Accreditation – sampling and testing laboratories - KBCN1337

Analysis / testing laboratory NC 2016 or newer: Where an organisation used for the analysis of indoor air or emissions from building products is not accredited to ISO/IEC 17025, the organisation must be accredited, either by a national accreditation body, or by a member of any one of the following accreditation groups: European Cooperation for Accreditation International Accreditation Forum International Laboratory Accreditation Cooperation The accreditation must specifically cover the analysis of indoor air or emissions from building products. Other schemes: Accreditation to ISO/IEC 17025 is not required in the criteria. However, this KBCN has been applied to encourage a consistent approach towards accreditation. Accreditation by a national or internationally recognised organisation helps to ensure rigorous, consistent and reliable testing results. Sampling organisation If another organisation carries out sampling on behalf of the analysis / testing laboratory, this organisation does not need to be accredited to the above. However, they must provide a brief report justifying: This report is provided to the BREEAM assessor and submitted as supporting evidence for this issue.
31-Oct-2022 Wording clarified. Scheme applicability updated.
10-Oct-2022 Title amended for clarity. Scheme applicability updated.
24-May-2022 Updated to differentiate between sampling and analysis requirements. 
07-May-2021 Added clarification regarding alternative qualifications. 
10-May-2021 Updated scheme applicability.

Acoustic performance in shell & core assessments - KBCN0235

The guidance below applies to all standard building types. For non-standard building types, a technical query should be submitted. BREEAM does not consider it appropriate to impose requirements on tenants in a shell and core development to carry out acoustic testing in accordance with the criteria, therefore this issue is to be assessed as follows: First credit: Indoor ambient noise level The focus of this criteria is to assess the acoustic performance of the external building fabric which is outside the control of the tenant. The criteria for indoor ambient noise level applies as normal. A Suitably Qualified Acoustician (SQA) must carry out an assessment of the built form specification, typical arrangement, and fit out specification for the building type and and any external factors that are likely to affect the indoor ambient noise levels. Where the layout is unknown, the acoustician must base their assessment on the most sensitive room type likely to be present in the building as a worst case. For example in a retail assessment where there are offices, the acoustician should make an assessment based the requirement for office buildings. Should the SQA determine that an augmented fit-out specification would be required to meet the BREEAM requirements, such details must be covered by one of the three Shell & Core options. First credit: Sound insulation This requirement does not apply to Shell and Core projects and the first credit can be assessed based on indoor ambient noise criteria only. Second credit: Reverberation time If it can be demonstrated that the building will not have any "areas used for speech" the second credit can be awarded by default. However, if this cannot be clearly evidenced due to the speculative nature of the development then this credit must be withheld.
09/06/2020: Reference to meeting rooms has been removed, in accordance with the content of the technical manual
 

Acoustic performance standards - KBCN0922

For the Acoustic performance standards credits it is possible to use either: or If assessors want to use standards that have not been approved yet, they should submit these to BRE along with all relevant documents detailed in the standards approval process. The extent and scope of these local standards and the SQAs justification statement will be checked by BRE acoustic experts to ensure that the overall effect is similar to the stated BREEAM requirements.

Air-conditioned spaces - KBCN00035

Air-conditioned spaces are assessed to ensure appropriate thermal comfort levels are achieved. Cooling capacity should be sufficient to comply with the requirements of CIBSE Guide A, however providing sufficient space to install additional capacity to meet the requirements at a later date in line with projected climate change scenarios is also acceptable. In addition, if it can be demonstrated that the air-conditioning system can achieve the thermal comfort criteria in accordance with CIBSE Guide A, Table 1.5, thermal modelling does not need to be carried out. The “time out of range” (TOR) metric should be reported as 0%.  

Applicability – retail and industrial office areas - KBCN00074

For industrial and retail buildings the 'potential for natural ventilation' requirements apply only to office areas. If a retail building does not contain any office areas, compliance is met by default. Whilst the requirements apply to permanently or semi-permanently occupied offices, small admin areas, which are used only occasionally, can be excluded. This also applies to shell only and shell and core projects, where it can be demonstrated that no office spaces will be provided, as part of the fit-out.
11-Oct-2022 Title amended for clarity and consistency.
15-Sep-2017 IRFO scheme applicability removed - please refer to KBCN0531.
19-Oct-2016 Clarification note added in relation to shell only and shell and core projects.
25-Oct-2016 Distinction between offices and small admin areas added.
 

Applying internal partition sound insulation criteria to internal doors - KBCN0665

Where sound insulation criteria apply to internal partitions the calculations do need to include any doors which are part of the wall in question. While sound insulation performance of a typical door will be lower than for a typical wall, with careful design, specification and detailing, this can be overcome. 

Applying the daylighting criteria - KBCN0579

When assessing the daylighting criteria, the required rooms must fully meet criteria 2a, 2b or 2c. It is not possible to combine criteria 2a, 2b and 2c to assess one room.  

Approach to thermal model when using BMS - KBCN0169

Where there are smart systems such as BMS in place, modelling must consider normal operating conditions, with the heating and cooling system in operation regardless of the control strategy. In order for the design team to size the heating/cooling plant, they will carry out modelling to calculate the heat/cold loss throughout the year. Results of these calculations must be submitted, with the heating/cooling plant specification which would demonstrate that the building has been designed to ensure internal winter/summer temperatures will not drop below an acceptable level, and that in effect the winter TOR is zero.
14 Apr 2023 Applicability to UK NC2018 and UK/Int V6 confirmed

Appropriate project stage to appoint a suitably qualified acoustician - KBCN0256

BREEAM requires that a suitably qualified acoustician is appointed at an appropriate stage of the project, so as to ensure that early design advice on criteria of pre-requisition is met. The aim is to ensure that costly amendments to building designs are not made as a result of late appointment of the acoustician. Ultimately, it is for the assessor to determine at what stage of the project is deemed to be appropriate for this appointment to have taken place given the project specific circumstances and procurement type.  

Areas in the public domain - KBCN0587

Where areas within the site boundary will be public domain after construction, and the design/specification has been determined by the local authority/statutory body/planning permission etc, they can be excluded from the assessment of the 'Safe Access' criteria. Evidence would be required to demonstrate that this was the case. Where the client/design team do not have control of the design of these areas, the development should not be prevented from achieving the credit.

Assessing industrial spaces – exemptions - KBCN0734

The thermal comfort criteria do not apply to the operational or storage areas typically found in industrial assets or other similar asset types. The criteria is still be applied to the other parts of the asset as appropriate. Operational and storage areas often have function-related thermal requirements determined by operational or storage needs. These functional requirements override the needs of any occupants.
17-Jan-2024 - Scheme applicability updated.
03-Nov-2020 - Issue 2.0 of UK RFO technical manual updated with new CN detailing the above.

