AI calculation – changes to public transport services during the assessment - KBCN1527
The AI is calculated as part of the design stage transport analysis and its value relates to the site location and to informing transport-related design decisions. This must be based on current information, including any planned and publicly-notified changes at the time the transport assessment is carried out. This should be used as the AI benchmark for the assessment.
Where later, unforeseen changes to public transport availability are implemented before post-construction certification, the AI benchmark should not be updated at post-construction stage.
Assessments should not be disadvantaged by, or benefit from such changes.
Amenities – Access to cash - KBCN0359
An ATM inside a building would be acceptable provided that its opening hours are similar to those of the assessed building, regardless of whether there is a nominal charge for the service. Cash-back from the till in a retail outlet is not compliant.
Access to cash should be available to the building users at all relevant times of the day. This should not require a prior purchase of goods and should provide access to other services, such as checking account balances.
Amenities – Assessed building is one of the listed amenities - KBCN0264
Where the assessed building is itself included in the list of amenities, that particular amenity criterion can be deemed to be met, e.g. a supermarket development itself meets the proximity to food outlet required for a Retail type building.
Amenities – Multi-residential assessments - KBCN0496
The single credits are awarded independently of each other i.e. you may have the four amenities within 500m but not the seven within a 1000m or vice versa.
Amenities – Pharmacy within hospital - KBCN0321
A publicly accessible pharmacy would typically be required in order to constitute a suitable amenity. If it can be confirmed that an internal pharmacy (in Northern Ireland this may also include an onsite controlled medical dispensary) will provide prescribed medicines for building users, this is acceptable.
Amenities – Sandwich van as a food outlet - KBCN0557
A food truck/ mobile catering service would not be sufficient to meet the criteria for this issue.
The aim of this Issue is to assess the location of the built asset relative to amenities.
Amenities – Vending machine as a food outlet - KBCN0653
A vending machine can be considered as a food outlet if a range of items, as can be reasonably expected, are for sale to meet the needs of the building users and it is confirmed to be a permanent fixture.
Applicable amenities for different building types - KBCN1269
The guidance for Healthcare buildings does not identify childcare facilities or a school as an applicable amenity. Where these can be demonstrated to be of benefit to the occupants of the assessed healthcare building (staff), this amenity can be considered as applicable.
Likewise, if it can be demonstrated that an amenity, not applicable to a particular building type, would provide a tangible benefit to the occupants of the assessed building, please submit details and justification to BREEAM for review.
Bristol Transport Access Level (BrisTAL) - KBCN1426
The Bristol Transport Access Level (BrisTAL) method provides a way of measuring the level of public transport connectivity within the city of Bristol. It is derived from the Public Transport Accessibility Level (PTAL) approach used by Transport for London. As such, the ‘Access Index (AI)’ output from BrisTAL can be used as evidence of compliance against the BREEAM and HQM Accessibility Index requirements. Please note that project teams must ensure that they use the version of the BrisTAL that is current at the time the transport assessment is undertaken. This is available here:
https://maps.bristol.gov.uk/pinpoint/
03 08 2022 - Updated to clarify that the dataset used must be current at the time of the transport assessment, but this does not need to be updated at post-construction stage
Community transport schemes in rural areas - KBCN00013
In rural areas, where scheduled public services are insufficient to gain credits via the calculation of the Accessibility Index, community transport schemes, including 'on-demand services', can be used to achieve the 'dedicated bus service' option. In such cases evidence must be provided to demonstrate:
- It serves a rural area
- It is available to all potential users
- The service is established at the time of the assessment being submitted
- The service is of an appropriate scale for the community it serves
Content reworded to highlight the availability of the on-demand service to all potential users. 24/04/2017
Cycle spaces – Minimum and maximum requirements - KBCN0637
These remain applicable where the 50% reduction allowed for building locations with a high level of public transport accessibility is in effect.
This means that, for instance, a large retail will still need to provide at least ten customer cycle storage spaces and could meet compliance with a maximum of fifty.
22-Nov-2023 Scheme applicability updated.
18-May-2017 Previous KBCN on large retail adapted to include any minimum requirement for cycle storage spaces.
Cycle spaces – Compliant types of storage - KBCN0257
Due to the number of different types of cycle storage facility available and the variation in site conditions, BREEAM New Construction is less prescriptive about the dimensions and type of cycle parking which can be used to demonstrate compliance. The Assessor is expected to exercise their professional judgement to determine whether the cycle parking spaces meet the aims of the Issue and the requirements listed in the compliance notes.
