New Construction / International / V6 / 03 - Energy /
Ene 01 - Reduction of energy use and carbon emissions
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.
Calculating EPR where there are multiple BRUKL/NCM outputs - KBCN1083
Where more than one NCM output is produced for a development, which is registered as a single assessment, an area-weighted average should be used to calculate the number of credits to be awarded.
This does not apply where the ‘similar buildings’ approach is used.
For for projects in England assessed under UKNC V6.0, please see KBCN1618
Projects assessed under UKNC V6.1 can upload multiple BRUKL.inp files for a single assessment and the platform will perform the calculation. See KBCN1618
Each energy performance output from the NCM output (actual CO
2/m
2 notional CO
2/m
2 etc.) must be area-weighted to produce area-weighted average values entered into the scoring and reporting tool. When applying this method, please include your area-weighting calculations and outputs as supporting evidence.
The following provides an example of an area-weighting calculation for two building areas A and B, each of 500m
2, for which separate NCM outputs are available:
For building area A:
Notional building heating and cooling energy demand: 230 mJ/m²
Actual building heating and cooling energy demand: 200 mJ/m²
Notional building primary energy consumption: 300 kWh/m²
Actual building primary energy consumption: 280 kWh/m²
TER: 40 kg CO₂-eq/m²
BER: 30 kg CO₂-eq/m²
For building area B:
Notional building heating and cooling energy demand: 150 mJ/m²
Actual building heating and cooling energy demand: 140 mJ/m²
Notional building primary energy consumption: 200 kWh/m²
Actual building primary energy consumption: 190 kWh/m²
TER: 40 kg CO₂-eq/m²
BER: 38 kg CO₂-eq/m²
Area-weighted values for building areas A and B (of total floor area 1000m2):
Notional building heating and cooling energy demand: 230*500/1000 + 150*500/1000 = 190 mJ/m²
Actual building heating and cooling energy demand: 200*500/1000 + 140*500/1000 = 170 mJ/m²
Notional building primary energy consumption: 300*500/1000 + 200*500/1000 = 250 kWh/m²
Actual building primary energy consumption: 280*500/1000 + 190*500/1000 = 235 kWh/m²
TER: 40*500/1000 + 40*500/1000 = 40 kg CO₂-eq/m²
BER: 30*500/1000 + 38*500/1000 = 34 kg CO₂-eq/m²
These area-weighted values are then used to calculate the overall EPRNC value.
20 Sep 2023 - Minor corrections, applicability to INC V6 confirmed and cross-reference to UKNC V6 guidance added.
14 Jun 2023 - Note added to confirm this is integrated into the platform for UKNC V6.1 in all countries.
24 Aug 2022 - Note added to confirm this is N/A to UKNC V6 for projects in England
07 Feb 2022 - Reference to 'BRUKL' amended to 'NCM output' to clarify for non-UK assessments
31 Oct 2018 KBCN clarified. Reference to EPRs and calculation example added
Erratum – up to V6 – checklist A5 – lighting - KBCN1629
Item 1 of Checklist A5 states:
This is incorrect. The requirements should be:
- Non-day lit areas with intermittent occupancy must have occupancy controls.
- Day-lit areas must have daylight detection controls.
- The controls conform to either ASHRAE 90.4 or California Energy Code.
GN48 Ene 01 Calculation Methodology – BREEAM International NC V6 - KBCN1487
Latest version: v1.1, February 2022
Guidance Note 48 describes the calculation methodology for energy performance under the Ene 01 issue of BREEAM International New Construction Version 6. The methodology has been revised for the new version of the scheme and uses a triple metric approach that addresses energy demand, energy consumption, and CO
2 emissions. The aim of using this approach is to recognise and promote designs that minimise energy consumption in buildings, and reduce the carbon emissions from that energy use.
Download Guidance Note 48
View all Guidance Notes (licensed assessors only)
Internationally approved Ene 01 calculation software - KBCN1177
The following calculation software are approved internationally and can be used, provided local weather files are available in the country of the assessment.
Please make sure the approved version, in brackets, is used. If you wish to use a different one, please submit a technical query to
[email protected] providing details of the changes.
- IES VE (all versions from 2014 onwards).
- Design Builder (version 4 onwards).
- TRNSYS (version 17 onwards).
- eQUEST (versions 3.63b and 3.64 onwards).
- Energy Plus (version 3 and version 6 onwards).