Assessing thermal comfort in residential buildings - KBCN1408

CIBSE TM59 can be used to demonstrate compliance with the thermal comfort requirements for residential buildings, instead of ISO 7730:2005. This is to recognise the most up to date methodology relating to the assessment of homes.

Compliant test body – alternative compliance route using a Suitably Qualified Acoustician - KBCN1412

Where acoustic testing and measurement has not been performed by an organisation or individual that meets the definition of a compliant test body, compliance with this requirement can still be demonstrated where a Suitably Qualified Acoustician has reviewed the relevant test report(s). The test report must: a) Be countersigned or authorised by a Suitably Qualified Acoustician b) Include a clear statement that the acoustic testing and measurements have been carried out in accordance with the BREEAM or HQM testing requirements AND c) Include evidence that the verifier meets the definition for a Suitably Qualified Acoustician within the relevant BREEAM or HQM technical manual

Cyclist safe access - KBCN0188

Safe access for cyclists must be via a compliant cycle lane, unless it is demonstrated that it would be impractical to cycle for a short distance between the site entrance and cycle storage. For example, where a gate, door or barrier forces the cyclist to dismount and walk for a short distance to access the cycle storage and it would be impractical for cyclists to re-mount1. Where it is not practical to provide compliant cycle lane from the entrance to the cycle storage, the safety of cyclists and pedestrians must be maintained. 1. The intent is that this be a short distance, over which cyclists would typically not choose to re-mount and is anticipated to be no greater than 10m. In order to be considered compliant for greater distances, evidence must be provided of effective additional physical measures to deter cyclists from re-mounting.
29/09/2021 - Additional note (1) added to provide further clarification of the intent
21/02/2020 Re-worded to clarify the intent
02 Jul 2021 - Applicability to UK NC2018 confirmed
 

Daylighting – speculative building - KBCN0269

Where the building is speculative and therefore the final layout is not defined (e.g. only an open plan shell is provided in each tenanted space), the required percentage of each open plan shell should meet the daylighting requirements. However, where it is possible to designate separable ancillary areas that would be required in the space (such as toilets or server room), these can be excluded from the calculation. For daylight calculations in speculative projects where the layout and colours are unknown, a realistic notional layout may be used.

Daylighting – Changing rooms - KBCN1132

The daylighting criteria are not applicable to changing rooms.

Daylighting – communal kitchens (multi-residential) - KBCN0217

Communal kitchens should be assessed under 'Non-residential / Communal Occupied Spaces. Communal kitchens outside of self-contained dwelling units, for example a kitchen within a self-contained student flat shared between several students would be classed as a private kitchen for the purposes of this issue. However, if it was shared between rooms along a communal corridor it would be considered a communal kitchen, and assessed under 'Non-residential buildings - occupied spaces'.

Daylighting – Floor areas for average daylight calculations - KBCN0471

Where the room size is comparable and the function is the same, such as ‘kitchen’, the percentage rule needs to be applied to the total floor area. As the average daylight factor is a measure of daylight across the whole room, only whole rooms can be compliant. This is why we refer to rounding up the ‘80% of the floor area’ requirement to the rounded-up number of compliant rooms. This rule applies to rooms of a similar size and function and compliance note ‘percentage of assessed area’ includes a simple example, where all the rooms are the same size. However, this rule can still be applied to rooms of different sizes. Spaces whose size is substantially larger should meet the average daylight factor requirement on their own. In these cases, the percentage requirement is still applicable to the floor area of the remaining rooms. For example, where 80% of ‘teaching, lecture and seminar spaces’ need to comply with the average daylight factor, if we have a large lecture theatre of 200m2 and 3 seminar spaces of 30m2 each, the requirements for 80% would mean 232m2 of the floor area need to comply. This would require the lecture theatre and two seminar spaces to comply. Where a building contains different area types, the 80% minimum floor area must be calculated by each separate building area type as defined in the table listing the average daylight factors required. For example, a multi-residential building that contains kitchen areas and living room areas, would need each one of these areas to comply with the 80% minimum floor area requirement separately. In schemes where dwellings are assessed separately, this is likely to result in 100% of the relevant dwelling areas complying. This is because in a typical house with one kitchen and one living room, an 80% requirement for the kitchen and an 80% requirement for the living room, would mean the whole kitchen and the whole living room need to comply (since only whole rooms can be compliant).
08/01/2021

Clarifications and example added.

Daylighting – requirements differing by area - KBCN0176

Where areas within a building have different daylighting requirements for the same credit, all relevant areas must meet the requirements to award the daylighting credit(s). The aim is to improve daylight conditions in all applicable area types of an assessed building.

Daylighting – retail cafe / dining areas - KBCN0968

Customer seating/dining areas in a cafe or restaurant should be considered as 'sales areas'. Sales counters, staff areas or food preparation areas, for example, should be assessed as 'Other occupied areas' in accordance with the definition of 'Occupied space'.. The requirements for 'Sales areas' are applied to transient spaces.  

Daylighting – studio flats - KBCN0866

In the case of studio flats, where there are no separating walls between occupied spaces, the minimum area of compliance for the average daylight factor requirement is based on the combined area of kitchen, living room, bed and study area. The required daylight factor for the open-plan space (subject to percentage requirement) should be based on the highest daylight factor required for any of the spaces. It is impractical to separate the open-plan space and assess the daylight according to notional lines. In order to maintain robustness, the highest daylight factor should be applied throughout.

Daylighting – uniformity ratio applicability - KBCN0584

The uniformity ratio requirements apply to the percentage of the building’s relevant areas specified in the table. In the NC 2013 scheme, this is 80%.

Dedicated cycle paths in the absence of cycle facilities - KBCN00039

Safe cycle access needs to be provided even if there are no dedicated cycle facilities. The dedicated cycle paths will generally need to be provided to the main entrance(s) of the building along routes likely to be used by cyclists through the site.  The design team are required to determine what is required to satisfy the intent of the criteria. Cycle access and cyclists' facilities are assessed independently of each other. Building users may cycle even if the building does not have cycle storage facilities and so safe and secure access to and from the building must be provided.

Definition – laboratory containment levels 2 and 3 - KBCN0903

Laboratory containment levels 2 and 3 are defined in: The Management, Design and Operation of Microbiological Containment Laboratories 2001, ACDP This was defined from BREEAM International NC 2016 onwards.
11-Oct-2022 - Title amended for clarity and consistency. Wording updated. Scheme applicability updated.

Definition of concourse - KBCN0386

A concourse is an open area within or in front of a public building which is used primarily for circulation, short term waiting, or incidental interaction, analogous to the concourse of a train station. It should not be considered occupied space.  

