New Construction / International / 2016 / 07 - Waste /
WST 04 - Speculative finishes
Information correct as of 27thApril 2025. Please see kb.breeam.com for the latest compliance information.
Designed-out or integrated finishes - KBCN1066
The requirements for this credit are met when either:
- No finishes within the scope of the issue have been specified, or
- Finishes are integrated into the asset and designed in a way that the finish cannot be removed.
For instance, a self-finished timber floor or exposed soffit which cannot be removed and does not require additional finishes when installed.
This issue recognises avoiding unnecessary waste of materials.
16-May-2023 - Merged with KBCN0046. Scheme applicability updated. Name updated for clarity.
Speculative finishes – multiple residential developments – fully-fitted - KBCN1448
Where fully-fitted multiple residential units are developed exclusively for the rental market, compliance for this Issue can be achieved where it is demonstrated that the tenancy agreement to be implemented stipulates that the finishes cannot be replaced by the tenant.
Speculative floor finishes – Take-back and re-use policy - KBCN1702
Where a developer has an established written policy whereby unwanted floor finishes will be removed for re-use elsewhere prior to the tenant taking possession, this can be considered as meeting the aim of this issue.
This is only applicable to types of flooring which are suitable for re-use, can be easily removed and do not require the use of adhesives or other permanent means of fixing.
Additionally, the tenancy agreement must otherwise prohibit the removal of the flooring by the tenant
Evidence to support this approach would include:
• A copy of the take-back policy
• Details of the flooring type and material
• A copy of the tenancy agreement
Speculative office including floor finishes/suspended ceiling - KBCN0259
The requirements can still be met where a speculative development includes the installation of floor finishes/suspended ceilings provided a Lease Agreement will be implemented to confirm that tenants are not permitted to remove these finishes.
BREEAM recognises that incoming tenants may need to adapt ceiling or floor finishes to suit the requirements of their fit-out. Therefore, where these finishes are installed throughout, in line with Criterion 2, the following applies:
A tenancy agreement, applied to the first tenancy, should stipulate that floor or ceiling finishes may only be modified where necessary, for example, to accommodate new partitions, lighting or other services, to replace worn or damaged components or to replace small, localised areas with a specialist floor or ceiling to account for abnormal conditions, such as wet areas.
Documentary evidence of this must be provided as evidence for the credit to be awarded.
18/04/2017 KBCN made applicable to NC 2016 and IRFO 2015
05/07/2018 Paragraph added to clarify the requirements of the tenancy agreement
27 Jul 2021 Clarified that the terms of paragraph 2 apply also to floor finishes