Home Quality Mark / HQM beta / A Our Surroundings / A3 Safety and Resilience /

06 Flood Risk

Information correct as of 24thApril 2024. Please see kb.breeam.com for the latest compliance information.

Flood risk – Site situated across numerous flood zones - KBCN0532

Where a site is situated across more than one flood zone, the flood zone with the highest probability of flooding, i.e. the worst case scenario, must be considered for the purpose of the BREEAM assessment. An exception to this would be where the areas in the higher probability zone include only soft landscaping and it can be demonstrated that access to the building will be maintained in a flooding event. This is to ensure that the site has adequately managed the worst case scenario level of flood risk associated with the site's location. 
22/07/2022 Applicability to HQM One confirmed
07/03/2018 Updated to include circumstances where an exception may apply.

FRA more than 5 years old - KBCN1580

Where more than five years have passed since the FRA was carried out, to be able to use the FRA in your assessment evidence would be required to demonstrate that the basis of the FRA has not changed in that time.
Information correct as of 24thApril 2024. Please see kb.breeam.com for the latest compliance information.