Where it is confirmed by an appropriate project team member that it is not possible to fully meet the leak detection criteria for fire hydrants or sprinklers, an alternative approach can be implemented for these systems.
This must demonstrably meet the aim of the issue by detecting and alerting the building management to major water leaks.
Previous guidance – superseded on 30 May 2024
To meet BREEAM compliance, emergency systems such as fire hydrants and sprinklers need also to be covered by a leak detection system.
The leak detection system must cover all mains water supply between and within the building and the ‘site boundary’.
11 Sep 2024 - Applicability to BIU V6 confirmed - QN-75509-C8H8V1 30 May 2024 - New guidance introduced to clarify that BREEAM compliance should not compromise the operation of building safety-critical systems. Applicability to NC V6 standards confirmed.