Emissions from products – ‘no formaldehyde’ declaration - KBCN1137

Where a product manufacturer’s declaration confirms that a product contains no formaldehyde, this can be used to demonstrate compliance with both the standard and exemplary level criteria. However, where a manufacturer has made a declaration of formaldehyde class E1 without testing, this can only be used to demonstrate compliance with the standard criteria. An E1 declaration only confirms that emissions of formaldehyde are ≤0.12 mg/m3, so this would not be valid evidence to demonstrate compliance with the exemplary level criteria emission limits. The manufacturer would need to provide additional information (e.g. test report) to show that emissions from the product meet the exemplary level emission limit.
11-Oct-2022 Title amended for clarity and consistency.

Emissions from products – absence of regulated / prohibited wood preservatives - KBCN0740

This requirement for wood panels means that PCP (pentachlorophenol, a regulated / prohibited substance) must be absent. In this case, 'absent' is defined as <5 parts per million. This must be verified by testing.
11-Oct-2022 - Title amended to standard naming format for clarity and consistency. Wording clarified.

Emissions from products – BS EN ISO 12460-5 standard - KBCN0118

Products tested to the BS EN ISO 12460-5 standard can show compliance with the BREEAM 'emissions from products' criteria only for the following products: These products must be made from unfaced particle board, unfaced OSB or unfaced MDF. Factory production control testing must demonstrate that the product has a formaldehyde content of ≤ 8mg/100g oven dry board.
10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency. Wording clarified.
01-Dec-2017 - Previously referenced standard EN 120 superceded by BS EN ISO 12460-5 Wood-based panels. Determination of formaldehyde release. Extraction method.

Emissions from products – earlier versions of AgBB standard - KBCN0655

Guidance Note GN22 lists the standard AgBB (2015) as a recognised scheme for emissions from building products for pre-December 2015 launched BREEAM schemes. Previous versions of the AgBB scheme are not listed as recognised schemes because earlier versions of AgBB did not include any requirement for the testing of Formaldehyde. If an earlier version AgBB has been used, further evidence will be required to provide additional information on the required Formaldehyde testing.
10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency. Made applicable to UK and International NC V6.

Emissions from products – exemplary level formaldehyde requirements - KBCN1124

The exemplary level criteria for formaldehyde emission levels are not applicable to the following product types: Formaldehyde emission levels should be assessed on all other product types. This applies also to any approved alternative VOC schemes for these product types listed in GN22.
11-Oct-2022 - Title amended for clarity and consistency.

Emissions from products – French regulations and Category 1A/B carcinogen emission limits - KBCN0741

As highlighted in Table 1 of BREEAM Guidance Note GN22, for certain product types, the French VOC regulation ('Arrêté du 19 avril 2011 relatif à l’étiquetage des produits de construction ou de revêtement de mur ou de sol et des peintures et vernis sur leurs émissions de polluants volatils') can be used to demonstrate compliance with the VOC emissions from building products requirements in pre-December 2015 launched BREEAM schemes. The emissions from building products criteria were significantly updated for the BREEAM International New Construction 2016. Unfortunately the 2011 French VOC regulation does not meet the updated performance requirements for post-November 2015 BREEAM schemes for the following reason. The updated BREEAM requirements require testing for Category 1A and 1B carcinogens (defined as “Carcinogenic compounds detectable by the VOC emission testing requirements in Table 1 and Table 2 and that are classified as category 1A or 1B carcinogens in Annex VI to Regulation (EC) No. 1272/2008 on classification, labelling and packaging of substances and mixtures, which are listed as Carcinogenic VOCs in Annex G.2 of prEN 16516 (draft)"). Annex G.2 of prEN 16516 (draft) lists a total of 57 carcinogenic substances. The 2011 French VOC regulation does not contain any requirements to test for any of these substances. BREEAM is aware of a 2009 French VOC regulation ('Arrêté du 30 avril 2009 relatif aux conditions de mise sur le marché des produits de construction et de décoration contenant des substances cancérigènes, mutagènes ou reprotoxiques de catégorie 1 ou 2') that contains performance requirements for category 1A or 1B carcinogens; however these only cover two substances in Annex G.2 (trichloroethylene and benzene). While BREEAM does not expect all of the substances in Annex G.2 to be analysed by a regulation or testing regime, we do expect more than two. Additionally only the A+ label would meet the updated BREEAM performance requirement for TVOC of 1.0 mg/m³ and only the A and A+ labels would meet the updated BREEAM performance requirement for formaldehyde of 0.06 mg/m³. As such, additional evidence would need to be provided to confirm French VOC regulation A+ labelled products are compliant with the BREEAM International New Construction 2016 performance requirements for category 1A and 1B carcinogens. As such, additional evidence would need to be provided to confirm French VOC regulation A+ labelled products are compliant with the BREEAM International New Construction 2016 performance requirements for category 1A and 1B carcinogens, (see also KBCN1280).
10-Oct-2022 - Title clarified, and amended to align with standard KBCN naming format for clarity and consistency. Made applicable to International NC V6.
26-Apr-2019 - Final paragraph and cross-reference to KBCN1280 added.

Emissions from products – Guidance Note 22 (GN22) - KBCN0719

Latest version: v2.8, January 2024 Within the Health and Wellbeing category of several BREEAM schemes, credits are awarded for specifying materials that minimise emissions from building products of formaldehyde and volatile organic compounds (VOCs). The criteria involve meeting emission level performance requirements in accordance with compliant performance and testing standards. Guidance Note 22 (GN22) lists schemes that show equivalent or better performance than the current BREEAM and HQM criteria, and therefore can be used to demonstrate compliance with the criteria. This document should be read in conjunction with the relevant assessment issue guidance provided in the appropriate BREEAM or HQM technical manual. The guidance note contains two tables: Download Guidance Note 22 View all Guidance Notes on BREEAM Projects (licensed assessors only)
01-Feb-2024 - Updated for release of GN22 2.8
31-Jan-2023 - Updated for release of GN22 2.7 
10-Oct-2022 - This KBCN merged with KBCN0646. Title amended to align with standard KBCN naming format for clarity and consistency. Made applicable to UK and International NC V6.
25-Jan-2019 - Link to Guidance Note updated
12-Mar-2018 - Link to Guidance Note updated

Emissions from products – installations manufactured off-site - KBCN0137

Internal finishes to installations manufactured off-site such as elevators need to be assessed for the emissions from products criteria. The specification of internal finishes (regardless of whether they are installed on site or in the factory) will impact on VOC emissions. By specifying low VOC finishes, design teams will be encouraging manufacturers to consider the environmental impacts of their products.
10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency. Made applicable to UK and International NC V6.
 

Emissions from products – manufacturers’ calculations for paints and varnishes - KBCN0452

Manufacturers' calculations of VOC content, based on the constituent ingredients, can be used to demonstrate compliance with the testing requirement for paints and varnishes.

