New Construction / UK / 2018 / 08 Land Use and Ecology /

LE 02 - Identifying and understanding risks and opportunities for the project

Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.

Determining ecological outcomes – criteria not met - KBCN1457

The 'determining ecological outcomes' criteria in both routes 1 and 2 have a major impact on achieving the rest of the credits in the Land Use and Ecology category. The dependency maps below show what potential effect this has on the assessment when this criteria is not achieved. Determining ecological outcomes rev 0.0

Ecological risk evaluation checklist – Assessment Route 2 - KBCN1113

Where assessment route 2 is chosen, regardless of the outcome of the Ecological risk evaluation checklist, the checklist does not need to be completed. The intent of the checklist is to understand the ecological risks associated with the site, and to confirm if assessment route 1 is appropriate for the site.

Ecology dependency diagrams - KBCN1456

These dependency diagrams show how ecology prerequisites and credits interact across issues in the ecology category. UK New Construction UK NC ecology dependencies rev 0.0 Applies to: Home Quality Mark HQM V6 ecology dependencies rev 0.0 Applies to:
30-Aug-2023 - HQM ecology dependency diagram added. Title and scheme applicability updated.

Exemplary level criteria – Shell only assessments - KBCN1511

Criterion 10c requires the credit for Pol 05 to be achieved. For shell only assessments, where Issue Pol 05 is filtered out, this requirement does not apply.

Exemplary level criteria – Wider site sustainability – Pol 03 requirements - KBCN1539

Criterion 10.b. is intended to be read as follows: Pol 03 Flood and surface water management - Achieve ALL credits for 'Surface water run-off' and 'Minimising watercourse pollution'
Technical manual to be updated accordingly in next reissue.

Guidance Note 35 withdrawn - KBCN1355

Guidance Note 35 has been withdrawn following the publication of v3.0 of the BREEAM UK New Construction 2018 Technical manual.  This manual reissue includes all of the information contained in this guidance note in a revised form and supersedes the GN content.  As such the GN should not be used for assessment purposes and it has been archived.  A copy can be downloaded if required for archive purposes only. Please see KBCN1221 regarding the original Guidance Note 35.

Guidance Note 40 to be updated - KBCN1356

Following the publication of v3.0 of the BREEAM UK New Construction 2018 Technical manual, the wording in Guidance Note 40 differs to some degree from that in the manual.  However, the underlying content is the same and the form may still be used to provide evidence for assessments.  Alternatively, it may be used to guide the preparation of evidence in a different format if preferred.  This GN will be updated to fully correspond to the wording in the reissued manual. Please see KBCN1190 regarding the purpose and scope of Guidance Note 40.

Methodology items to consider – Land use and ecology - KBCN1264

The methodology section provides a list of considerations for several credits, for example, a list of possible stakeholders and a list of items to be included as part of the survey and evaluation. The items in these lists can be applied flexibly, therefore if they are not deemed appropriate or relevant to the site by a Suitably Qualified Ecologist (or project team member if using route 1), they do not need to be included or referred to in the report. The items should be used as a basis for ensuring the delivery of the required outcomes, by ensuring all relevant aspects have been considered.

Optimal Ecological Outcome - KBCN1265

The optimal ecological outcome for a site can be defined as a solution that both, provides maximum benefit to the ecology, whilst accounting for other priorities for the development. This may result in several options/iterations and the most favourable option selected and justified, taking account of all site-specific considerations (for example scale, scope, size and any other priorities).

Recognised local ecological expertise - KBCN1193

Organisations/individuals that have the expertise to provide specialist input or guidance to inform the adoption of locally relevant (within the zone of influence) ecological measures that enhance the ecological value of the site.  This may include bodies such as: a. Local Government and other statutory relevant organisations. b. Local community groups, organisations, or charities, such as the Wildlife Trusts. c. Local, regional, or national fauna focused groups such as Bug life, RSPB, Bat Conservation Trust etc.
This definition will be added to the relevant technical manuals in their next re-issue.

Relating green roofs to multiple assessments in the same building - KBCN1195

A green roof on top of such buildings can be used to award credits for each assessment for which the Land use and ecology Issues apply. The benefit can be applied to to all assessments undertaken for the building provided all are completed within the appropriate time-frame of a valid ecological survey.

