Erratum – up to v1.2 – timing of pre-requisite – indoor air quality plan

In Issues 1.0 and 1.2 of the technical manual, the prerequisite requires the Indoor air quality plan to be produced no later than the end of Concept Design.

 Clarification of the requirements in Hea 02:

The prerequisite currently states:

‘1. A site-specific indoor air quality plan has been produced and implemented in accordance with the guidance in Guidance Note GN06. The plan must be produced no later than the end of Concept Design. The objective of the plan is to facilitate a process that leads to design, specification and installation decisions and actions that minimise indoor air pollution during occupation of the building…’

Clarified criterion:

‘1 A site-specific indoor air quality plan has been produced and implemented in accordance with the guidance in Guidance Note GN06. The objective of the plan is to facilitate a process that leads to design, specification and installation decisions and actions, which minimise indoor air pollution during occupation of the building…:’

12-Oct-2022 Title amended for clarity.
This will be confirmed in the next re-issue of the technical manual, but can be applied immediately in all issues of the UK NC2018 scheme.