10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency. Scheme applicability updated.

Emissions from products – resin flooring - KBCN0980

Resin flooring products (such as epoxy floor coating) are assessed as ‘Resilient textile and laminated floor coverings’.
11-Oct-2022 Title updated for clarify and consistency. Wording simplified.

Emissions from products – rigid wall covering adhesives - KBCN00076

Rigid wall covering adhesives need to meet the standard listed for flooring adhesives.
11-Oct-2022 - Title renamed to standard naming format for clarity and consistency. Scheme applicability updated.
16-Jun-2015 - Published pending reissue of the technical manual UKNC2011/REISSUE UKNC2014/REISSUE UKRFO2014/REISSUE.

Emissions from products – scope of assessment - KBCN0212

General This issue covers any product installed or applied inside the inner surface of the building’s infiltration, vapour or waterproof membrane. Where this membrane is not present, it applies to the inside of the building envelope’s interior-facing thermal insulation layer. Only products that are installed or applied in parts of the building where their emissions are likely to affect indoor air quality need to be assessed. Paints and coatings Any decorative paints and varnishes that occupants are exposed to should be assessed. This is likely to include paints and coatings applied to walls, ceilings, floors, doors, etc. Whole products A finish applied to a product in the factory is assessed as a whole product, and not separately as a paint or coating. For instance, a wood panel has a finish applied in the factory. The whole panel, including all the elements that make up that panel, would need to comply with the requirements set for wood panel products in this issue. The finished product as a whole must meet the performance requirements / emission limits set in the manual.
11-Oct-2022 - Title amended for clarity and consistency. Content merged with KBCN0871.
10-Oct-2022 - Wording simplified. Scheme applicability updated.
16-Jun-2017 - Title and general principle amended to extend the applicability of the KBCN to all finishes. Paints specified for specialist applications covered in KBCN0872.
 

Emissions from products – specialist paints and coatings - KBCN0872

Where a paint or coating falls within: then the paint or coating must be assessed. Specialist paints and coatings are exempted from meeting the emission limits where there are no alternative products available that can perform the function, and still meet the emission limits. This must be clearly evidenced.
27-Oct-2022 Wording clarified. New compliance principle added from UKNC V6.
10-Oct-2022 Title amended for clarity. Scheme applicability updated.
13-Mar-2020 KBCN amended to clarify exceptions and applicability.
16-Jun-2017 Content merged with KBCN0212.

Emissions from products – testing to ISO 16000-10 - KBCN1134

Results of testing to ISO 16000-10 can be considered compliant with the relevant testing requirements of the emissions from construction products credit where the product manufacturer can demonstrate the results generated by testing to ISO 16000-10 correlate to results that would be achieved using EN 16516 or ISO 16000-9. This is because EN 16516 classifies ISO 16000-10 as an ‘indirect method’, which means “any simplified, screening, secondary, derived or alternative method. An indirect method can be applied if it provides a result that is comparable to or that correlates with the result of the reference method under the conditions applied. The validity of the correlation with the reference method is limited to the field of application for which it has been established.
11-Oct-2022 - Title amended for clarity and consistency. Scheme applicability updated.

Emissions from products – wall covering fabric - KBCN0724

For the 'Volatile Organic Compound emissions levels (products)' criteria: Any fabric specified as part of a wall covering should be assessed as part of the 'wall covering' requirements. It should not be assessed as part of the 'resilient textile and laminated floor coverings' requirements.
11-Oct-2022 Title amended for clarity and consistency. Wording clarified.

Emissions from products – alternative testing standard for paints - KBCN1003

Where stated in EU Directive 2004/42/CE, ASTMD 2369 can be used as an alternative the testing standard for paints where reactive diluents are present.
11-Oct-2022 - Title amended for clarity and consistency. Wording simplified.

Erratum – exemplary level requirements - KBCN0739

The exemplary level credits are awarded where volatile organic compound emission levels for products are not exceeded. Criteria 29 and 31 should refer to criteria 8-9 instead of 10-15.
11-Oct-2022 Title renamed for clarity and consistency. 
Technical manual to be updated accordingly in next reissue.

External lighting – architectural façade lighting - KBCN0650

Architectural façade (or other decorative) lighting, which does not provide users with lighting to perform tasks outdoors, does not need to be included in the assessment of external lighting. This Issue seeks to ensure that lighting levels are appropriate for tasks which building users will be undertaking outdoors.

External lighting – High frequency ballasts - KBCN0278

The requirement for all fluorescent and compact fluorescent lamps to be fitted with high frequency ballasts does not apply to external lighting.  

Glare control – adjacent buildings - KBCN1211

It is acceptable to account for surrounding buildings, structures or other permanent environmental features when using simulation modelling to assess the risk of glare, provided this accounts for both direct sunlight and reflected glare from glazing or reflective surfaces.

Glare control – alternative measures - KBCN0139

Alternative forms of glare control to those listed in the guidance can potentially be accepted, if it can be justified to the BREEAM assessor that the proposed system will effectively eliminate disabling glare and the assessor accepts this.

Glare control – blackout blinds - KBCN0447

Blackout blinds can be used to meet the glare control requirements. Where the criteria set an upper limit for transmittance value, but no lower limit, blackout blinds will meet this requirement.

Glare Control – no relevant areas - KBCN0429

If the scope of the assessment does not include any relevant building areas, as defined within the manual, the criteria for Glare Control can be considered as met by default. Only spaces that fall within the definition of relevant areas and are within the assessment's scope need to be assessed.  
22/06/17 Wording clarified
16/06/17 KBCN amended to exclude content of KBCN0146.

Glare control – no windows in relevant areas - KBCN0146

Where a ‘relevant area’ as defined in the manual does not include any windows, the glare control criteria can considered as met for this area. Note that the view out and daylight criteria would not be achieved in rooms with no windows. Where there are no windows in a room there would be no potential for disabling glare, so the aim of the credit would be achieved.

Glare control – residential institution and multi-residential bedrooms - KBCN0666

Assuming that occupants are generally elsewhere during daylight hours, lighting and resultant glare are not considered to be problematic for bedrooms in residential institution and multi-residential assessments. The only exception to this is where designated additional office working space is provided. In these circumstances it is the role of the assessor to determine if individual spaces should be determined as 'relevant building areas' in accordance with guidance provided. Glare control criteria apply to building areas where lighting and resultant glare could be problematic for users.

Glare control – use of tinted windows - KBCN0862

Solar control or 'tinted' glazing could potentially support the attainment of this requirement. However, the assessor must be satisfied and provide evidence to demonstrate that the particular glazing type, when used on the assessed building for a given location, is meeting this overarching aim of preventing disabling glare. It should be noted that whilst certain types of glazing, such as low emissivity glazing, may be slightly tinted, they may not necessarily be effective in reducing disabling glare. For facades receiving direct sunlight, tinted windows alone are unlikely to be sufficient in the majority of situations.

