Prediction of operational energy consumption – passive design analysis

The credits for ‘Prediction of operational energy consumption’ in Ene 01 require the project team to have first identified opportunities to implement passive design measures.

For Ene 01, it is acceptable for the analysis of potential passive design measures to be completed later than Concept Design if there are still opportunities to implement passive design measures in the project.

The intention of including the criterion on passive design analysis in Ene 01 is to ensure passive design features that could reduce the operational energy demand of the building have been considered before credits are awarded for predicting operational energy demand. The analysis must occur when there are still opportunities to influence the design.