10 Construction Impacts

Information correct as of 11thApril 2021. Please see kb.breeam.com for the latest compliance information.

00 Test Note – please ignore - KBCN1100

This is a test note only. If there are no other compliance notes below this one it simply means that none exist yet for this issue.

Evidence for ’04 Detailed monitoring and reporting’ at design stage - KBCN1232

The evidence requirements associated with ‘04 Detailed monitoring and reporting’ for Design Stage in both the 'Construction Water and Energy Use' are incorrectly formatted and should appear in the Post-Construction Stage column. For design stage evidence requirements, please refer to KBCN1231 'Design Stage evidence requirements when a contractor has not been appointed'

GN33 has been updated - KBCN1282

GN33 BREEAM and HQM Responsible Construction Management v1.0 (to be used in conjunction with BREEAM New Construction 2018 and HQM ONE) has been updated to v1.1. The main changes are clarifications to Table 2 as follows: -the final CCS monitor’s report must be used to determine the score achieved in CCS -where a score of ≥35 is achieved, a score of at least 7 in each of the five CCS sections must be achieved. GN33 v1.1 can be downloaded from BREEAM Projects » BREEAM Assessor Guidance

GN33- Evidence requirement clarification - KBCN1157

In Guidance Note 33, BREEAM recognised responsible construction schemes are mapped against the 'Responsible construction management' criteria within the manual, in order to determine the degree of comparability. Table 2 in GN33 provides a mapping of the recognised schemes, the relevant scores and the BREEAM items ‘a-s’ which are achieved. Where items in the table have been 'ticked', the only evidence that is required is confirmation of the formal certification under the relevant scheme, in addition to the evaluation report. No further information is required to achieve these items. Where an item in the table has been 'crossed', this means that either, the responsible construction scheme does not demonstrate compliance with that BREEAM item, or that the score achieved is not high enough to confirm compliance with the item. Where a cross exists against an item, additional evidence will be required to demonstrate compliance with those items, (where credits are sought). View full Guidance Note (licenced assessors only)

Responsible Construction Practices -Crit 1 - KBCN1297

There is a typo in crit 1, it should say 'Achieve items required for two credits in Table 57'
Information correct as of 11thApril 2021. Please see kb.breeam.com for the latest compliance information.