Glare control for roof lights - KBCN0319

Where roof lights are present, they must be considered when demonstrating that the glare control strategy provides adequate control/measures for minimising glare in that space. All sources of glare need to be considered when designing out the potential for disabling glare.

Glare control in residential areas - KBCN00040

Glare control criteria apply to building areas such as study bedrooms or facility management offices, where work or study will be carried out and where glare would hinder such activities. It does not apply to other residential areas.  

Hazards – Applicability of the issue - KBCN0541

The applicability of issue Hea 07 Hazard is related to the risk of natural hazards in the country, or region, in which the project is situated. This is reflected in the environmental weightings. The approach to this issue changes according to the country and to the scheme. BREEAM International New Construction 2013 and BREEAM International Refurbishment and Fit Out 2015 This issue should not be taken into consideration for countries which have a weighting for this issue equal or lower than 1%. The suggested threshold to start considering this credit is more than 1%. Where no risks are identified in the risk assessment report, this issue will not be applicable, even if the related weighting has a value higher than 1%. Thus before undertaking a risk assessment, it is recommended to investigate if the area might be subject to the natural hazards listed in the technical manual. BREEAM International New Construction 2016 Countries with no or very low risk, have a weighting of 0% for this issue. Thus, according to the BREEAM scoring and rating system, this issue should not be considered. The suggested threshold to start considering this credit is more than 0%. Where no risks are identified in the risk assessment report, this issue will not be applicable, even if the related weighting has a value higher than 0%. Thus before undertaking a risk assessment, it is recommended to investigate if the area might be subject to the natural hazards listed in the technical manual.

High frequency ballasts - KBCN0284

Fluorescent and compact fluorescent lamps are the only types of lighting where high frequency ballasts are required. The requirement does not apply to any other type of lamps.

Hotels – calculating the required number of water coolers in public areas - KBCN0184

The number of building users should be based on the maximum number likely to be using the public areas of the hotel, such as the gym or bar area,  at any time during a typical day. Hotel bedrooms can be excluded from the calculation.  

Indoor air quality plan – Guidance Note 6 - KBCN0618

Latest version: v2.1 August 2022 Guidance Note 6 provides guidance to assessors and project teams regarding the content and rigour of an Indoor Air Quality Plan (IAQP) as required by the Hea 02 Indoor air quality criteria in the BREEAM New Construction and Refurbishment schemes. It should not be interpreted as BREEAM criteria. It is intended to provide assessors and project teams with further, flexible information and guidance regarding the rigour, content and tasks of an IAQP. Download Guidance Note 6 (licensed assessors only) View all Guidance Notes (licensed assessors only)
10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency.

Indoor air quality plan – later consideration - KBCN1544

Where BREEAM has been engaged at a later stage in the project (for instance, at the beginning of a Post-Construction Assessment) the IAQ plan must still be produced. The late stage plan must clearly identify opportunities to improve indoor air quality that: The plan is focused on decisions and actions that can still be practically carried out. The indoor air quality plan is an on-going consideration that extends into the operational life of the asset.

Indoor air quality plan – scope - KBCN0294

Where possible, the indoor air quality plan must cover all items in the criteria. This means the plan must be completed for: Within these requirements, there is flexibility for the design team to use their professional judgement to determine what is appropriate to meet the criteria. Any exclusions must be clearly evidenced and justified. As the basis for effective asset management, the indoor air quality plan must be written in a consistent and comprehensive manner. The report must address relevant aspects as fully as possible within the scope of the development.
11-Oct-2022 Title updated for clarity. Wording clarified. Content merged with KBCN0556. Reference to KBCN1544 added. Scheme applicability updated.

Instant hot / cold drinking water systems - KBCN0136

In principle it is acceptable to use instant hot / cold water systems (for example zip taps) to meet the drinking water requirement, provided that their use is appropriate for the building type and user profile.  

Internal lighting levels where computer screens are used - KBCN0283

For areas where computer screens are regularly used projects can specify 300 lux, as referenced in CIBSE Lighting Guide 7, rather than the levels prescribed in the standard EN 12464:2011.
07/12/2021 Applicability to BIU V6 Commercial confirmed.
 

International suitably qualified professionals - KBCN1266

In some issues the International NC and RFO schemes prescribe specific requirements for suitably qualified professionals. We appreciate that some countries might have different recognition schemes in place, and these might differ from the BREEAM requirements. Where this is the case, assessors should submit a technical query with appropriate information, and we will review and approve each situation on a country basis.

Natural ventilation – use of CIBSE TM52 - KBCN0935

For a naturally ventilated building, it is acceptable for the thermal comfort limits and calculation methodology in CIBSE TM52: The Limits of Thermal Comfort: Avoiding Overheating in European Buildings to be used in place of ISO 7730:2005. BREEAM recognises that adaptive comfort models can provide more appropriate thermal comfort limits for naturally ventilated buildings.

Occupant control – BMS and degree of control - KBCN0175

A Building Management System controlled set point with local override controls limited to a set range would satisfy the occupant control requirement so long as the temperature range available to building users is confirmed as appropriate for the building type and user profile.

Occupant control – spaces requiring user controls - KBCN0170

This guidance is intended to clarify the types of area for which user controls are required or would be considered beneficial. Zoning is required in all areas of the asset where specified in the assessment criteria. Please refer to the specific requirements of the applicable BREEAM standard to interpret this guidance appropriately. User controls required Spaces where users are expected to have independent control over their environment. User controls not required Spaces where users are not expected to have independent control over their environment.
14-Dec-2022 - KBCN applicability updated to include BIU. Wording clarified, and amended for compatibility with BIU criteria.

Post-construction measurement – formaldehyde / VOC levels exceed limits - KBCN0258

If the measured formaldehyde / VOC concentrations were above the prescribed limits, the appropriate remedial action must be taken, as described in the IAQ Plan. The criterion requires confirmation of 'the measures that have or will be undertaken' however it does not specifically address re-testing. We would expect, however that the IAQ Plan should outline what remedial measures are appropriate depending upon the severity and type of the non-compliance with prescribed limits. Such measures may include re-testing as a matter of 'best practice'. Where levels are found to exceed these limits, the project team confirms the measures that have, or will be undertaken in accordance with the IAQ plan, to reduce the TVOC and formaldehyde levels to within the above limits.
10-Oct-2022 - Title amended to align with standard KBCN naming format for clarity and consistency. Made applicable to UK and International NC V6.

