New Construction / International / 2016 /

07 - Waste

Information correct as of 26thOctober 2021. Please see kb.breeam.com for the latest compliance information.

Adaptation to climate change strategy study – timing - KBCN0533

Late consideration of the climate change adaptation strategy study, might reduce the study to a ‘paper exercise’, with minimal value to the project. However, if the assessor is satisfied that there is clear justification for the strategy being developed at a slightly later stage (i.e. early RIBA stage 3) AND there is clear evidence that the strategy has achieved the intended outcomes (i.e. the later consideration has been in no way detrimental to the outcomes of the strategy study/appraisal and the benefits can still be realised on the project), then this will be sufficient for compliance. In any case, all other requirements of the issue must be met for the credits to be awarded. The requirements for the timing of the climate change adaptation strategy are intended to ensure that the benefits of these strategies are realised through early consideration.

Alternatives to composting - KBCN0465

In anaerobic digesters, organic waste is digested by micro-organisms which break down fats, oils and grease. Digesters where the only output is water that is safe to discharge into drains and sewers are acceptable alternatives to composting. Macerators which simply reduce solids into small pieces through a shredding or grinding process and flush the residue into the drainage system are not an acceptable alternative to composting.

Apportioning foundations where not all floors are assessed - KBCN0643

Where a development does not include all the storeys of a building, not all of the aggregates used in the building foundations need to be included in the assessment.  Any apportioning must be justified and calculated by a structural engineer, and it is the responsibility of the assessor to ensure that the process used is appropriate, robust and meets the aim of the credit issue.

Considering Sand and Cement Replacements - KBCN0181

Neither sand or cement replacements should be taken into account when assessing the percentage of recycled or secondary aggregate used in a project. The recycled aggregates issue only assesses the use of coarse aggregates.  
29/03/2017 Title amended and additional reference to cement substitutes added
 

Contractor not yet appointed at the design stage - KBCN000002

Where the contractor has not been engaged at the design stage certification, it is acceptable to award the credits based on a commitment. This commitment must be from a suitable member of the design team, and must detail the targets and criteria which must be met. Evidence must also confirm that the details in the commitment will form part of the contractual requirements.  

Contractual agreements for Shell Only / Shell & Core assessments - KBCN0942

For Shell Only and Shell & Core (RFO Part 1, Part 2, and combined Part 1 & 2) assessments, all relevant criteria are applicable. Contractual agreements confirming future provision of spaces are not acceptable. Evidence must be provided showing waste storage space(s) that are suitably sized, dedicated and unlikely to be used by the future tenants for other purposes. While the location of the space/spaces may change when fitting out, at this stage a space that is conveniently located for the deposit and collection of operational waste must be provided.

Demolition – external guidelines (incl BS 6187) - KBCN0630

Independent standards exist and some are referenced in the BREEAM manual and can be used to provide additional guidance for clients/design teams. Unless explicitly stated they are not 'deemed to satisfy' BREEAM criteria and assessors must demonstrate that BREEAM criteria have been met in the usual way. One such standard is BS 6187:2011 which gives good practice recommendations for the demolition (both full and partial) of facilities, including buildings and structures. The standard is therefore applicable to demolition activities undertaken as part of structural refurbishment. It also covers decommissioning. Unless explicitly stated external standards do not automatically satisfy BREEAM criteria and assessors must demonstrate that BREEAM criteria have been met in the usual way. 

Demolition records not available - KBCN1009

Where demolition records are missing, either wholly or in part, the credit available for diversion of construction and demolition waste from landfill cannot be achieved. This includes instances where demolition was conducted under a separate contract or by a third party on behalf of the developer.

Excluding applications from assessment - KBCN0875

Where a structural engineer has determined that recycled or secondary aggregate cannot be used in line with the criteria for a particular application, or where they will not allow the minimum BREEAM level to be used, that application can be excluded from the assessment. Where the engineer allows some content to be used, this percentage must still be specified in the excluded application. The engineer's decision must be suitably justified (for example following the BS8500 series and associated standards) and must be provided as evidence for the BREEAM assessment.

Excluding excavation waste from ‘Diversion of resources from landfill’ - KBCN0226

Excavation waste should not be included and assessed against the requirements under ‘Diversion of resources from landfill’. This also applies to BREEAM Communities RE05 - 3rd/4th credits.  

Existing materials recycled on site - KBCN0813

When existing elements are recycled (ie crushed and used as aggregate) on site, they can contribute to awarding credits as recycled aggregates. This issue aims to recognise and encourage the use of recycled and secondary aggregates and addresses waste rather than materials. It refers to recycled aggregate obtained on-site or off-site, based on materials identified as waste and removed during construction works. 
Previous incorrect KBCN text amended. CN 'Aggregates in existing applications' to be amended accordingly in next reissue of the RFO Technical manuals.

