Refurbishment and Fit Out / RFO Commercial V7 /
01 - Management
Information correct as of 10thSeptember 2026. Please see kb.breeam.com for the latest compliance information.
Capital cost reporting and LCC measured area - KBCN0438
When assessing the Capital cost reporting and the LCC credits, the area to be considered should be the Gross Internal Floor Area (GIFA), according to the below
RICS definition:
Gross Internal Floor Area
Gross Internal Floor Area is the area of a building measured to the internal face of the perimeter walls at each floor level, which includes:
- Areas occupied by internal walls and partitions
- Columns, piers chimney breasts, stairwells, lift-wells, other internal projections, vertical ducts, and the like
- Atria and entrance halls with clear height above, measured at base level only
- Internal open sided balconies, walkways, and the like
- Structural, raked or stepped floors are treated as a level floor measured horizontally
- Horizontal floors with permanent access below structural, raked or stepped floors
- Corridors of a permanent essential nature (e.g. fire corridors, smoke lobbies, etc.)
- Areas in the roof space intended for use with permanent access (BCIS)
- Mezzanine areas intended for use with permanent access
- Lift rooms, plant rooms, fuel stores, tank rooms which are housed in a covered structure of a permanent nature, whether or not above main roof level
- Service accommodation such as toilets, toilet lobbies, bathrooms, showers, changing rooms, cleaners’ rooms and the like
- Projection rooms
- Voids over stairwells and lift shafts on upper floors
- Loading bays
- Areas with a headroom of less than 1.5m
- Pavement vaults
- Garages
- Conservatories (BCIS)
And excludes:
- Perimeter wall thickness and external projections
- External open-sided balconies, covered ways and fire escapes
- Canopies
- Voids over or under structural, raked or stepped floors
- Greenhouses, garden stores, fuel stores and the like in residential property
- Open ground floors and the like (BCIS)
14.02.18 - KBCN content amended to extend the applicability to LCC and to refer to GIFA rather than GEA, to reflect current industry practice.
Elemental LCC and options appraisal timing - KBCN1889
The elemental LCC should be undertaken as part of the strategic options appraisal process and used to inform the selection of significant building elements and systems, such as the structure, envelope and building services. Completing the options appraisal after key design decisions have been finalised may reduce its effectiveness and limit the opportunity for the findings to influence the final design.
However, the timing requirement can still be met, where the assessor agrees that there is a justification for the appraisal continuing into early AIA Stage 2 - Schematic Design (or equivalent), and clear evidence to demonstrate that:
- The key options remained under consideration during the appraisal.
- The findings were capable of influencing the final design solution.
- The intended outcomes of the elemental LCC process have not been compromised.
In all cases, the outline elemental LCC plan and identification of relevant project options must be completed by the end of Concept Design
Erratum – Monitoring utility consumption – Meeting the set targets - KBCN1899
The target and actual total energy and water consumption figures must be entered into the platform. However, meeting the targets is not required for compliance.
The relevant criteria will be clarified in the next reissue.
GN54 Responsible construction management – BREEAM V7 - KBCN1752
Latest version: v1.0, July 2026
Guidance Note 54 (GN54) provides information on achieving the responsible construction management requirements in Man 03 in BREEAM V7.
It has two parts:
- Part 1 lists the requirements that must be met to achieve credits for responsible construction management in BREEAM V7.
- Part 2 provides a list of the schemes or tools that have been evaluated by BREEAM and can contribute to the achievement of one or more credits for responsible construction management.
This guidance note only applies to BREEAM V7. There is a separate guidance note for earlier versions of BREEAM UK NC and UKNCR (see
Guidance Note 33).
Download Guidance Note 54
View all Guidance Notes on BREEAM Projects (licensed assessors only)
15-Jul-2026 - Updated version released (v1.0)
Submitting aftercare & post occupancy evaluation data - KBCN0589
Where credits have been awarded which require post-occupancy evaluation or an element of aftercare data collection (according to scheme requirements) from the building once operational and occupied, the data gathering must take place at the specified time and the findings reported to BRE.
The timing of this evidence gathering depends on the criteria of the BREEAM scheme having been undertaken. However, for all schemes, once the evidence is due for submission, it should be sent to BREEAM@bre.co.uk with the following title;
'
BREEAM Assessment Type Building Data
BREEAM Assessment Reference'
For example, a BREEAM 2011 New Construction assessment would use the following title when submitting their evidence;
'BREEAM NC 2011 Building Data BREEAM-1234-5678'
This KBCN replaces KBCN0695 for HQM.
Information correct as of 10thSeptember 2026. Please see kb.breeam.com for the latest compliance information.