New Construction / NOR / V6 / 01 - Management /
MAN 02
Information correct as of 1stSeptember 2025. Please see kb.breeam.com for the latest compliance information.
Definition – Critical value - KBCN1006
Critical value aims to
maximise whole life value of the building based on client requirements, and differs from minimising life cycle cost. This is a more specific analysis of how the building's ongoing maintenance and operation can impact business needs. For instance:
- Where any disruption to business is costly, a specification with long periods between maintenance cycles and reduced maintenance time may be desirable.
- Where maintaining aesthetics are important, a maintenance cycle may be based on aesthetic upkeep rather than functional lifespan.
- Where maximum recyclability and re-usability is important, an alternative, costlier specification may be required.
- Where capital costs are constrained, the specification with the lowest LCC may not be affordable, and instead, the best available option within the budget is chosen.
Life cycle cost – Multiple assessments on the same site - KBCN000003
Where there are multiple assessments on a site and a single life cycle cost (LCC) plan will be carried out, it is acceptable to use this plan as evidence provided that the results of the LCC plan can be applied to all of the assessed buildings and therefore may have a positive influence on the material specification of such buildings. Where the design of some assessments differ to the extent that the LCC plan cannot reasonably be applied, a separate LCC plan is necessary to achieve credits for this issue.
Where multiple assessments are covered under a single LCC plan, there must be sufficient detail for each building to enable them to be adequately assessed.
Information correct as of 1stSeptember 2025. Please see kb.breeam.com for the latest compliance information.