29 Construction Energy Use & 30 Construction Water Use -Methodology

Criterion 3 in both of the above categories states that the meter reading and reporting should be done on a weekly basis however, in step 2 of the Water monitoring and reporting methodology it states:-

Check the frequency of monitoring the contractor wishes to maintain throughout the project to ascertain eligibility for crit 3 above.”

What this means, is that whichever frequency of monitoring and reporting the contractor wishes to do for the duration of the project, to be eligible for crit 3, they have to be made aware that weekly monitoring and reporting is required to obtain crit 3 credits. This will be required to be shown as evidence.