Seasonal commissioning evidence

Where the criteria require that seasonal commissioning activities are to be completed over a minimum 12 month period following the occupation of the building, it is accepted that completed records may not be available at the time of Final Certification.

In such cases, evidence of the appointment of a seasonal commissioning manager and schedule of commissioning responsibilities which fulfils the BREEAM criteria are acceptable to demonstrate compliance.