- EDSL Tas (v9.5.0 onwards).
Any software that has been approved on the ASWL for a particular country can be used in other countries, provided relevant weather files are available.
26-Mar-2024 - Scheme applicability updated.
08-Aug-2022 - Applicability to BREEAM Communities 2012 confirmed.
30-Jun-2023 - Added note relating to software approved for a particular country.
LZC – Local regulations and private wire arrangements - KBCN1658
Where local regulations do not permit electricity generated by on-site renewables to be connected directly to the building, and where evidence of the relevant regulations is provided at QA, the requirement for a private wire arrangement can be waived.
On-site LZC – whole site shared connection - KBCN1424
To be recognised in BREEAM, the on-site Low and Zero Carbon (LZC) technology must have a direct physical connection to the assessed asset.
OR
Where the LZC technology is;
- Located on the same site,
- Is owned and managed by the same organization as the assessed building, and
- Where it is impractical to physically connect the assessed building to the system,
It is acceptable to allocate the renewable energy generated proportionally as a calculation of the asset's predicted energy consumption compared to the total energy consumption of the whole site.
To allocate renewable electricity by proportional consumption:
- Obtain the total annual renewable electricity generated on-site.
- Exclude all renewable electricity which has been exported to the grid.
- Determine the respective electricity consumption of all assets on the whole site (predicted for new builds and measured for existing assets).
Where consumption data is missing, renewable electricity must not be allocated to the assessed asset. In this case, it is assumed that all electricity consumed is sourced from the grid.
17-Jan-2024 - Applicability BIU V6 Ene 13 removed, as this approach is not applicable to assessing the area of PV fitted.
21-Dec-2022 - Applicability to In-Use V6 confirmed.
24-Aug-2022 - Applicability to UKNC V6 confirmed.
Prediction of operational energy consumption – alternative route to Excellent minimum standard - KBCN1336
Where the ‘Prediction of operational energy consumption’ criteria are achieved, the minimum standard for Excellent in Ene 01 is met.
This is independent of meeting any minimum credit score in the issue to achieve the Excellent minimum standard. See
KBCN1602.
Substantial improvement
To meet this minimum standard, the asset must show a
substantial improvement in operational energy performance, following the ’Prediction of operational energy consumption’ criteria.
This 'substantial improvement' is defined as achieving 4 credits using amended metrics generated using the dynamic simulation modelling and for:
- UK: the Ene 01 methodology that applies to your scheme version.
- International: assessments using the Option 1 approach.
Amended definitions
Performance is calculated based on amended definitions of an actual and a notional building:
Amended actual building:
- Actual fabric.
- Expected actual occupancy.
- Actual building servicing systems.
Amended notional building:
- Notional fabric.
- Expected actual occupancy.
- Notional building servicing systems*.
*The notional building servicing system may be replaced with a gas boiler as the heat generation source.
Where the performance improvement over the amended notional building does not achieve 4 credits, the BREEAM Excellent standard may still be met. Robust evidence must be provided showing that this level of performance improvement is not possible, based on constraints outside of the control of the project team.
Additional notes for UK schemes
Projects assessed under UKNC V6.1 can manually input amended figures from the modelling into the platform to demonstrate the 'substantial improvement'. See "DSM Alternative Ene 01 inputs" in BREEAM Projects for this issue.
For the energy modelling and reporting criteria, the CO
2 metric can be calculated using either:
08-Nov-2023 - Additional wording and link to KBCN1602 added to clarify situation for UK simple buildings.
26-Jun-2023 - Content updated to apply to International schemes. Title and wording clarified. Text on manual errata in NC 2018 3.0 moved to KBCN1602.
14-Jun-2023 - Note added to confirm this is integrated into the platform for UKNC V6.1 in all countries.
24-Aug-2022 - Content updated and applied to UKNC V6
19-Aug-2019 - Clarification for UKNC 2018 3.0.
Shell only – energy demand parameter not available - KBCN0576
In 2016 New Construction (NC) international scheme shell only assessment, energy demand is the required assessment metric for Ene 01. A lot of international assessments are unable to provide the energy demand performance information, and as such, this approach won’t always be possible. Where there is no demand parameter available, follow the same approach as outlined for ‘shell and core’.
26-Nov-2024 - Scheme applicability updated.
Information correct as of 27thDecember 2024. Please see kb.breeam.com for the latest compliance information.