Travel Plan – Confirmation of timing requirement - KBCN1665

The criteria require that 'a travel plan has been developed as part of the feasibility and design stages'. To clarify: Ideally, this will be completed and shared with the project team before the end of Concept Design Stage, so that sustainable transport options can be considered in the built form of the development. However, in all cases, it must be demonstrated that the Travel Plan was undertaken at an appropriate stage in the design development to influence decisions on implementing sustainable transport measures.    