Commissioning certificates – evidence - KBCN1311
Certificates demonstrating compliance with any relevant standards are acceptable for the commissioning criteria, where they cover all the systems referred to in the criteria (hot water, heating, ventilation etc.) and any relevant commissioning best practice guidance has been complied with.
The ‘commissioning best practice guidance’ outlines how to carry out commissioning for various different systems that may be present. Some of the guidance is more appropriate for complex systems and often won’t be relevant. The person or persons carrying out the commissioning activities is expected to be familiar enough with the standards referenced, to determine the ones that are relevant to the systems they are commissioning.
Independent Air Testing Scheme (IATS) – Elmhurst Airtightness Scheme (EAS) - KBCN1699
Please note that the Independent Air Testing Scheme (IATS) has been rebranded as the Elmhurst Airtightness Scheme (EAS) and therefore where referenced, this may also be accepted.
Thermographic survey – Seasonal constraints - KBCN00031
Where seasonal constraints prevent the thermographic survey from being completed prior to certification at the post construction stage, the requirements can be satisfied with:
- Evidence that a Suitably Qualified Professional (SQP) has been contractually appointed
- Written confirmation by the SQP that the seasonal constraints prevent the survey at an appropriate time before certification
- The survey is scheduled to take place at the earliest opportunity after the handover, and
- There is a specific contractual agreement in place to remedy any identified defects before the defects liability period expires.
Thermographic surveys are designed to map the thermal efficiency of buildings and to detect areas where there are breaches in the thermal envelope. Surveys need to be conducted when temperature differences between the external areas of the building and surrounding air can be detected after the envelope is sealed. There may will be instances where the survey cannot be done before certification after the envelope is sealed and as such, the survey would take place after certification.