External works – waste reporting requirements - KBCN1379

Waste arising from external works does not need to be included within the calculations for construction resource efficiency. To do so would be incongruous with reporting waste relative to the building's floor area. This follows the logic of excluding excavation waste from this criterion. However, waste from external works should be addressed in the RMP and should also be reported in the calculations for the Diversion of resources from landfill credit, which is not reported relative to the building's floor area.

Functional adaptation strategy study – content - KBCN0930

To achieve compliance with Wst 06, the building-specific functional adaptation strategy study should consider all the items listed in the relevant compliance note 'Functional adaptation strategy study'. Due to site specific constraints, it may not always be possible to pursue all of the items listed. In these cases, any omissions must be clearly justified in writing when submitting as evidence.

Functional adaptation strategy study – timing - KBCN0730

Late consideration of the strategy appraisal, might reduce the study to a ‘paper exercise’, with minimal value to the project. However, where the assessor is satisfied that there is clear justification for the study being developed at a slightly later stage (i.e. early RIBA stage 3) AND there is clear evidence that the strategy has achieved the intended outcomes (i.e. the later consideration has been in no way detrimental to the outcomes of the strategy study/appraisal and the benefits can still be realised on the project), this will be sufficient for compliance. In any case, all other requirements of the issue must be met for the credit to be awarded. The requirements for the timing of the functional adaptation strategy study are intended to ensure that the benefits of the study are realised through early consideration.

Granular fill and capping - KBCN1378

Granular fill and capping only refers to roadworks and not building foundations.

Home composting facilities – clarification - KBCN0927

Home composting facilities are individual composting containers placed within the kitchen area or communal space for each self-contained dwelling, bedsit or communal kitchen. These containers are either emptied into local on-site communal facilities or are collected by composting collection services run by the waste collection authority. Individual composting containers should be:
  1. Located in a dedicated, non-obstructive position.
  2. Easily accessible to all users.
  3. Durable, low maintenance and cleanable.
  4. Enclosed to manage odour and pest issues.

Labelling and signage – Shell only/Shell & core assessments - KBCN1380

For a shell only or shell & core assessment, in terms of labelling individual bins, a written commitment from the developer is acceptable as future waste streams may be unknown and it is recognised that the bins may not be provided by the local authority/waste management company at the time of certification. However, it is a requirement of criterion 1 that the space itself is clearly labelled, ie. has appropriate signage, to indicate that it is to be used for storing recyclable waste

Multi-Residential: Internal recyclable waste container if waste is sorted off site - KBCN0354

Where the Local Authority or waste management company for the scheme provide evidence confirming that recyclable waste will be sorted after they have collected it from site, it is acceptable to provide one internal storage bin of a minimum capacity of 30 L rather than 3 separate internal bins. The relevant recycling scheme must collect at least 3 of the following materials; paper, cardboard, glass, plastics, metals or textiles.    

Multi-residential: Waste storage shared by more than six bedrooms - KBCN0856

Where multi-residential buildings contain communal facilities shared by more than six bedrooms, the requirement for total waste storage can be increased on a pro-rata basis to demonstrate compliance. For instance, if the standard requirement is 30L for six bedrooms, this equates to 5L per bedroom. Where assessing a flat with eight bedrooms, this requirement increases to 40L (8 x 5L). The minimum size of individual containers remains unchanged as per the criteria.

Multiple developments monitoring construction waste on a site - KBCN00036

Where the same contractor is working on a site with more than one development, a single Site Waste Management Plan (SWMP)/Resource Management Plan (RMP) can be produced to demonstrate compliance, if it can be justified that separation of the waste would be impractical. Where the developments are of a similar nature, such as all new-build or all refurbishment with similar scope, the results from the whole development can be apportioned on the basis of floor area to derive the figures upon which the separate developments will be assessed. Where the buildings are not similar, the design team will need to provide calculations to demonstrate that the waste has been apportioned as accurately as possible according to the project types.
21/11/16 Clarification added in relation to dissimilar projects on the same site.

National waste recovery rate – Error in the ASWL - KBCN0996

When the national waste recovery rate is unknown, the project team should assume that it is 50% by weight, according to CN3.4 in the BREEAM International NC 2016 manual. The value given in version 30.0 and previous versions of the ASWL refers to the BREEAM International NC 2013 and RFO 2015.
The value has been corrected in ASWL version 31.