Post-construction measurement – sampling methodology and KPIs - KBCN0380

When testing for VOCs post-completion and pre-occupancy, a representative sample of the building needs to be carried out. Each sample TVOC and formaldehyde measurement needs to achieve the threshold levels individually, either in the initial testing or after remedial measures have been implemented. This ensures that all tested areas of the building are below the limits, and that areas of non-compliance are not ‘averaged out’. 'When providing KPI test results for air quality post-construction / pre-occupancy within scoring and reporting tool, where the limits are exceeded and remediation and re-testing are carried out, the figure should be an average for the whole building post-remediation, as this is the key figure that reflects the building at its certified state'. Where testing is not a requirement of the IAQ Plan and this is not carried out, the original testing figures should be entered and the assessment report should provide details of the remediation measures undertaken to reduce these to within the prescribed limits.
10-Oct-2022 Title amended to align with standard KBCN naming format for clarity and consistency. Scheme applicability updated.
06-Dec-2017 Amended to account for situations where re-testing is not required by the IAQ Plan.

Post-construction measurement- TVOC concentration using BS ISO 16000-6: 2021 VOCs in air by active sampling - KBCN1642

Where BS ISO 16000-6: 2021 VOCs in air by active sampling is used, the TVOC concentration measurement can be performed over a 40-60 minute period.

Potential for natural ventilation – areas exempted - KBCN0806

For projects where the majority of a building's occupied spaces will meet the criteria to achieve the potential for natural ventilation credit, but a relatively small area will not comply due to functional requirements of the space, (e.g. a lecture theatre), the credit can be awarded where this approach can be justified. The intention is to encourage the design of buildings where a strategy of (potential for) natural ventilation has been implemented as far as practically possible, given functional constraints. 

Potential for natural ventilation – mechanically ventilated and mixed mode assets - KBCN1533

Scope of KBCN This KBCN clarifies the associated compliance note for this credit. Clarification Mechanically ventilated and mixed mode assets can potentially achieve the 'potential for natural ventilation' credit by:
  1. Meeting the relevant criteria for room depth and glazing area OR, where this is not possible:
  2. Show through modelling that the building has the potential to be ventilated entirely via a natural ventilation strategy.
For 2. the second paragraph of the CN allows flexibility in demonstrating adaptability to an entirely natural ventilation strategy. An asset can allow for mechanical ventilation for ≤ 5% of its annual operating hours to boost ventilation rates, and (for this credit) can still be considered to be a fully naturally ventilated strategy. ≤ 5% mechanical ventilation requirement The focus of this credit is to demonstrate future adaptability to introduce fresh air into the asset for occupant comfort, so this requirement relates only to the time that mechanical systems are used to drive air through the asset. The use of active heating / cooling is not considered in this calculation. Natural Ventilation Heat Recovery Units (NVHR) systems can also be used, provided it meets this ≤ 5% requirement. ≤ 5% is a weighted average over all of the asset's occupied spaces. The basis for the weighting will be determined by the modelling software used. Scope and time scale of modelling The modelling covers all occupied spaces. Where relevant, exclusions are allowed - see related KBCNs for details. The modelling period is one year, during the asset's operating hours. The modelling must be based on a plausible scenario that is realistic. This means that:
22-Oct-2022 Content from KBCN1126 merged to this KBCN.

Potential for natural ventilation – shell only assessments - KBCN0408

Where compliance depends on a speculative layout which is unknown, it is the responsibility of the design team to demonstrate that it is feasible for a future tenant to achieve compliance in the relevant areas via the use of a notional layout. This ensures that the shell allows the potential for compliance, and if this can be demonstrated the credit may be awarded.  

Potential for natural ventilation – use of doors to comply - KBCN0690

Doors can only be used to demonstrate potential for natural ventilation where: In all cases, the use of doors must be clearly and robustly justified by the Assessor.
19-Oct-2022 - Wording clarified. Scheme applicability updated.

Provision of fresh drinking water – risk of contamination - KBCN0302

Mandatory requirements relating to microbial contamination must be met for all buildings, however, the provision of fresh drinking water only applies where there are relevant areas in the building types. It may be justified that the drinking water requirement is not applicable to achieve the credit.    

Provision of fresh drinking water – suitable location - KBCN0825

Supply of accessible potable drinking water should be provided in a suitable location in order to ensure potable, clean and fresh water is easily reachable by all staff and permanent building users.

Reporting PPD and PMV Figures - KBCN0867

The PMV (Predicted Mean Vote) and PPD (Predicted Percentage Dissatisfied) values need to be entered into the scoring & reporting tool for data recording purposes. The thermal modelling specialist should be able to provide values for both the PMV and PPD for the asset. The values to report are the observed range of values for PMV and PPD: If the software or calculation method used does not generate these PMV / PPD metrics, they do not have to be provided. [accordion] [accordion_block title="Example"] An asset has the following thermal comfort ranges across its occupied spaces: [/accordion_block] [/accordion]
15.09.22 Wording and example clarified.

Restricted movement within a secure perimeter - KBCN000009

Where the movement of pedestrians, cyclists and vehicles is tightly controlled within a secure perimeter due to security considerations, these areas may be excluded from the safe access criteria. Where the whole assessment is within such a zone, the credit may be awarded by default.
08 Jun 2022 Applicability to UK NC2018 confirmed

Risk assessment – appropriate person - KBCN0539

If an officially recognised body or a local/city authority are in charge of conducting an assessment of the natural risks for a development, and this meets the BREEAM criteria, this can be accepted as meeting compliance.  In this case the body/authority can be considered an 'appropriate person'.

Safe access – vehicle delivery routes - KBCN1046

Vehicle delivery routes which cross cycle or pedestrian routes may be acceptable provided there are adequate physical control measures in place to ensure safe access and thus minimise the possibility of delivery vehicles coming into conflict with cyclists and pedestrians. Examples of such measures could be vehicle barriers or retractable vehicle bollards, which only allow access to delivery vehicles when required and whose operation and controls account for cycle and pedestrian movements.
18 Mar 2021 wording clarified
07.06.2018 Intent and wording clarified.

Safe access criteria requirements for small infill developments and extensions - KBCN0810

For smaller infill developments (typically those with a total gross floor area of less than 1,000m2) where there is no opportunity to make changes to the surrounding site or access to the building itself (other than those directly related to connecting building access points to existing pathways etc.), it is recognised that full compliance with the BREEAM criteria for safe access may not be achievable.  This applies to developments where either: In such instances the existing site layout should undergo a risk assessment against the BREEAM 'Safe Access' criteria to identify areas where there is potential for enhancement across the site.  The findings should be reported to the client and design team and any non-compliant aspects should be resolved as far as practically possible within the scope of the project, however there is no express requirement to achieve full compliance in every respect.  Where the assessor is satisfied that the above requirements have been met,  the credit for 'Safe access' can be awarded.
31/03/17 Reference to achieving 'Security' credit removed

Studio Bedroom Daylighting Calculations - KBCN0733

Where studio rooms in multi-residential projects include multiple area types (e.g. A kitchen and lounge area), compliance can be achieved where either: 1. The entire studio room meets the more onerous requirements or 2. The room is nominally divided into the relevant spaces and the requirements are applied to each as appropriate.

