If a Quantity Surveyor (QS) changes during a project, the new QS must demonstrate that subsequent criteria are met in order to gain the 2nd and 3rd credits. While the initial modelling data may not be available, the results and outputs given to the client team will be and can be used to remodel the LCC at the later stages of development using the new QS’s data. Provided the new QS can model and determine the best option based on the latest project information, the 2nd and 3rd credits can still be attained.
It may be necessary to repeat modelling where there has been a change of QS however, provided the intent of the issue and criteria are met, the credits can still be awarded.