New Construction / UK / V6 /
06 Materials
Information correct as of 13thOctober 2024. Please see kb.breeam.com for the latest compliance information.
Building LCA – Scope when a BREEAM Assessment covers only part of the new building design - KBCN1172
To give reliable results, building LCA must capture the interactions that occur across an entire design (the system). A design decision in one part of the design will, in many cases, cause knock-on effects to other parts of the design. If only part of a building being designed is included in the building LCA the designer may choose a design option that optimises environmental impacts for the limited part analysed, but will be unaware of potential detrimental effects to the overall environmental impact of the building.
In addition, if a building LCA only includes the construction products that form the BREEAM assessment area, inconsistencies arise with regards to construction products that serve all areas of the building in common. For example, an assessment on a central floor that excludes the roof, compared with an assessment on the (otherwise identical) top floor that does include the roof. This approach would be unfair.
Therefore, the building LCA scope should normally include the whole building design (as defined in Mat 01, ‘Scope of assessment’) even if the area covered by the BREEAM assessment scope is only part of the building.
However, where in the opinion of the BREEAM Assessor this is not reasonable, it is acceptable for the building LCA scope to match the BREEAM assessment scope. Examples where this may be the case include newly-constructed, mixed-use buildings (where the different use zones are assessed under different schemes or some are not being assessed at all) and part new-build part refurbishment projects.
Where this is the case:-
- Comparison with the BREEAM benchmark cannot be done, only options appraisal.
- Only include construction elements/components that are both:
Within or forming the boundary of the BREEAM assessment scope.
Predominantly the responsibility of the project team undertaking the building LCA work.
Note: Based on the above conditions, if no construction elements/components are included, or what is included is too limited to have significantly different options to appraise, then credits cannot be awarded.
- In the BREEAM Mat 01/02 Results Submission Tool:
Select ‘Other’ for the ‘BREEAM assessment building use type’ (note: ‘mixed-use’ should only be entered for mixed-use buildings where the whole building is included in the building LCA scope).
For ‘Functional quantity…’, enter the value corresponding to the scope included in the building LCA.
Include the following text in cell C10 of the ‘DifferencesID2,3,4’ sheet: “The scope of this building LCA work matches the BREEAM assessment scope, which covers only part of a building being newly constructed/refurbished. Of the areas being newly constructed/refurbished, the building use type(s) of the areas included in the building LCA scope are [insert use type(s)] and the building use type(s) of the areas excluded are [insert use type(s)]. The Functional quantity of the areas excluded are [insert value]”.
06-Mar-2024 - Scheme applicability updated to UK NC V6.
01-Dec-2020 - Clarification to previous update added.
27-Nov-2020 - Exceptions paragraph added.
06-Dec-2019 - Scope of KBCN clarified.
Building LCA – similar buildings approach - KBCN1459
If multiple buildings share an
identical design, as per
KBCN1226, the one set of LCA evidence can be submitted for (where pursued) the superstructure and core buildings services criteria for each identical building.
Where buildings are
similar, but not identical the following applies.
Level of variation
- For <10% variation in LCA results between the buildings, submit the Mat 01/02 calculator for only the worst performing design.
However, results for all buildings must be included in the LCA report.
- For ≥10% variation in LCA results submit the Mat 01/02 calculator for every building. See below:
Tool submission
Separate submissions are carried out in BREEAM Projects:
- Upload one zip file per building.
Each zip file will contain all required files as if for individual assessments. Clearly identify each building (e.g. the filename should contain 'Building A', 'Building B' etc).
- Identify the worst performing building.
By adding ‘_Worst Performing’ to the end of the filename.
Evidence submission
Separate and specific building LCA evidence for each building must be submitted for (where pursued):
- The superstructure and core buildings services criteria.
- The substructure and hard landscaping criteria.
These aspects will almost always vary irrespective of identical superstructure and core building services design.
Refer to the technical manual and relevant KBCNs on how to assign hard landscaping to each building on a shared site.
For options appraisals, common evidence covering all similar buildings can be used. There is no requirement for different design options for each building, although this can still be done if this brings value to the project.
04-Oct-2023 - Title and layout updated for clarity and consistency. Scheme applicability updated.
16-Nov-2021 - Revised and re-published.
Building LCA – evidence requirements for multiple assessments with identical designs - KBCN1226
Superstructure + core building services
Where an
identical superstructure design and / or
identical core building services design is used for multiple buildings, the same building LCA evidence may be submitted for all these assessments.
