BREEAM AP – Achieving the design credit at the Post Construction Assessment - KBCN0215
Where a project will be undertaking a post construction stage assessment only (no interim assessment), to demonstrate that the criteria were met at the design stage a "BREEAM credit monitoring report" should be provided when the assessment is submitted, which shows that at the design stage of the project the building was still on target for the proposed BREEAM rating. This could be an excel document showing the issues that the design is on target for achieving with a short summary of how the BREEAM AP is steering the project for the correct rating.
As long as the criteria are met and the correct information can be gathered for your evidence, a design stage certification is not required.
BREEAM AP – Change of BREEAM APs/Sustainability champions during project - KBCN0295
Whilst it would generally be preferable to retain the same individual in the role of BREEAM AP/Sustainability champion throughout the design and construction of a particular project for the purposes of continuity, we appreciate that this may not always be feasible. It is therefore entirely appropriate that the three credits available for using BREEAM APs/Sustainability champions can still be awarded where the individual performing the role changes (provided the ongoing involvement of an AP/SC is maintained in accordance with the criteria).
BREEAM AP/Sustainability Champion appointment timing - KBCN0738
It is acceptable for the BREEAM AP/Sustainability Champion to be appointed later than the required stage, if it can be demonstrated that the AP/Sustainability Champion was appointed at the earliest appropriate time in the project and that the late involvement will not have a detrimental effect on the setting of BREEAM performance targets that need to be formally agreed no later than the concept design stage.
Design team meetings via conference call - KBCN0201
Design team meetings can be conducted via conference calls.
Conference calls may provide a more convenient and sustainable way to conduct meetings.
Stakeholder consultation – Building occupier unknown - KBCN0227
Where the building occupier is unknown, it is still possible to achieve the credit. The end user requirements must be assumed and considered by other project parties (e.g. client, design team, etc.) using their experience and judgement until such time as the occupier is known.
Stakeholder consultation – Existing shared facilities - KBCN0360
The consultation must include any existing shared facilities relied on to achieve compliance as well as the new facilities.
To ensure the shared existing facilities are appropriate and in line with the users' requirements.
Information correct as of 25thJuly 2026. Please see kb.breeam.com for the latest compliance information.