted when temperature differences between the external areas of the building and surrounding air can be detected after the envelope is sealed. There may will be instances where the survey cannot be done before certification after the envelope is sealed and as such, the survey would take place after certification. 

Transport of construction materials – Data and methodology - KBCN0413

To ensure comparability across assessments, the information completed in the scoring and reporting tool should be restricted to the minimum data specified in the technical manual. For the purposes of this BREEAM Issue, the distances reported should be calculated from the point from which the products or materials were sourced, whether this be directly from a manufacturer or from a builders' merchant/distributor: Where products cannot be sourced locally, for example on small islands, the transport required to import the materials or products can be discounted, and only the local onward transport to the site recorded. The aim of this requirement is to encourage developers to consider the impacts of transporting products and materials to site. As such, the criteria seek to address only those impacts, which can be influenced by the developer.
27.07.2018 Wording amended to add clarity.

Information correct as of 20thAugust 2026. Please see kb.breeam.com for the latest compliance information.