New Construction / NOR / V6 / 03 - Energy /

ENE 01

Information correct as of 1stJune 2025. Please see kb.breeam.com for the latest compliance information.

District heating systems – fuel mix - KBCN0885

Where the feasibility study is considering connection to a district heating system and this burns a mixture of fuels, only the proportion of output generated from second generation bio-fuels (or waste incineration that complies with BREEAM requirements) can be considered for this issue. For instance, a system burning a 25/75 mix of compliant biofuel vs fossil fuel can only count 25% of its output towards a meaningful reduction in CO2 emissions (where relevant to the BREEAM scheme) against the baseline building. As fuel mixes may vary over time, at least one year or more of historical information must be provided to balance out any seasonal variations. Where the system is new or proposed, robust evidence must be provided of the anticipated fuel mix. The fuel mix must be calculated based on the energy content of the input fuels in kWh.
19/12/2017 Wording clarified

Feasibility study – comparison with connection to existing LZCs - KBCN0563

In carrying out a feasibility study (covering all the areas required as stated in the manual) the primary intent is to demonstrate to a reasonable level of certainty that the chosen LZC is the most appropriate of all those available. Some of the options (for example community heating/cooling schemes) may not allow for a simple like for like comparison but a comparison can be made overall across many factors. For example in a community heating scheme the life cycle costing estimate might need to be simply the cost of using and maintaining the system for the measuring period, if upfront costs and payback period information is not available. Similarly for an existing community scheme, planning would not be a barrier but land use and noise impacts could be compared. The feasibility study must include a comparison of all criteria and for it to show that each has been factored into the final option being made. While some options may provide information in different formats and differing levels of detail making direct comparisons not straightforward, a comparison can still be made and this should aim to be as comprehensive and representative as possible. This will serve to demonstrate with reasonable certainty that the chosen option is the most appropriate. 

LCC – LZC energy sources discounted - KBCN0606

When sufficient information can be provided to justify that LZC energy sources are not appropriate for the development, the LCC analysis, for those LZC sources, do not need to be included in the feasibility study. The feasibility study (covering all the areas required as stated in the manual) intends to demonstrate, to a reasonable level of certainty, that the chosen LZC is the most appropriate of all those available.

LZC feasibility study – timing - KBCN1052

If a feasibility study is undertaken at a stage later than Concept Design, this must include an explanation for any local LZC technologies ruled out because of constraints arising from the late consideration. Compliance may still be achieved if other LZCs are feasible and the criteria are met. If the late completion of the feasibility study resulted in no LZC being installed, the credit must be withheld.  

LZC technologies – energy centre or other LZCs connected at a later stage - KBCN0267

If a project specifies LZCs that have been proposed in the feasibility report which reduce emissions, and/or will be connected to a site-wide energy centre operational at a later stage of the phased development, after the Post Construction Stage review has been submitted, the Energy and Pollution issues can be assessed as follows: In a phased development where the primary heating system will be upgraded at a later stage than the building being assessed, a commitment to install the new heating source must be made in the General Contract Specification (as per the BREEAM requirements). BREEAM does not specify a particular time for phasing as it is difficult to set parameters, however as a rule building users should have to wait the least time possible before they can use the upgraded heating source. For the quality audit, two Energy model outputs/EPCs must be produced at the final stage - one with the actual interim system installed for building control, and one for the BREEAM assessment which can include the predicted energy from the proposed energy centre.  Additionally, the legally binding general contract specification for the new heating source must be submitted with details of the timescales proposed for the completion of the second phase of work. Where this approach is to be followed BREEAM must be consulted in each case to ensure that the arrangements are sufficiently robust to award the credits. BREEAM seeks to recognise the environmental impacts of a building's energy use throughout its life, therefore temporary arrangements can be accommodated, provided there is robust evidence on future connection to the permanent systems.
24/08/2022 - Applicability to UKNC V6 confirmed

LZC technologies – shell only feasibility study - KBCN0409

For a shell only project, compliance may be assessed on the built form only i.e. demonstrating that sufficient space and clearance for the installation of future LZCs has been considered, the built form is suitably sited, and that massing and orientation are optimised for the future systems.

On-site LZC – whole site shared connection - KBCN1424

To be recognised in BREEAM, the on-site Low and Zero Carbon (LZC) technology must have a direct physical connection to the assessed asset. OR Where the LZC technology is; It is acceptable to allocate the renewable energy generated proportionally as a calculation of the asset's predicted energy consumption compared to the total energy consumption of the whole site. To allocate renewable electricity by proportional consumption: Where consumption data is missing, renewable electricity must not be allocated to the assessed asset. In this case, it is assumed that all electricity consumed is sourced from the grid.
17-Jan-2024 - Applicability BIU V6 Ene 13 removed, as this approach is not applicable to assessing the area of PV fitted.
21-Dec-2022 - Applicability to In-Use V6 confirmed.
24-Aug-2022 - Applicability to UKNC V6 confirmed.

Passive design analysis – Modelling the standard building when existing building elements are retained - KBCN1270

In circumstances where an existing building element (e.g. a facade) is being retained it is acceptable to incorporate them into the modelling of the 'standard building' baseline, for the purpose of undertaking passive design analysis. All other building elements should be modelled with fabric performance equivalent to that of the local Building Regulations Notional Building (or for Scotland, an equivalent compliant building) and without the passive design measures (where feasible i.e. building orientation is likely to be fixed).


Prediction of operational energy consumption – Multiple (similar) buildings assessments - KBCN1479

Sampling is not appropriate to meet the aim of the criteria; it is necessary to model the predicted operational energy consumption of all assessed units. Credits are awarded for undertaking the detailed modelling, therefore there is no requirement to identify the worst performing unit and KNCN1382 is not applicable.
24/08/2022 - Applicability to UKNC V6 confirmed

Information correct as of 1stJune 2025. Please see kb.breeam.com for the latest compliance information.