It is sometimes possible for an assessment to be resubmitted after certification for a higher rating. When this is requested, the BREEAM QA team must be informed in advance of resubmitting the report. It must also be stated clearly within the cover letter/email with the report resubmission that this is what is being requested.

Requests for re-certification will be considered on a case-by-case basis, by the Certification Manager, to determine whether it is appropriate to proceed. Factors influencing the decision will include but are not limited to:

  • Time since original certification
  • Building type
  • Number of additional credits to be awarded

If it is agreed that this may proceed, a new audit will be carried out of any additional credits added in. The assessor may also need to confirm and if necessary provide supporting evidence to demonstrate, that there have been no other changes to aspects of the project for which credits are being retained.

The assessment will be subject to first submission timescales and the full certification fee (in line with FS036).