BREEAM is used to certify buildings, not products. Cycle parking systems cannot, therefore, be considered inherently 'BREEAM compliant'. These must be assessed in context with reference to their location and the intended user profile.
29/01/2024-made applicable to HQM
Cycle spaces – Folding bicycles and scooters - KBCN00024
The provision of cycle storage that is only suitable for folding bicycles or scooters is not compliant.
Providing reduced storage space for folding bicycles or scooters in place of compliant cycle storage may limit future travel options.
14 03 2018 Wording clarified and reference to scooters included.
Cycle spaces – Large retail - KBCN0528
For large retail developments that provide at least 50 customer cycle storage spaces, this meets the requirement for customer spaces. The requirement of one cycling space every 10 staff needs to be met in addition to this.
Cycle spaces – Maximum number of stadium visitors - KBCN0323
To calculate the required provision, the sliding scale of compliance should be used for the staff and up to 5000 stadium visitors.
Cycle spaces – Prominent location - KBCN00053
The requirement to provide cycle storage facilities in a prominent location on site, within view of building users, is intended to encourage use through advertising their presence to building users. Providing these facilities inside the assessed building, such as in the basement, may be compliant so long as there is prominent signage to indicate their location to all building users.
Cycle spaces – Provision for extensions - KBCN0707
When assessing an extension to a building, partial refurbishment or a stand-alone building, which extends an existing facility to be occupied by the same building users (such as a classroom block in an existing school), a site-wide approach should be used to determine the number of new, compliant cycle spaces required.
In such instances a stand-alone approach cannot generally ensure that the new cycle spaces for the assessed extension would be dedicated and available to the occupants of the assessed extension, refurbishment or building. This can only be used where it can be demonstrated that the use of the new cycle storage can be effectively restricted to only those using the assessed extension, either by effective positioning and or management.
Cycle spaces – Provision for regular, large visitor numbers - KBCN0546
Where there are large numbers of visitors on a regular basis, provision of cycle storage for visitors should be based on the maximum number at any given time.
This is to ensure that at peak times enough cycle storage is provided.
Cycle spaces – Public cycle spaces - KBCN1057
Existing public cycle spaces cannot contribute to compliance in BREEAM UK schemes
These are outside the influence of the design team and building operator and it cannot, therefore, be guaranteed that these will be available to building users.
Cycle spaces – Similar buildings assessments - KBCN0570
Where cycle storage and/or facilities are provided for individual units, a site-wide approach cannot be used to include all units. If, however, these are a shared facility, provided in a suitably-located communal area, this may be acceptable.
When assessing using the 'similar buildings' approach, each of the similar buildings has to be assessed separately and credits have to be awarded, based on the worst performing building.
14 03 2018 Clarified to account for suitable shared facilities
Cycle spaces – Small retail – multiple units - KBCN0187
In a development of multiple small retail units, to achieve credit, 10 compliant cycle storage spaces in total are required where it can be shown that these are accessible to all units. However, where such developments consist of multiple units over a large area or are separated by barriers such as roads, the assessor should ensure that the provision is both adequate and conveniently located for all units.
The 50% reduction allowed for building locations with a high level of public transport accessibility is not applicable in this case.
17/11/2016 Note related to the 50% reduction added.
14/03/2018 Note added regarding multiple units over a large area or separated by barriers.
Cycle spaces – Timing of installation in phased projects - KBCN00015
Where cycle storage cannot be installed at construction stage, due to phasing and / or pending demolition works, compliance may still be demonstrated provided:
- Clarification and justification is given for why the storage is not currently available.
- A written contractual agreement is in place to provide BREEAM compliant storage within a clear timescale.
- Alternative storage is provided in the meantime that allow bikes to be easily stored and removed, with the ability to be locked securely against a fixed structure.
The methodology above applies to cycle storage only, and cannot be applied to provision of cyclist facilities (such as showers and lockers) which must be assessed as normal.
This is to allow flexibility within the project programme for the installation of the final, permanent BREEAM-compliant cycle storage whilst still ensuring adequate cycle storage is available during the construction phase.
Cycle spaces and facilities – Rounding calculations - KBCN0445
The calculation for the required cycle spaces and facilities must always be rounded up. If the calculation works out as 5.3 cycle spaces, 6 cycle spaces must be provided.
