Refurbishment and Fit Out / UK / 2014 / 08 - Land Use and Ecology /
LE 05 - Long Term Impact on Biodiversity
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.
Aircraft safety – developments in the proximity of airports - KBCN0977
Where it can be demonstrated that an assessed development, within or adjacent to an airport or similar must restrict the ecological value of the site for reasons of aircraft safety (mitigating the risk of bird-strikes to meet ICAO/EASA/CAA or equivalent regulations), the approach for some issues in the Land Use and Ecology category can be adjusted. If in these circumstances, the client wishes to enhance ecological value on an external site, outside of the main development site, this can be considered in the following way for each issue:
Ecological value of site and protection of ecological features: The development site only must be assessed, but the recommendations may be tailored to suit the requirements of the relevant legislation.
Enhancing site ecology: The development site and the external site must be included in the SQE’s report and recommendations, albeit that, for the development site, the approach may to be to restrict biodiversity. Enhancements implemented in-line with the recommendations of the SQE are likely to apply to the external site.
Long term impact on biodiversity: Both sites must be considered in the SQE’s report, albeit that, for the development site, the approach may to be to restrict biodiversity. Credits for additional measures to improve the site’s long-term biodiversity can be awarded on the basis of adopting these for the external site only, in line with the guidance.
GN13 Relating ecologist’s report and BREEAM - KBCN0626
Introduction
This guidance note is to be used for registered BREEAM UK New Construction 2014 and RFO 2014 and International New Construction 2016 and RFO 2015 assessments, where an ecologist has been appointed by the client and has produced an ecology report for the proposed development.
The purpose of this guidance note is to help the BREEAM Assessor relate the content of the ecologist’s report to the BREEAM Land Use and Ecology section criteria (assessment issues LE 02, LE 03 (UK only), LE 04 and LE 05). The guidance within this document has been produced to support the assessment of the aforementioned BREEAM issues and should not be interpreted as criteria. If the BREEAM Assessor chooses to use the template provided within this guidance note as evidence in the assessment (use of this document is optional) the assessor or the appointed suitably qualified ecologist must complete all relevant sections
View full Guidance Note (licensed assessors only)
View all Guidance Notes (licensed assessors only)
01/04/2020 Clarified applicability to UK RFO 2014 and International RFO 2015 schemes
Habitat management plan – Level of detail required - KBCN0132
The level of detail required in the landscape and habitat management plan needs to be commensurate with the complexity and extent of the landscaped areas. If there is a limited amount of landscaping, then a simple plan would be acceptable, commensurate with the significance of the area assessed.
Where the suitably qualified ecologist, appointed prior to commencement of activities on site, confirms that a landscaping and habitat management plan is not applicable due to the nature of the site and its surroundings, such as being nearly all or entirely hardstanding or having little or no external space, then full credits can be awarded for demonstrating that the relevant legislation has been followed.
21 Feb 2023 - Applicable to UK NC2018/V6
Landscape and Habitat Management Plan – SQE involvement - KBCN0564
Even if not stated explicitly, it is implied and expected that the Suitably Qualified Ecologist (SQE) does verify the content of the Landscape and Habitat Management Plan to ensure that it is consistent with the whole site ecological strategy.
19 Nov 2021 Applicability to UK NC2018 confirmed
Late appointment of the Suitably Qualified Ecologist - KBCN0603
If the Suitably Qualified Ecologist (SQE) is appointed after the commencement of activities on-site and if the other requirements of this issue are met, then credits can still be awarded, provided that:
- the SQE confirms that all relevant UK and EU legislation relating to the protection and enhancement of ecology has been complied with during the design and construction process
- the SQE confirms that their late appointment has not compromised the adoption of any measures to improve the assessed site's long term biodiversity.
13th Jul 21 Correction - applied to UK NC2018 LE05
No opportunity for ecological protection or enhancement - KBCN0921
This Issue is not applicable to the assessment where it can be demonstrated that;
- There are no new or existing landscaping areas and therefore no need for ecological protection (ie when the ‘Protection of ecological features’ Issue is N/A)
AND
- There is no opportunity to make ecological enhancements (ie when the ‘Enhancing site ecology’ Issue is N/A). An example of such a case could be a retail building with a glazed shop frontage, where there are no other external elements or spaces for enhancement.
Evidence that there are no suitable external facades, roofs or other external areas within the developer’s control must be provided by the design team.
When both of the above conditions are in place and the two relevant scoping questions are completed in the scoring and reporting tool, this Issue will be filtered out of the assessment.
Off-site ecological enhancement - KBCN0651
BREEAM does not recognise enhancements which are not within the boundary of the site being assessed, as the aims of the land use and ecology section relate to the ecological value and biodiversity of the specific site under assessment.
However, off-site ecological enhancement can be accepted where:
- It is within the wider site, surrounding or adjoining the development.
- The land is currently under the ownership of the developer and intended to remain so (i.e. there are no immediate plans to sell);
- The Suitably Qualified Ecologist (SQE) confirms that the proposed ecological enhancements are appropriate and more effective than can be done solely within the red line boundary;
- The owner remains responsible for the on-going maintenance of the land.
Full justification and robust evidence must be submitted when relying on this approach.
BREEAM recognises that the red-line boundary drafted for planning purposes may not reflect the entire site within the control of the developer or building owner.
Shared ecological enhancements - KBCN0656
A site-wide approach to ecological enhancements can be used on sites where multiple buildings share areas of soft landscaping. The enhancement benefits are applied to the individual building assessments within the site.
Similarly, where a building comprises more than one assessment, eg different floor assessments, a green roof on top of that building can be used to award credits for each assessment for which the Land use and ecology issues apply.
The benefit can be applied on a site-wide basis provided all developments are completed within the appropriate timeframe of a valid ecological survey.
Suitably Qualified Ecologist – Other recognised organisations - KBCN0192
With regards to the definition of a Suitably Qualified Ecologist, in addition to the organisations already listed within the manual, full members of the following organisations are also deemed SQE's;
- Royal Society of Biology
- Institute of Environmental Sciences
Provided the individual meets all other requirements as outlined in the definition of a Suitably Qualified Ecologist (SQE).
Suitably Qualified Ecologist – Professional membership - KBCN0743
With reference to the definition provided in the technical guidance, ecologists can be considered as meeting Requirement 3 based on full membership of the organisations listed.
Those who are not full members may be considered as meeting Requirement 3, however the assessor must ensure and demonstrate, that the ecologist is covered by a professional code of conduct and is subject to peer review.
In all cases, Requirements 1 and 2 must also be met.
24 May 2024 - Updated to clarify that where ecologists who are not full members of a professional body meet the above guidance for Requirement 3, other than also meeting Requirements 1 and 2, no additional evidence or confirmation is required.
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.