Multiple developments monitoring construction waste on a site

Where the same contractor is working on a site with more than one development, a single Site Waste Management Plan (SWMP)/Resource Management Plan (RMP) can be produced to demonstrate compliance, if it can be justified that separation of the waste would be impractical.

Where the developments are of a similar nature, such as all new-build or all refurbishment with similar scope, the results from the whole development can be apportioned on the basis of floor area to derive the figures upon which the separate developments will be assessed.

Where the buildings are not similar, the design team will need to provide calculations to demonstrate that the waste has been apportioned as accurately as possible according to the project types.

21/11/16 Clarification added in relation to dissimilar projects on the same site.