Thermal comfort – Changing rooms - KBCN1133

Whilst thermal comfort in changing rooms may be considered as significant, such spaces are, generally, outside the scope of this Issue, as they would not fall within the definition of an 'occupied space'.
17/06/2019 - This supersedes the advice previously provided in this KBCN, which was published in error on 13/06/2018

Thermal modelling for large scale projects - KBCN1171

In cases where the scale of the project makes it unfeasible to provide thermal modelling for every space, it is acceptable to demonstrate compliance with a representative sample of floors or rooms, ensuring any worst case scenarios are included.

Users with special hearing and communication needs - KBCN0969

Criterion 1c aims to ensure that the acoustician has considered designing the building to better meet the acoustic requirements for users with special hearing and communication needs. The extent and scope this should cover will depend on the building type. The following information, taken from The UK Department for Education ‘Acoustic design of schools: performance standards building bulletin 93' (February 2015) provides clarity as to the type of users typically to be considered: Users with special hearing or communication needs includes, but are not limited to, people with permanent hearing impairment or with severe or complex needs, including: Such users should be considered by the suitably qualified acoustician, along with the other points a-d when giving early design advice regarding room layout, sound insulation and reverberation times etc.
01/03/2019: Amended to clarify that this is a 'typical' list of users, but does not impose a new requirement.

Ventilation – distance between air intakes and exhausts - KBCN0638

The minimum distance required between the building's air intakes and exhausts is described by r. Where the distance does not meet r, the design team must either:
12-Jan-2023 - Value r clarified to account for different requirements in applicable schemes.
18-Nov-2022 - Requirements clarified. Title amended for clarity.
11-Oct-2022 - Scheme applicability updated. Wording clarified. Reference to EN13779 removed for international assessments, see KBCN1054.

Ventilation – e-cigarettes - KBCN1014

The use of e-cigarettes and vaporizers is considered equivalent to smoking. A smoking ban must also include a ban on e-cigarettes and vaporizers.
11-Oct-2022 - Scheme applicability updated.
   

Ventilation – single room MVHRs - KBCN1042

Single room mechanical ventilation heat recovery units do not need to show that the air intake and exhaust are a suitable distance apart. However, the air intakes of these units must be located to minimise intake of other potential external pollutants.
11-Oct-2022 - Title amended for clarity and consistency. Wording simplified. Scheme applicability updated.

View out – alternative method of compliance for fixed workstations - KBCN1484

In relevant spaces that include fixed workstations* (such as a built-in cash registers or reception desks) an alternative method can be used. This is based on the number of compliant workstations. For instance, where the requirement is for 95% of the relevant area to comply, 95% of the fixed workstations must have a compliant view out, rounded up to the nearest workstation.   Example A retail assessment has 35 built-in cash registers, 95% of which must comply with the view out criteria. 35 x 0.95 = 33.25, rounded up to 34. The requirement is met for this area if 34 registers comply with the criteria.   Where an asset includes a mix of relevant areas; both fixed workstations and flexible areas, compliance for the whole assessment must be demonstrated for all areas, as appropriate, based on either area or number.   *freestanding desks and other items of moveable furniture cannot be considered as fixed workstations, regardless of whether their locations are pre-determined.

View out – Calculating the glazing to wall ratio - KBCN1506

This should be calculated based on the glazed area of window, expressed as a percentage of the area of the external wall in which the window sits. Where the ceiling height of the room is unusually high, relative to the window height, the wall area can be calculated based on a standard ceiling height for the building type.

View out – Corrections to Table - KBCN1136

The values for distance from window to workplace in the View out Table are incorrect. The Table should read as follows:  

View out – eye level - KBCN0581

BREEAM defines an adequate view out as being at seated eye level (1.2 – 1.3m) within the relevant building areas. However, where occupants will not have the option to be seated, for example in some industrial operational areas where the work being undertaken requires occupants to remain standing, the height of the view out can be changed accordingly to suit the eye level of occupants. All other view out requirements have to be met and clear justification provided for changing the height/level of the view out. In some relevant building areas, occupants may not be sitting down to undertake tasks. Allowing the view out height requirements to be changed accordingly ensures building occupants gain maximum benefit from the view out.   

View out – internal view within an atrium - KBCN1240

Where the criteria are otherwise met, an internal view across an unobstructed atrium void can be considered compliant. Internal views are generally not acceptable, however where it is physically impossible to obstruct the view with partitions, equipment or furniture, this can be accepted at the discretion of the assessor.

View out – no relevant areas - KBCN0876

If the scope of the assessment does not include any relevant building areas, as defined within the manual, the criteria for 'view out' can be considered as met by default. Only spaces that fall within the definition of relevant areas and are within the assessment's scope need to be assessed.

View out – percentage area - KBCN0166

For the view out credit, compliance must be demonstrated for the percentage of the floor area in each relevant building area, rather than the percentage of the total relevant building area in the building.
14/2/17 Wording amended to clarify that the percentage must be achieved for each 'relevant building area'.

View out – relevant areas - KBCN0268

The aim of the View Out criteria is to allow occupants to refocus their eyes from close work. Relevant areas are spaces where close work in a fixed position is carried out for sustained periods of time. The view out criteria are therefore not applicable to occupied areas such as meeting rooms, or other spaces where such close work is not being carried out. Where rooms contain areas of different functions, only relevant areas should be assessed. In this case a notional line can be drawn on the plans and calculations made based on these relevant areas only. However, spaces such circulation routes or other transient spaces within a relevant area can only be excluded if the route or area is clearly defined by the building layout. If this is arbitrary or based solely on a proposed furniture layout, it cannot be excluded. Features of the building layout which may be considered as dictating a function area would include, for example, the position of doors or fixed furniture such as a reception desk or canteen servery.
07-Oct-2022 Additional paragraph added to clarify how function areas must be defined. 
21-Sep-2022 General principle of 'relevant area' added, and applicability of KBCN extended to BIU V6 Commercial.

View out – rooms used for security or other critical functions - KBCN1040

The View out criteria are not applicable to rooms containing security or critical systems or sensitive material, such as CCTV monitoring rooms. Where it can be demonstrated that the presence of compliant windows would compromise a critical function of the space, the criteria can be considered not applicable.

View out for commercial kitchens - KBCN1216

It is not necessary to provide a view out for commercial kitchens. This is because in such a space it is likely that kitchen staff will move around, doing various tasks. This makes the requirements for the view out to rest the eyes unnecessary.