Off-site waste sorting - KBCN0696

Where a building's recyclable waste is sorted off-site, BREEAM requirements relating to segregation of recyclable waste need not be met. In such cases, the assessor should provide evidence of the following:
  1. That a waste management plan is in place which provides adequate storage for the frequency of collection
  2. That the space could reasonably be converted to comply with all BREEAM waste storage requirements if required
  3. That an on-going co-mingled waste recycling contract is in place
  4. The typical recycling rates from the waste management company
BREEAM assesses the sustainability of the building itself rather than the management practices of the current occupier. 
16/04/18 Wording clarified.

Operational waste requirement for catering – applicability - KBCN1162

The additional operational waste storage requirement for developments which include catering is generally only applicable where a commercial scale kitchen is present. Where the design team can justify that there will be no significant waste streams from a modest facility, such as a small cafe, selling only drinks and pre-prepared snacks, the additional waste storage area identified in the default values does not need to be provided to meet compliance.

Operational waste storage sizing - KBCN0560

The dedicated space requirements given in the technical manual are default guidance, for situations where it is not possible to demonstrate the required size based on known waste streams. Compliance can, therefore, be achieved provided that it is clearly demonstrated and evidenced that there is adequate justification for the type of facilities & size of waste storage provided, and that the assessor is satisfied that the sizes and facilities meet the criteria based on the building type, occupancy and the likely waste volumes generated as a result of these.

Pre-demolition audit & diversion of resources from landfill - KBCN00025

There is currently no requirement to carry out a pre-demolition audit to allow the award of the credit for diversion of resources from landfill.

Pre-demolition audit – demolition in a later phase - KBCN1012

Where the demolition of an existing building forms part of the works to enable the assessed development, a pre-demolition audit must be carried out to comply with the criteria, even if the demolition occurs as part of a later phase.
28/02/2018 Wording amended for clarity

Pre-demolition audit/(pre-refurbishment) on other structures and hard surfaces - KBCN00045

A pre-demolition/(pre-refurbishment) audit is required where any existing buildings, structures or hard surfaces are present on a development site. The intent of the pre-demolition/(pre-refurbishment) audit is to ensure that any potentially useful materials are considered for re-use or diversion from landfill, not just materials resulting from buildings. 
22.11.17 Reference added to the pre-refurbishment audit for RFO assessments.

Pre-demolition/(pre-refurbishment) audit requirement - KBCN0243

Where the site demolition/clearance does not form part of the principal contractor’s works, but has been undertaken by the developer for the purposes of enabling the assessed development, a pre-demolition/pre-refurbishment audit must be carried out and referenced within the SWMP as per the guidance. Where justification and robust evidence can be provided, the following exceptions may apply:   This requirement seeks to encourage good practice by developers and design teams in relation to previously developed sites.
11/12/2019 Additional exception added to align with KBCN1257 and guidance re-structured for clarity
22 11 2017 Reference added to the pre-refurbishment audit for RFO assessments.
15 11 2017 Wording amended for clarity

Proposing national best practice guidance on defining granular fill and capping as a high grade use - KBCN1138

Recycled aggregates used for granular fill and capping can only be considered ‘high grade’ if they:
  1. conform to specifications in national best practice guidance (refer to the ASWL).
  2. OR, where there is no national best practice guidance approved, new guidance can be proposed to BRE for approval:
    • Specifications in national best practice guidance must include as a minimum, limits and requirements on the properties listed in Checklist A6.
    • Specifications must be specifically for recycled aggregate for use as granular fill or capping.
    • National best practice guidance is not required to cover test methodologies.
  3. OR, alternatively, the UK standard ‘Specification for Highway Works (SHW) Series 600 Earthworks’ and classifications as listed in the relevant definition section of the UK NC 2014 manual can be used.
If none of these apply, the recycled aggregates should be considered ‘low grade’ and excluded from the assessment of the Issue.

Recycled aggregate evidence prior to contractor’s appointment - KBCN0231

If the contractor has not been appointed at the time of submitting the Design Stage assessment, whilst it is imperative for the design team to demonstrate a firm commitment to meet the criteria and award the credit at this stage, a letter from the design team or developer to confirm that no contractor has been appointed should be submitted in lieu of the stated letter of confirmation. This should also be clarified in the Assessment Report. BREEAM recognises that it may not be desirable to confirm the specification, source and availability of a particular recycled aggregate for a project where the contractor has not been appointed yet. This would restrict the contractor's ability to source the most economically viable recycled aggregate to meet the BREEAM criteria.

Recycled aggregates in concrete - KBCN0823

The relevant CN in the technical manual, which confirms that no concessions are given to the criteria, reads: ‘Where national building regulations limit the use of recycled aggregates in concrete (typically applicable to bound aggregate uses as listed), the onus for achieving this credit is on the unbound uses (please note that the total aggregate figure must still include the bound uses).’ To clarify, in the calculation, the percentage of recycled aggregates in both bound and unbound uses can be considered against the total high grade use for the project.  
Technical manual to be updated accordingly in next reissue.
 