The following shall be identical:
- Products specified and quantities installed.
- Transport of the products to the site (10km variation in transport distance to site is acceptable).
- In-use assumptions (e.g. maintenance, service lives of products).
- End-of-life assumptions.
Substructure and hard landscaping
It is unlikely that the same substructure and hard landscaping design will apply to more than one building due to variations in ground conditions and site layout.
Therefore, it is not acceptable for the same substructure / hard landscaping LCA evidence to be submitted for this criteria for more than one assessment.
Similar buildings approach
If the LCA(s) are part of a similar buildings assessment, please also see
KBCN1459.
04-Oct-2023 - Link to KBCN1459 added. Scheme applicability updated. KBCN layout adjusted for clarity.
Building LCA – no significantly different superstructure options - KBCN1672
Mat 01 requires multiple significantly different superstructure options at both concept and technical design stage.
Sometimes due to project, cost, or client requirements it is not possible to produce viable options that are significantly different.
In these cases, multiple options are still required in line with the criteria but are not required to meet the definition of significantly different as defined in the methodology.
Regardless of this, design teams must aim to provide meaningfully different design or specification options that still offer viable alternative outcomes for the project, its life cycle impact, and life cycle costing (where this credit is targeted).
Any restrictions which limit the possible options must be justified for the QA submission.
Erratum – 2018 to V6 – scope – external doors - KBCN1651
The scope of this issue includes external doors.
Currently, external doors are missing from the Mat 03 scope 'internal finishes'.
This will be corrected in future versions.
FSC and PEFC Mixed Sources certified timber - KBCN00091
Products labelled:
- FSC Mix or
- PEFC Mixed Sources
Meet the BREEAM responsible sourcing requirements. This means any such products:
- In HQM, and in BREEAM NC 2016 or older schemes: meet the prerequisite for legally harvested and traded timber.
- In BREEAM NC 2018 or newer schemes: meet the prerequisite for legal and sustainable timber.
- In all schemes: can be used to demonstrate responsible sourcing.
Products carrying the FSC Mix label contain at least 70% FSC certified and recycled material. These products may contain a small proportion of FSC Controlled Wood (KBCN00054). However for BREEAM compliance, the FSC Mix label is sufficient to meet our requirements.
14-Mar-2024 - Wording clarified and expanded. Relevant prerequisites and requirements clarified. Scheme applicability updated.
FSC Controlled Wood - KBCN00054
The
FSC Controlled Wood label minimises the risk that wood comes from illegal or controversial sources, however it does not eliminate this risk.
Therefore, products which are:
- Labelled as FSC Controlled Wood or,
- Where the majority of material in a product is comprised of FSC Controlled Wood,
Do not meet the BREEAM definition of responsibly sourced.
Where FSC Mix labelled products contain FSC Controlled Wood, see KBCN00091.
This means that any such products:
- In HQM, and in BREEAM NC 2016 or older schemes: do not meet the prerequisite for legally harvested and traded timber.
- In BREEAM NC 2018 or newer schemes: do not meet the prerequisite for legal and sustainable timber.
- In all schemes: cannot be used to demonstrate responsible sourcing.
14-Mar-2024 - Wording clarified and expanded. Relevant prerequisites and requirements clarified. Scheme applicability updated.
Responsible sourcing certification – validity - KBCN1693
Where it can be demonstrated that the responsible sourcing certificates were valid either at the time of specification, or at the time of purchase, they may contribute to the awarding of the credits.
BREEAM is primarily trying to encourage designers to take responsible sourcing into consideration when specifying or selecting products and as such it is not necessary for certification to be valid at the time of design or post-construction stage submissions.
Sustainable procurement plan – timing - KBCN1659
Where a sustainable procurement plan is not in place before Concept Design (as required in the criteria), the credit can still be achieved if:
- A sustainable procurement plan is in place before the end of Concept Design.
- The assessor justifies that the later timing has not compromised the ability of the plan to guide specification and procurement activities.
Third-party verification – Timing - KBCN1603
The third-party LCA verification requirements for concept and technical design stages do not need to be completed at a specific project stage.
It is, for example, acceptable for these to be verified as a single exercise, following technical design stage.
Information correct as of 13thOctober 2024. Please see kb.breeam.com for the latest compliance information.