Water Fountains - KBCN0648

Water fountains are generally not accepted to demonstrate compliance with Hea 04 on the basis that a typical water fountain (of the type which projects a jet of water upwards towards a user's mouth) does not allow a water bottle to be filled, and therefore does not encourage adequate fluid intake. However, if it can be demonstrated that a particular type of water fountain is specified that addresses the issues of bottle filling, such as a water fountain with an additional bottle-filler, this can be considered acceptable.

Zoning and control – dimming - KBCN1018

Localised dimming controls installed in line with the criteria, along with a master on/off switch, can be considered as meeting the aim of the requirement for 'controls' in open plan offices. The aim is for occupants to have local control over their lighting and maintain comfortable lighting levels.

Zoning and control – PIR in circulation spaces - KBCN0332

PIR controls can be deemed compliant in circulation spaces such as corridors. In this instance 'separate occupant controls' are not required. The requirement for user control is so that the building users can have direct control over their immediate work environment to ensure it is suitable for their personal needs. In circulation spaces, occupancy is transient and PIR control in these spaces is acceptable.  

Zoning and occupant control – access to lighting controls - KBCN00032

The relevant areas for the criteria apply only to areas where users are expected to have control. For instance, this means that areas intended for the general public, or a shop floor would not be expected to have lighting controls. The general principle which applies to user access to general environmental controls (heating, cooling, ventilation) may also apply to access to lighting controls. See KBCN0170. However, the the exact approach may differ between the two types of systems and assessor judgement must be used to determine compliance. In all cases zoning is required in all areas of the asset where specified in the assessment criteria. Please refer to the specific requirements of the applicable BREEAM standard to interpret this guidance appropriately.
14-Dec-2022 - KBCN applicability updated to include BIU. Wording updated. Link to KBCN0170 created.

Zoning and occupant control – PIR detection systems - KBCN0335

The aim of the Health & Wellbeing category is to recognise ways to benefit occupants through giving them control of their lighting environment. Without manual overrides, presence or absence detection lighting controls (such as PIR detection systems) are not compliant with the criteria. BREEAM recognises the energy efficiency benefits of detection systems in buildings through the Energy category. In some cases, the design team may have to prioritise one particular lighting strategy to the detriment of achieving a credit elsewhere.
28 04 2021 Wording amended to include absence detection systems.
18 09 2017 Wording amended to clarify the meaning.
 

Zoning and occupant control – whiteboards and display screens - KBCN1433

Whiteboards and display screens in dedicated teaching or presentation spaces require separate zoning and control for lighting, as specified in the criteria. Lighting around whiteboards and display screens which are typically found in general office areas, meeting rooms, or in other generic spaces do not require separate zoning and control to meet the criteria. In such cases, the assessor should provide justification. Whiteboards and display screens in dedicated teaching / presentation spaces are likely to be used frequently, and require appropriate zoning and control. An increasing number of offices and meeting rooms now include display screens - however separate zoning and control may not be appropriate.

Zoning of lighting – speculative buildings - KBCN0197

Compliance note CN1 confirms that in speculative buildings, the lighting control system must have the capacity to be zoned as required, once the final tenant is known and occupancy patterns/layout are agreed. Alternatively compliance can be demonstrated using Shell and Core options 1-3.    

[KBCN withdrawn] ~ Areas assessed for formaldehyde and TVOC - KBCN1008

This KBCN is no longer applicable. Please refer to KBCN0871 for scope of 'Emission levels (products)' and 'Other information' section of the technical manual for scope of 'Emission levels (post-construction)'. Superseded text: Products applied or installed in parts of the building likely to affect the indoor air quality and impact the wellbeing of building users need to be assessed. Areas are not excluded on the basis of how long building users are present in those areas.
27-Feb-2018 - KBCN N/A due to ambiguity of applicability to criteria

[KBCN withdrawn] ~ Erratum – Table 1 in GN22 v2.5 - KBCN1436

Table 1 in V2.5 of GN22 has two footnote symbols missing: • Product Type column – Paints and varnishes should read Paints and varnishes* • Product Type column – Wood panels should read Wood panels^
10-Oct-2022 KBCN withdrawn as GN22 has been re-issued with fixes.

[KBCN withdrawn] ~ GN22 – Scheme version applicability - KBCN0646

Table 1 is for the use of any version of a scheme where the first version was released pre-December 2015, and table 2 is for the use of any version of a scheme where the first version was released post-November 2015.
10-Oct-2022 This KBCN has been merged with KBCN0719. KBCN withdrawn.

[KBCN withdrawn] ~ Indoor air quality plan for shell only and shell and core assessments - KBCN0556

The indoor air quality plan must be completed for the scope of works being BREEAM assessed. This applies for shell only and shell and core assessments, as well as fully fitted. Assessors should use their judgement to determine the applicability of each aspect of the requirements for IAQs and ensure that the report addresses relevant aspects as fully as possible within the scope of the development.
11-Oct-2022 KBCN withdrawn. Content merged with KBCN0294.

[KBCN withdrawn] ~ Natural Ventilation Heat Recovery Units - KBCN1126

Natural Ventilation Heat Recovery Units (NVHR) systems can be used to support a natural ventilation strategy where it can be demonstrated that openable windows provide sufficient fresh air to the building for the significant majority of the time that the space is occupied. The assessor will need to use their professional judgement to determine a 'significant majority of time' and be able to justify this within the assessment report.
22-Oct-2022 Content merged with KBCN1533 and clarified with additional guidance on mixed mode systems. This KBCN withdrawn.

[KBCN withdrawn] ~ Scope of product assessment for VOCs - KBCN0871

For the purpose of this Issue, this covers any product installed or applied inside of the inner surface of the building’s infiltration, vapour or waterproof membrane or, where not present, inside of the inner surface of the building envelope’s interior facing thermal insulation layer. Only products that are installed or applied in parts of the building where their emissions are likely to affect indoor air quality need to be assessed.
11-Oct-2022 - Content merged with KBCN0212. KBCN withdrawn.

[KBCN withdrawn] ~ VOC product types – other - KBCN0698

Where a product does not appear to fit into any of the defined VOC product types listed in the manual this does not mean it is automatically exempt from being assessed. If it is similar to one of the listed product types and clearly could have an impact on VOC levels it should normally be assessed. In such cases the supplier/manufacturer should seek to demonstrate that their product meets the equivalent standards required for the closest matching product type.
19-Oct-2022 - KBCN replaced by KBCN0872.

[KBCN withdrawn] ~ VOC testing – alternative methods for compliance for paints and varnishes - KBCN0492

Manufacturers' calculations of VOC content, based on the constituent ingredients, can be used to demonstrate compliance with the testing requirement for paints and varnishes instead of ISO 11890-2:2013.