New Construction / NOR / V6 /

01 - Management

Information correct as of 9thMay 2025. Please see kb.breeam.com for the latest compliance information.

BREEAM Advisory Professional (AP) – Retrospectively applying AP status - KBCN1080

The AP status cannot be applied retrospectively. The purpose of using an AP on a project is that they can advise and steer the development from the outset to maximise its BREEAM and sustainability performance for the least cost/risk. If early AP appointment and involvement does not occur then the aims and criteria of this BREEAM issue are not being met.

BREEAM AP – Achieving the design credit at the Post Construction Assessment - KBCN0215

Where a project will be undertaking a post construction stage assessment only (no interim assessment), to demonstrate that the criteria were met at the design stage a "BREEAM credit monitoring report" should be provided when the assessment is submitted, which shows that at the design stage of the project the building was still on target for the proposed BREEAM rating. This could be an excel document showing the issues that the design is on target for achieving with a short summary of how the BREEAM AP is steering the project for the correct rating. As long as the criteria are met and the correct information can be gathered for your evidence, a design stage certification is not required.

BREEAM AP – Change of BREEAM APs/Sustainability champions during project - KBCN0295

Whilst it would generally be preferable to retain the same individual in the role of BREEAM AP/Sustainability champion throughout the design and construction of a particular project for the purposes of continuity, we appreciate that this may not always be feasible. It is therefore entirely appropriate that the three credits available for using BREEAM APs/Sustainability champions can still be awarded where the individual performing the role changes (provided the ongoing involvement of an AP/SC is maintained in accordance with the criteria).  

Certificate validity – EMS - KBCN1401

The requirement for the principal contractor to operate an EMS relates to the duration of operations on site. Certification against ISO 14001/EMAS must be valid at the Design Stage and Post Construction Stage submissions and cannot be expired, pending or applied retrospectively.
07/05/2021: Clarification on Design and Post Construction Stage added

Definition – Critical value - KBCN1006

Critical value aims to maximise whole life value of the building based on client requirements, and differs from minimising life cycle cost. This is a more specific analysis of how the building's ongoing maintenance and operation can impact business needs. For instance:  

Design team meetings via conference call - KBCN0201

Design team meetings can be conducted via conference calls.

It can be difficult for design team members to be in the same place at the same time. Conference calls are a more sustainable way to conduct meetings. 


Environmental management – Timing of obtaining ISO 14001/EMAS certification - KBCN0229

The contractor must be in possession of the ISO 14001/EMAS certification prior to starting works on the development under assessment. This is to ensure that the aim of the issue, to ‘encourage construction sites managed in an environmentally sound manner’, can be achieved. To uphold the robustness of BREEAM, the date of certification to ISO 14001/EMAS must be prior to initial works starting on the site.  

Erratum – Commissioning and handover – Shell only assessments - KBCN1591

There is an error in the assessment scope of Man 04 under Shell only. 'Ref 1.1' does not apply to Shell only assessments This will be corrected in the next re-issue

Life cycle cost – Multiple assessments on the same site - KBCN000003

Where there are multiple assessments on a site and a single life cycle cost (LCC) plan will be carried out, it is acceptable to use this plan as evidence provided that the results of the LCC plan can be applied to all of the assessed buildings and therefore may have a positive influence on the material specification of such buildings. Where the design of some assessments differ to the extent that the LCC plan cannot reasonably be applied, a separate LCC plan is necessary to achieve credits for this issue. Where multiple assessments are covered under a single LCC plan, there must be sufficient detail for each building to enable them to be adequately assessed. 

Responsible construction management – corporate registration - KBCN1084

Where credits are awarded for the assessment of the site against a compliant scheme, corporate registration, which assesses the contractor's overall operations and performance across multiple sites, is not in itself recognised. To award considerate construction credits, BREEAM requires the assessment of the specific assessed development, in line with the criteria

Responsible construction practices – Multiple contractors on the same project - KBCN0352

It is the site that must comply with BREEAM issues rather than any individual contractor. Several different contractors may have obligations to meet compliance criteria. One of the contractors and/or site managers may have responsibility for ensuring compliance during site operations. It is ultimately the client/project team's responsibility to determine and demonstrate compliance.

Stakeholder consultation – Existing shared facilities - KBCN0360

The consultation must include any existing shared facilities relied on to achieve compliance as well as the new facilities. To ensure the shared existing facilities are appropriate and in line with the users' requirements.  
Information correct as of 9thMay 2025. Please see kb.breeam.com for the latest compliance information.