Remedial works – timing of acoustic re-testing

The intent of CN “Remedial works” is that, where these are required, re-testing is carried out prior to handover and occupation.

However, it is permissible to carry out the re-testing post-occupation. This is provided any specific guidance for particular building types related test conditions have been met (for instance, it may be that some building specific guidance requires furniture or carpets to not be present during the testing).

Compliance cannot be achieved based on a letter from the SQA confirming that the contractor has followed their advice to achieve the required performance.

07.11.18 KBCN amended to allow for re-testing to be carried-out post-handover.