New Construction / NOR / V6 / 01 - Management /

MAN 01

Information correct as of 26thApril 2025. Please see kb.breeam.com for the latest compliance information.

BREEAM Advisory Professional (AP) – Retrospectively applying AP status - KBCN1080

The AP status cannot be applied retrospectively. The purpose of using an AP on a project is that they can advise and steer the development from the outset to maximise its BREEAM and sustainability performance for the least cost/risk. If early AP appointment and involvement does not occur then the aims and criteria of this BREEAM issue are not being met.

BREEAM AP – Achieving the design credit at the Post Construction Assessment - KBCN0215

Where a project will be undertaking a post construction stage assessment only (no interim assessment), to demonstrate that the criteria were met at the design stage a "BREEAM credit monitoring report" should be provided when the assessment is submitted, which shows that at the design stage of the project the building was still on target for the proposed BREEAM rating. This could be an excel document showing the issues that the design is on target for achieving with a short summary of how the BREEAM AP is steering the project for the correct rating. As long as the criteria are met and the correct information can be gathered for your evidence, a design stage certification is not required.

BREEAM AP – Change of BREEAM APs/Sustainability champions during project - KBCN0295

Whilst it would generally be preferable to retain the same individual in the role of BREEAM AP/Sustainability champion throughout the design and construction of a particular project for the purposes of continuity, we appreciate that this may not always be feasible. It is therefore entirely appropriate that the three credits available for using BREEAM APs/Sustainability champions can still be awarded where the individual performing the role changes (provided the ongoing involvement of an AP/SC is maintained in accordance with the criteria).  

Design team meetings via conference call - KBCN0201

Design team meetings can be conducted via conference calls.

It can be difficult for design team members to be in the same place at the same time. Conference calls are a more sustainable way to conduct meetings. 


Stakeholder consultation – Existing shared facilities - KBCN0360

The consultation must include any existing shared facilities relied on to achieve compliance as well as the new facilities. To ensure the shared existing facilities are appropriate and in line with the users' requirements.  
Information correct as of 26thApril 2025. Please see kb.breeam.com for the latest compliance information.