To determine the requirements for developments with multiple types of building user, calculate the requirement for each user group separately (rounding up to the determine the number of spaces) and then add the number of cycle spaces for each user group together.
04/10/2018 Wording amended to clarify the correct calculation method for developments with multiple user groups.
Cycle Storage – Electric cycle charging stations - KBCN1238
Electric charging stations can be considered as compliant, provided they also meet the criteria for cycle storage spaces.
However, where these are dedicated spaces, (ie they are not available for non-electric cycles), these should not constitute more than 10% of the provision required for compliance.
Cycle storage – new spaces in the public domain - KBCN1410
Where it is not possible to locate short-term visitor/customer cycle storage spaces within the assessment boundary, these may be provided in a suitable and convenient location within the public realm.
The assessor must be satisfied that there is legal agreement and a long-term commitment to the provision of the spaces.
All relevant criteria must be met, however, where justified, the requirement for overhead covering can be waived.
BREEAM accepts that for cycle storage spaces within the public realm, there may be restrictions on the ability to provide overhead covering.
Cyclists’ facilities – Adequately sized lockers - KBCN0961
The requirement for adequately sized lockers is so that cyclists have a dedicated space to store their cycling equipment and clothes. It is not compliant for the space requirement to be met by providing two or more inadequately-sized lockers for each cyclist.
Requiring cyclists to separate their equipment into different lockers/storage spaces could create a barrier to uptake of commuting by bicycle.
Cyclists’ facilities – Combining different facilities - KBCN0683
Cyclists' facilities can be combined, provided that all relevant compliance requirements are met and it is demonstrated that there is no conflict impacting on their use. For example, compliant showers can be combined with compliant lockers in one room, subject to the principle below.
For combined facilities to count as multiple facilities, they must be capable of being used independently of each other at the same time (where relevant) with reference to any space requirements, access, gender and privacy issues.
11 Jan 2023 - Applicability to BIU V6C confirmed
10 Feb 2022 - Updated to clarify that facilities can be combined where there is no conflict.
Cyclists’ facilities – Matching additional cycle spaces - KBCN00093
The minimum number of showers/lockers/changing facilities required for BREEAM compliance is determined by the minimum number of compliant bicycle spaces required, not by how many total compliant bicycle spaces have been provided. Where more than the minimum number of compliant cycle spaces has been provided, there is no requirement to provide more than the minimum number of showers/lockers/changing facilities.
01 Feb 2022 - Wording clarified and applicability to BIU V6C confirmed
Cyclists’ facilities – Multi-residential / residential institutions - KBCN0967
Where there is a BREEAM requirement for residents, compliant facilities within their accommodation can be considered as cyclists' facilities. Separate facilities for staff must be provided as required to achieve compliance.
22 Aug 2023 Applicability to BIU V6 Commercial confirmed.
Cyclists’ facilities – Provision of only one shower - KBCN0566
Where only one shower is provided, this needs to cater for users of both genders.
For a changing facility to count as an additional amenity, it must be capable of being used independently of any showers, otherwise it could not be considered as two facilities.
A shower which is a mixed gender facility must be capable of being used privately. As such, it requires adequate private changing space associated with it.
Amended to provide further clarification and to add the general principle.
10/11/2016
Cyclists’ facilities – Shell only/shell & core assessments - KBCN0882
Cycle parking must be provided as part of the base-build for all assessment types.
Where compliance is sought for additional cyclists’ facilities, the developer should provide all aspects of the installation which fall within the scope of their work and facilitate the future completion of any aspects which do not.
For shell & core assessments, if additional facilities, such as showers and drying space, are not provided in core areas and internal walls are not provided to tenanted areas, these must be indicated on design drawings and all relevant services provided. This would include capped-off supplies and electrical points as necessary in order to facilitate the completion of the compliant facilities by the tenant.
Where internal walls are within scope, a compliant changing area must be provided, however for lockers, compliance can be achieved by providing a design drawing showing that there is an adequately sized and suitably located space for the required number of compliant lockers.
The developer should do as much as they can, within the scope of their work, to facilitate the future installation of compliant facilities and should not do anything which would make future installation more onerous.
