New Construction / NOR / V6 / 08 - Land Use and Ecology /
LE 01
Information correct as of 22ndOctober 2025. Please see kb.breeam.com for the latest compliance information.
Land reclaimed from the sea - KBCN0558
Land reclaimed from the sea cannot be considered as previously developed land.
It has not been occupied by a permanent structure and any associated fixed surface infrastructure (please refer to the Additional information section).
Previously developed land – temporary structures - KBCN0659
The presence of concrete and hardstanding areas established as temporary structures for enabling works are not considered to be previously developed land on a site.
The nature of enabling works are temporary; with the purpose of enabling the delivery of a development and are not constructed to be permanent. Temporary structures of this kind are not included in the definition of previously developed land no matter how long they have been present on a site.
Previously occupied land – Fixed surface infrastructure - KBCN1140
Car parks and other hard-landscaped areas often incorporate small pockets of soft landscaping. Where these are integral to the hard landscaping and constitute a small proportion of the total area, these areas can be considered as part of the fixed surface infrastructure.
Previously occupied land – multi-use games areas (MUGAs) - KBCN1464
For education assessments, playing fields are considered previously occupied land if an equivalent area of playing field is reinstated on land of low ecological value within one year of completing the construction works.
Multi-use games areas (MUGA) or similar are also acceptable as replacements for playing fields.
Previously occupied land – multiple assessed buildings - KBCN1093
For sites with multiple assessed buildings, where it is not possible to clearly define separate development footprints for each building, the assessment can be done on a site-wide basis.
In this approach, the boundary of the development footprint is considered to be the whole site.
This overall result is used to assess compliance for each included BREEAM assessment.
20-Oct-2022 Title amended for clarity. Wording clarified. Scheme applicability updated.
Information correct as of 22ndOctober 2025. Please see kb.breeam.com for the latest compliance information.