Erratum – NC V7 – Ene 07 Flexible demand response

This applies only to the UKNC V7.0 and INC V7.0 manuals.

There is an error in the following:

UKNC V7.0.0 Ene 07 Table 6.16

INC V7.0.0 Ene 07 Table 41

  • Other systems or equipment is now shown separately from Battery energy storage systems
  • The options and number of points scored under Battery energy storage systems have been reformatted for clarity

The corrected table is below:

Systems present  Points available  Flexible demand capability  Points awarded 
Electric space heating 1 Operation can be optimised based on signals from the electricity supplier or local renewable sources. 1
Electric space cooling 1 Operation can be optimised based on signals from the electricity supplier or local renewable sources. 1
Electric domestic hot water 1 Operation can be optimised based on signals from the electricity supplier or local renewable sources. 1
Electric vehicle charging points 2 Charging with one-way control based on signals from the electricity supplier or local renewable sources. 1
Charging with two-way control based on signals from the electricity supplier or local renewable sources. 2
Other systems or equipment with flexible demand capability 1 Installed 1
Battery energy storage 3 Installed battery energy storage with no flexible demand response capability. 1
The installed battery energy storage system is only capable of charging based on signals from the electricity supplier or local renewable sources. 2
The installed battery energy storage system is only capable of feeding electricity back into the grid. 2
The installed battery energy storage system is capable of both charging and feeding electricity back into the grid, based on signals from the electricity supplier or local renewable source. 3

 

The technical manual will be updated accordingly in the next re-issue. The scoring for the Ene 07 calculator in the platform aligns with the above corrected table.