01 Oct 2024 - Addition paragraph added to clarify the approach for changing areas and lockers.
25 May 2018 - Wording amended to clarify the intent.
Cyclists’ facilities – Shower provision for male and female users - KBCN0536
Where a deviation from the guidance for a 50:50 split can be fully justified, (for example, based on actual occupancy data from a similar development of the same building type) this can be deemed as compliant by the assessor.
If such justification cannot be provided but design teams wish to provide a flexible arrangement for showers to suit the anticipated building occupancy, providing unisex showers accessible to all building users would be acceptable.
Cyclists’ facilities – Visitors - KBCN00014
Where the cycle spaces requirement is based on the number of staff plus visitors, customers or patients, the number of cyclist facilities required to demonstrate compliance is based on the number of cycle spaces for staff only.
Visitors, customers or patients would not be expected to have access to showers and lockers within a building.
Cyclists’ facilities – Within toilet facilities - KBCN00050
To comply with the criteria for cyclist facilities, showers should not obstruct the use of other facilities. Where a shower is located in a room with a WC, this cannot be considered compliant, unless it can be unequivocally demonstrated that the WC is provided over-and-above the requirements of relevant standards or regulations for general and disabled WCs.
To ensure that there is no conflict between the use of general or disabled WCs and the use of cyclist facilities.
25.10.18 KBCN reworded to improve clarity.
Demand-based bus services in AI calculation - KBCN1338
Demand-based bus services operated by public transport providers can be included in the calculation of the Accessibility Index. The project team will need to determine an average number of stops per hour to allow input into the AI tool.
Education – Boarding schools - KBCN00089
The number of cycle spaces and facilities should be calculated based on the number of day pupils and boarders and these should be available to pupils and staff as appropriate.
For boarders, the cycle storage and cyclists' facilities requirement may depend upon a number of factors, such as the age of the pupils/students, distance of the residential accommodation from the school buildings and the school’s policy on cycling. Therefore, the assessor is required to calculate the appropriate number of cycle storage spaces and facilities for pupils and staff based on the relevant criteria.
Calculations, justification and supporting evidence should be provided in the assessment report.
14 03 2018 - Heading and wording clarified and amended to remove requirement for assessors to submit a technical query prior to certification.
Education – Different age ranges and/or non-acute SEN - KBCN0224
For a combined school campus the number of cycle storage spaces and compliant facilities will need to be calculated individually for each user-group of the building; e.g. the number of facilities for nursery schools, primary schools and secondary schools should be calculated as per the criteria defined for each of these education types and totalled.
Where this includes non-acute SEN facilities and the unusual structure of the classes prevents standard assessment, the assessor should use their judgement to determine whether to apply the pre-school criteria or base on the total number of staff and students.
While within the scoring and reporting tool the dominant education building type category will be selected, calculations need to be provided as supporting evidence, with the assessor's comments/notes used to clarify the calculation used to demonstrate compliance.
14 03 2018 - clarified and key information incorporated from KBCN0424
Education – Primary schools - KBCN1056
Cycle spaces:
Cycle parking spaces are intended for the use of pupils and staff and are calculated based on the number of form groups per year as per the technical guidance.
Additional facilities:
Compliance for pupils can be based on the provision of adequate space in a cloakroom to store outdoor clothing and cycle helmets.
The number of additional facilities for staff should be calculated based on 1 locker per 10 members of staff and 1 shower per 10 lockers’, subject to a minimum of one shower being provided.
In a primary school, pupils are not expected to have access to private showers or other cyclists’ facilities.
22/11/2019: Clarification added regarding the number of additional facilities.
Education – Secondary schools - KBCN0119
Cycle spaces:
Cycle parking spaces may be shared between students and staff, and are calculated based on the total number of staff and students as per the technical guidance.
Students:
Compliance for students can be based on the provision of compliant lockers only based on the following logic:
• Where secondary schools have sports facilities, compliance shall be based on the provision of compliant lockers only. The provision of showers or changing spaces is assumed to be included with the sports facilities are do not need to be assessed.
• Where secondary schools do not have sports facilities, cyclist facilities are assessed as per the technical guidance.
Secondary schools will, in almost all cases, will already have sports facilities including enough showers and adequate changing facilities to meet the BREEAM requirements by default. For most students however, the most important facility is likely to be adequate locker storage rather than showers or changing facilities.
Staff:
Separate shower and changing facilities must be provided for staff. Locker facilities may be shared with students if appropriate, but staff lockers should be suitably located in relation to the other staff facilities.