Residential institutions – short term stay - KBCN0811

The additional criteria for Residential institutions are not applicable to Residential institutions - short term stay.  

Solid concrete washout - KBCN00063

Solid concrete washout waste should be included in the waste resource efficiency benchmarks.  

Speculative finishes – multiple residential developments – fully-fitted - KBCN1448

Where fully-fitted multiple residential units are developed exclusively for the rental market, compliance for this Issue can be achieved where it is demonstrated that the tenancy agreement to be implemented stipulates that the finishes cannot be replaced by the tenant.

Speculative office including floor finishes/suspended ceiling - KBCN0259

The requirements can still be met where a speculative development includes the installation of floor finishes/suspended ceilings provided a Lease Agreement will be implemented to confirm that tenants are not permitted to remove these finishes. BREEAM recognises that incoming tenants may need to adapt ceiling or floor finishes to suit the requirements of their fit-out. Therefore, where these finishes are installed throughout, in line with Criterion 2, the following applies: A tenancy agreement, applied to the first tenancy, should stipulate that floor or ceiling finishes may only be modified where necessary, for example, to accommodate new partitions, lighting or other services, to replace worn or damaged components or to replace small, localised areas with a specialist floor or ceiling to account for abnormal conditions, such as wet areas. Documentary evidence of this must be provided as evidence for the credit to be awarded.
18/04/2017 KBCN made applicable to NC 2016 and IRFO 2015  
05/07/2018 Paragraph added to clarify the requirements of the tenancy agreement
27 Jul 2021 Clarified that the terms of paragraph 2 apply also to floor finishes

Suitability of waste storage facilities - KBCN0186

In situations where direct vehicular access to the recyclable waste store is limited by logistics or if size is a problem, for example inner city locations, some flexibility to the application of the criteria is allowed. The assessor can use their judgement on whether the storage space is appropriately sized and if the distance and changes in level via lifts or steps are acceptable. Convenience, H&S issues and the volume and type of waste likely to be generated must be considered.  Where the assessor deems the arrangement to be satisfactory this would be acceptable. Typically ‘accessible’ is defined as being within 20m of a building entrance. In some circumstances site restrictions or tenancy arrangements could mean it is not possible for the facilities to be within 20m of a building entrance. If, in the opinion of the BREEAM assessor it is not feasible for the facilities to be within 20m of a building entrance, their judgement can be used to determine if the facility is deemed to be ‘accessible’ to the building occupants and for vehicle collection.

Using BRE SMARTWaste tool - KBCN0236

BRE SMARTWaste may be helpful in demonstrating the construction waste benchmarks; however its use is not compulsory to achieve the credits. Reference to the SMARTWaste tool has been included in the issue as an example of a tool that can be used to manage and monitor waste generated during construction.  

Waste management practices - KBCN0247

16/04/2018 This compliance note is no longer valid as it does not fully explain how to approach this Issue. Please refer to the technical guidance and other compliance notes, such as KBCN0696, which deals with co-mingled recyclable waste. The requirement to provide a dedicated space for the segregation and storage of operational recyclable waste, as well as relevant facilities (e.g. for large amounts of packaging and/or compostible waste), relates to the building, not the occupier or the local authorities. A dedicated space and facilities must be provided irrespective of the waste management practices of the relevant stakeholders. The BREEAM certification relates to the building, not the occupier's or the local authorities' waste management practices. Therefore, the provision of a dedicated space and the relevant facilities is required to ensure the building's operational recyclable waste streams is diverted from landfill.
22/02/2017 Amended to include facilities (in addition to dedicated spaces)

Waste storage provision for catering - KBCN0755

As the manual states, the additional 2m2 per 1000 m2 of waste storage area provided for catering is measured against the "net floor area where catering is provided" and NOT the floor area of the catering facility. Generally, a catering facility will serve building users throughout the building. If it can be demonstrated that this is not the case, for example if part of the development is subject to a separate tenancy, not served by the catering facility, the area calculation can be adjusted accordingly. Where the net floor area is not indicative of the actual occupancy, the default values may not be appropriate. In such cases, the predicted waste streams should be calculated based on the actual occupancy and waste streams generated. This requirement accounts for the increase in waste produced by building based on the likely number of building users served by the catering facility. Please note that these default calculations are only intended for use where it is not possible to determine accurately what provision should be made based on predicted waste streams. 
15 06 2017 Wording updated to clarify

Water outlet - KBCN0824

A water outlet referred to in criterion 3.c is meant to be any device able to supply water (tap, faucet, hose, etc.)
Information correct as of 26thOctober 2021. Please see kb.breeam.com for the latest compliance information.