Pre-refurbishment/demolition audit – late development - KBCN0537

Where the pre-refurbishment/demolition audit has not been done at RIBA stage 2/Concept Design, as required in the criteria, the credit can still be achieved. Robust evidence must be provided confirming that the timing of the pre-refurbishment/demolition audit has not compromised its ability to influence the design, consideration of materials re-use and the setting of targets for waste management. Evidence must demonstrate that this allowed decisions to be made before the start of strip-out/demolition works.