The number of showers for staff should be based on the total number of staff and one shower for every 100 staff*, subject to a minimum of one shower being provided.
*This is based on 1 cycle storage space per 10 staff, and 1 shower per 10 cycle storage spaces.
10 03 2020 Further clarification of the intent
14 03 2018 Heading and wording clarified
Future transport nodes - KBCN0966
Where a transport node is currently inactive but will become active soon after project completion, it can be included when calculating the existing AI.
To demonstrate this, confirmation of the start of service date and service frequency from the appropriate public transport authority or company will be required.
Greater Manchester Accessibility Level (GMAL) - KBCN1394
The Greater Manchester Accessibility Levels (GMAL) method has been created to provide a way of measuring the density of public transport provision at any location within the Greater Manchester region. It is derived from the Public Transport Accessibility Level (PTAL) approach used by Transport for London. As such, the Greater Manchester Accessibility Index (GMAI) scores generated by the GMAL method can be used as evidence of compliance against the BREEAM and HQM Accessibility Index requirements. Please note that project teams must ensure that they use the version of the GMAL dataset that is current at the time the transport assessment is undertaken. This is available from the data.gov.uk website (
https://data.gov.uk/dataset/d9dfbf0a-3cd7-4b12-a39f-0ec717423ee4/gm-accessibility-levels-gmal).
02 08 2022 - Updated to clarify that the dataset used must be current at the time of the transport assessment, but this does not need to be updated at post-construction stage
No car parking provision - KBCN00059
Where the assessment criteria are applicable to a building that has no car parking spaces and where there are no parking spaces accessible to building users, the benchmarks can be considered to be met. If, however, parking is shared with other buildings or parking spaces are available on a campus-type site then the provision must still be assessed.
No data for AI at Design Stage - KBCN0551
If there is insufficient data for a future transport service to include this in the calculation of the AI at the Design Stage, it should not be accounted for.
If at Post Construction stage the data is available, this can be incorporated.
Whilst certain Design Stage requirements can be based on commitments to achieve a certain performance, this must be based on verifiable data.
16/04/18 Wording amended to clarify that this applies to future services and to allow applicability to UK NC 2018
Obligation to provide a minimum number of car parking spaces exceeding BREEAM requirements - KBCN0401
Where it can be demonstrated (by documentary evidence) an obligation to meet a ’minimum car parking requirement’ which exceeds the BREEAM benchmarks is imposed by the planning authority, as long as no more than the stipulated minimum spaces are provided, a single credit can be awarded.
Occupancy calculation – Buildings with shift patterns - KBCN0431
In buildings with shift patterns, as shifts may overlap, the building users calculation should be based on the maximum occupancy of the building at any given time.
Occupancy rates – 24-hours consulting or treatment rooms - KBCN1258
The default occupancy rate for 24-hour consulting or treatment areas in hospitals and care homes is 0.07.
Published pending reissue of the technical manual UKNC2014/REISSUE UKNC2018/REISSUE
03.11.2021 Issue 2.0 of the UK RFO technical manual amended.
On-demand public bus services - KBCN1404
These can be recognised as follows:
- The location of the transport node should be determined as the nearest available pick-up point to the assessed building
- The frequency of the service should be considered as the published maximum wait time (or actual average wait time, if the service is established and this data is available)
- Such services, whilst they may serve multiple destinations, should be considered as a single route
- It must be demonstrated that information on the availability and how to access the service is made available to building users
This is limited to genuine on-demand bus services, which are operated as public transport with multiple pick-up and drop-off points and does not extend to private hire, taxi or other similar operations.
Park and Ride Schemes - KBCN0754
'Park and ride' bus services run from one or more car parks to a city centre or other destination to allow travellers to park their car at a convenient location and complete their journey by bus. These generally stop at transport nodes en route to allow passengers to board or alight.
Provided the service meets the aim of the Issue with reference to the guidance, they can be considered for this Issue in the same way as any other bus service.
Parking integral to development’s use - KBCN1145
Dedicated on-site parking which is integral to the function of the development can be excluded from the calculation of parking capacity. Examples could include, but are not limited to:
- Dedicated bays for police vehicles at a police station
- Parking for delivery vehicles at an industrial warehouse
- Holding bays for damaged vehicles at a vehicle repair centre
The spaces are only to be used for this purpose, and must have appropriate signage and / or markings.
