Ene 02 – Criterion 5 incorporated into Criterion 4

To clarify the intent, criteria 4 and 5 should be read as a single criterion, as follows:

 

4. Monitor a significant majority of the energy supply using:

4.1 An accessible energy monitoring and management system

OR

4.2 Separate accessible energy sub-meters with pulsed or other open protocol communication outputs for future connection to an energy monitoring and management system

for:

a. each tenancy area – in multi-tenanted assets

OR

b. relevant function areas or departments – in single occupancy assets

OR

c. each floorplate – in large single occupancy or single-tenancy assets with one homogeneous function, such as hotel bedrooms or offices

 

This will be updated in the relevant technical manuals at the next reissue