Risk to Ecologist’s safety - KBCN0704

In some situations a significant safety risk may prevent a suitably qualified ecologist from attending the site to undertake a site survey. In these cases a desktop study can be used to demonstrate compliance, where the ecologist confirms that it is an acceptably robust substitute. In these cases, the assessor must provide evidence to confirm the type of significant safety risk present.  

Site clearance prior to purchase of the site - KBCN1197

For sites cleared prior to purchase of the site and less than five years before assessment, a Suitably Qualified Ecologist should estimate the site’s ecological value immediately prior to clearance using available desktop information (including aerial photography) and the landscape type/area surrounding the site. Where it is not possible for the ecologists to determine ecological value of the site prior to site clearance, i.e. where there is no evidence to determine compliance, the credits must be withheld. For sites cleared more than five years ago, the ecological value of the site must be based on the current situation, on the basis that, within five years, ecological features would have started to re-establish and this is, therefore, representative of the site’s ecological value prior to development.

Site wide approach to ecological enhancements - KBCN1194

A site-wide approach to ecological enhancements can be used on sites where multiple buildings share areas of soft landscaping. The enhancement benefits are applied to the individual building assessments within the site. The benefit can be applied on a site-wide basis provided all developments are completed within the appropriate timeframe of a valid ecological survey.

Suitably Qualified Ecologist – Other recognised organisations - KBCN0192

With regards to the definition of a Suitably Qualified Ecologist, in addition to the organisations already listed within the manual, full members of the following organisations are also deemed SQE's; Provided the individual meets all other requirements as outlined in the definition of a Suitably Qualified Ecologist (SQE).

Suitably Qualified Ecologist – Professional membership - KBCN0743

With reference to the definition provided in the technical guidance, where requirements 1 and 2 are met, full members of the named organisations can be considered as a SQE for BREEAM on the basis of their membership. Those who meet requirements 1 and 2 who are not full members may be considered, however the assessor must ensure, and be able to demonstrate, that the ecologist is covered by a professional code of conduct, subject to peer review and that their expertise and experience is appropriate for the assessed project.

Targeting ecology issues using a mixture of routes - KBCN1306

Where Route 1 is pursued initially and it is subsequently decided that Route 2 should be followed, the Suitably Qualified Ecologist appointed should review all evidence available for the issues already assessed to confirm the actions taken were appropriate. Note: Route 1 and Route 2 are referred to as the 'Foundation' and 'Comprehensive' routes in HQM ONE, respectively.  

Timing of Ecological survey/report - KBCN0292

If the ecologist's site survey and/or report is completed at a later stage than required, the assessor would need to be satisfied that it was produced early enough for the recommendations to influence the Concept Design/design brief stage and leads to a positive outcome in terms of protection and enhancement of site ecology.
21/02/2017 Wording clarified.

Timing of Ecological survey/report - KBCN0292

If the ecologist's site survey and/or report is completed at a later stage than required, the assessor would need to be satisfied that it was produced early enough for the recommendations to influence the Concept Design/design brief stage and leads to a positive outcome in terms of protection and enhancement of site ecology.
21/02/2017 Wording clarified.

Verification of an ecology report / information - KBCN1192

If the appointed ecologist does not meet the definition of a ‘suitably qualified ecologist’ (SQE) the report / information submitted to support the assessment must be verified by an individual who does. 1. The individual verifying the report must provide written confirmation that they comply with the definition of a ‘suitably qualified ecologist’. 2. The verifier must provide signed confirmation that they have checked and approved the report. This must clearly reference the report and can be in the form of a signed letter or their printed name and signature on a completed pro-forma. In doing so, they are deemed to confirm that the report: a. represents sound industry practice b. is correctly, truthful, and objective c. is appropriate given the local site conditions and scope of works proposed d. avoids invalid, biased, or exaggerated statements Such confirmation from the verifier must be provided in addition to all other information required by the relevant technical manual and referenced as part of the evidence submitted to demonstrate compliance. It can take a number of years for an ecologist to meet the SQE definition. Verification of information by an existing SQE supports the practical application of the assessment criteria and is in line with industry practice.
13/08/2019 Updated to clarify, in practical terms, what evidence of verification will be considered acceptable.
 
Information correct as of 29thMarch 2024. Please see kb.breeam.com for the latest compliance information.