Parking spaces with electric car recharging stations - KBCN00044
Electric car spaces should be included in the total number of car parking spaces calculation for maximum car parking capacity.
Whilst electric cars provide benefits in terms of reduced emissions, they do not directly reduce congestion which is one of the aims of this issue.
PTAL report supporting evidence - KBCN0230
For developments in Greater London where a Public Transport Accessibility Level (PTAL) report is provided, this report does not need to be supplemented by additional evidence to demonstrate compliance with criteria. The assessor should be satisfied that the PTAL report is current and accurately relates to the assessed site.
Public car parks - KBCN00092
Any public car parks in the vicinity of the assessed building, for which the building owners/operator are not providing some form of subsidy or an agreement with the car park operators to provide priority spaces for building staff, can be excluded from the assessment.
Retail/Industrial showroom assessments - KBCN1178
For Retail/Industrial showroom assessments, Tra 04 is not applicable as suggested in the Retail/Industrial Showroom Appendix.
In order to remove the applicability of Tra 04 for this building type on BREEAM Projects, please select any of the retail types of buildings under Tra 03, so that credits under Tra 04 become unavailable.
Regarding the assessment of Tra 03, please continue to refer to the ‘industrial’ building criteria of the BREEAM UK New Construction 2014 technical manual as per Retail/Industrial Showroom Appendix.
Rounding the number of parking spaces - KBCN0602
Where the calculated number of car parking spaces is a fraction of a whole number, this should be rounded down to the next whole number to assess the issue.
Fewer parking spaces are preferable as the more sustainable solution.
Safe pedestrian routes: definition, measurement and verification - KBCN0238
Definition
Safe pedestrian routes include pavements and safe crossing points, which may be controlled or, for example, be identified by tactile paving, a crossing island or a dropped kerb. An element of judgement may be required, in which case justification should be provided.
Measurement
Distances could be measured, for example, along a pavement, across a road at a safe crossing point and along the pavement on the other side. The distance should not be measured diagonally across a road, following the most direct route.
Evidence from Google Maps or other digital sources may be used to indicate routes and distances, provided that the scale is appropriate and clearly indicated.
Verification
The assessor’s site inspection is an important aspect of the assessment of this issue as it must confirm that all relevant information is current and should include photographs of any key areas. This may also help to identify safe crossing points or hazards which may not be apparent from a desktop study.
For BREEAM NC and RFO assessments, Google Streetview may be acceptable as evidence to demonstrate safe pedestrian routes and the presence of key features or amenities at Design Stage only. Such information must be verified as above for Final Certification.
07 Mar 2024 - No changes have been made. This appears as 'updated' due to an administrative error.
11 Jan 2024 - Wording re-structured for clarity
19 Dec 2023 - Applicability to BIU V6 confirmed
Temporary Car Parking - KBCN0751
The number of car parking spaces should be based on the permanent parking spaces provided specifically for the development once fully operational.
Assessors should determine whether parking spaces should be considered 'permanent' or 'temporary', based on evidence provided by the design team.
Tram services - KBCN000004
Tram services are classified as train services when assessing transport accessibility.
Visitor car parking spaces for Other Buildings (Transport type 2) - KBCN0242
For developments such as hotels and visitor centres, which have a relatively small number of staff and large visitor numbers, the guest/visitor car parking spaces do not need to be assessed for this Issue where these are separate from the staff parking spaces. However, if the staff and visitor’s spaces are combined (and not clearly segregated) then all spaces must be accounted for within the calculation for maximum car parking capacity.
The aim of this Issue, 'To encourage the use of alternative means of transport...' is intended to apply to those commuting to the building on a regular basis.
21 06 2017 Wording amended to clarify the type of building and building-user covered by this KBCN.
[KBCN withdrawn] ~ Cycle storage spaces for all range schools and non-acute SEN - KBCN0424
This KBCN has been withdrawn and is no longer valid. Please see
KBCN0224 for relevant guidance.
This is due to duplication of guidance.
KBCN withdrawn 14 03 2018:
Where assessing an all range school, the appropriate criteria should be applied for each age range. Where this includes non-acute SEN classes and the unusual structure of the classes prevents standard assessment, the assessor should use their judgement to determine whether to apply the pre-school criteria or base on the total number of staff and students. The approach taken should be fully justified.
To encourage a sensible application of the criteria in meeting the aim of the Issue